BUILDING STRONG
Trusted Partners Delivering Value Today for a Better Tomorrow1 As of:
POC:
Pre-Proposal Teleconference
Design Build Contract Design Build Contract for Miscellaneous Roof Repairs and
Replacement for the U.S. Virgin Islands National Guard (VING) Within
St. Croix and St. Thomas, U.S. Virgin Islands
Solicitation # W912EP18R0040
Date: July 9, 2018
Time: 2:00 PM EST
Call in number: 877-402-9753, Access/Participant code is 4696035, and Password is 1234
9 JUL18
J. House
Trusted Partners Delivering Value Today for a Better Tomorrow2 As of:
POC:
AGENDA
Welcome and Introductions (Roll Call)
Administrative Items
Design Build for VING Roof Repairs and Replacement – Overview
Statement of Work
Overview of USACE Selection Procedures
Selection Criteria
Small Business
Questions
Trusted Partners Delivering Value Today for a Better Tomorrow3 As of:
POC:
Administrative Items
Introductions and Roll Call
Phones Muted, unless taking speaking or asking questions
Questions will be allowed:
► General questions OK
► Technical questions
• OK if yes/no
► Otherwise submit questions via Bidder Inquiry in ProjNet
► Slides and roster will be posted
9 JUL 18
Trusted Partners Delivering Value Today for a Better Tomorrow4 As of:
POC:
Design Build for VING Roof Repairs and
Replacement Projects
Cavaughn Benjamin
USACE SAJ
Engineering Technical Lead
Trusted Partners Delivering Value Today for a Better Tomorrow5 As of:
POC:
Design Build for VING Roof Repairs and
Replacement Projects
► The Virgin Island Army National Guard (VING) facilities are located on the islands of St. Croix and St. Thomas. The work includes all design, permitting, and construction required to deliver the renovated areas complete and usable for multiple facilities. The areas of the buildings range from 45, 000 SF to 50,000 SF.
NAZARETH: SFC Leonard B. Francis Armory– STT:
► Field Maintenance Shop (FMS) #2– STT
► Control Humidity Preservation (CHP) Building repairs – STT
► Readiness Center Roof repairs & Interior remodel – STT
Sprat Hall Military Compound- STX
Army Aviation Operating Facility - STX
BETHLEHEM: LTC L.A. Jackson Armory- STX:
► USPFO office and warehouse - STX
► Access Control Facility – STX
► General Instruction building RTI – STX
► Readiness Center –STX
► Period of Performance: Total of 730 calendar days after receipt of NTP
Trusted Partners Delivering Value Today for a Better Tomorrow6 As of:
POC:
Project Locations – St. Thomas
Trusted Partners Delivering Value Today for a Better Tomorrow7 As of:
POC:
Project Locations – St. Thomas – Nazareth
SPC Leonard B. Francis Armory
Trusted Partners Delivering Value Today for a Better Tomorrow8 As of:
POC:
Project Locations – St. Croix
Trusted Partners Delivering Value Today for a Better Tomorrow9 As of:
POC:
Project Locations – St. Croix –
Sprat Hall Military Compound
Trusted Partners Delivering Value Today for a Better Tomorrow10 As of:
POC:
Project Locations – St. Croix –
Army Aviation Operating Facility
Trusted Partners Delivering Value Today for a Better Tomorrow11 As of:
POC:
Project Locations – St. Croix – Bethlehem
LTC L.A. Jackson Armory
Trusted Partners Delivering Value Today for a Better Tomorrow12 As of:
POC:
Design Build for VING Roof Repairs and
Replacement Projects – Scope of Work
• The work entails demolition, lawful disposal, and replacement of the existing metal and modified bitumen roofing systems, flashing, roof vents and drains, gutters, downspouts, overhead doors, hangar doors, man-doors, windows, interior and exterior renovations, HVAC and plumbing systems, electrical systems, fire alarm systems, and other associated activities. Note that the project shall be phased for renovations to buildings located on the island of St. Thomas to be the first priority.
• The Contractor shall be responsible for the full design and construction of the replacement and renovations to roofs and various other building maintenance for various buildings. All aspects of the design shall be signed and sealed by a
Registered Professional Architect, Registered Professional Engineer, or other registered professional licensed. Fast tracking of the design is not required.
• Section 01 33 16 DESIGN AFTER AWARD contains additional requirements for the
Design and Construction submittals. All roof coverings and openings, including but not limited to overhead and personnel doors, repaired or replaced under this contract are required to meet High Velocity Wind Zone (HVWZ) requirements for 174 mph velocities. All designs are required to be accepted by the Government prior to commencing construction.
Trusted Partners Delivering Value Today for a Better Tomorrow13 As of:
POC:
Overview of Selection Procedures
Susan Forchette
USACE SAJ
Contracting Officer
Trusted Partners Delivering Value Today for a Better Tomorrow14 As of:
POC:
Overview of Selection Procedures
► Phase I Request For Proposals – Performance Capability ► Technical Merit
► Past Performance
► Phase II Request for Proposals ► Based on Design Technical/Schedule
► Small Business Participation
► Price
Trusted Partners Delivering Value Today for a Better Tomorrow15 As of:
POC:
Overview of Selection Procedures
► Source Selection Evaluation Board
Two (2) phase design build procedures authorized by 10 U.S.C 2305a. and 41 U.S.C. 3309 in conjunction with FAR Part 15 negotiation procedures will be utilized for the award.
• This preproposal conference will discuss the criteria for Phase 1
Strict adherence to selection criteria
Entire package is reviewed by all members of the Board
Board determine most highly qualified firms
Up to 5 firms will be selected to submit proposals for Phase 2
Notifications sent to all applicants
Debriefings
Trusted Partners Delivering Value Today for a Better Tomorrow16 As of:
POC:
Selection Criteria
► Phase I Proposal Selection Criteria
Factor 1 - Technical Merit Sub-factor 1 - Specialized Experience
Roofing Construction
Roof Replacement/Installation
Sub-factor 2 - Organization and Technical Approach Key Project Personnel Capabilities and Experience
Quality Control
Sub-factor 3 - Remaining Performance Capability
Factor 2 - Past Performance Relevant to scope of this effo0rt
Performance on previous projects – CPARS and Questionnaire
► Submission by 4 pm on July 25th;
Volume 1- Technical Package (Original plus 4 Copies)
Volume 2– Past Performance Package (1 Original and 2 Copies). Each copy shall be separately bound.
One (1) cd containing an electronic version of all the proposed documents.
Trusted Partners Delivering Value Today for a Better Tomorrow17 As of:
POC:
Overview of Selection Procedures
Beth Myers
USACE SAJ
Deputy of Small Business
B. Myers
Trusted Partners Delivering Value Today for a Better Tomorrow18 As of:
POC:
Small Business Considerations
Small Business Participation Factor – Detailed Phase II
Used in Unrestricted – Best Value Procurements
Applies to all offerors (both large and small businesses)
Shall submit Small Business Participation Proposal (SBPP) Phase II
Large Business concerns will also have to submit a Small Business
Subcontracting Plan – Addressed in Phase II
Trusted Partners Delivering Value Today for a Better Tomorrow19 As of:
POC:
LOOKING FOR OPPORTUNITIES
IN ALL THE RIGHT PLACES
System for Award Management www.sam.gov
Dynamic Small Business Search http://dsbs.sba.gov/dsbs/search/dsp_dsbs.cfm
SB firms keep profile current w/bonding, past performance, and capabilities
LB/prime contractors can use many filters to locate SDB, HUBZone, WOSB, SDVOSB specific firms and their location
FEDBIZOpps www.fbo.gov
SB firms register as an interested party for the solicitation
Trusted Partners Delivering Value Today for a Better Tomorrow20 As of:
POC:
SMALL BUSINESS
CONTACT INFORMATION
Beth Myers, Deputy for Small Business
(904) 232-1150 elizabeth.r.myers@usace.army.mil
Florida Procurement Technical Assistance Center http://www.fptac.org/contactus.htm
Jacksonville District WebPages www.saj.usace.army.mil
How do I contact Small Business?
FY2018 Forecast
Frequently Asked Questions
Trusted Partners Delivering Value Today for a Better Tomorrow21 As of:
POC:
Questions
► General questions OK
► Technical questions
• OK if yes/no
► Submit questions in writing via Bidders Inquiry on ProjNet
► Slides and roster will be posted to FBO