AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14.

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Herbert Hoover Dike Rehabilitation, Structure Replacements,S-265 (KI-2) and S-266 (KI-1) Reconstruction, Okeechobee County, Florida

See SF30 Continuation Sheet for a complete description of the changes.

The Proposal due date remains 21 June 2017 @ 3:00 PM EST.

All other conditions remain unchanged.

W912EP-17-R-0006 2 Amendment 0004

SF 30 CONTINUATION SHEET

Herbert Hoover Dike Rehabilitation, Structure Replacements, S-265 (KI-2) and S-266 (KI-1) Reconstruction, Okeechobee County, Florida

SUMMARY OF CHANGES

Volume 1 of 2 – Contract Documents:

SF1442 Block 11 Make a Pen and Ink change to change the calendar days from 30 calendar days to 63 calendar days.

Per Section 00700, DELETE FAR Clause 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) - ALTERNATE I (APR 1984) in it’s entirety and REPLACE with FAR Clause 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR

1984) - ALTERNATE I (APR 1984)

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -

ALTERNATE I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 63 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 1,451 days after the receipt of the Notice to Proceed + 90 days for sodding (for a total of 1,541 calendar days).

topmostSubform[0]:
Page1[0]:
IDCode[0]: J
Page[0]: 1
Pages[0]:
AmendNo[0]: 0004
EffDate[0]: June 8, 2017
ReqNo[0]:
ProjNo[0]:
IssCode[0]: W912EP
IssuedBy[0]: USA ENGINEER DISTRICT, JACKSONVILLE

CONTRACTING DIVISION

701 SAN MARCO BLVD

JACKSONVILLE, FL 32207-8175

AdmCode[0]:
AdminBy[0]: SEE ITEM 6
ContName[0]:
ContStrt[0]:
ContCnty[0]:
ContSt[0]:
ContZIP[0]:
Code[0]:
FacCode[0]:
SolChgYs[0]: Yes
SolChgNo[0]: Off
SolAmdNo[0]: W912EP-17-R-0006
AmendDate[0]: May 18, 2017
ModNo[0]:
ModDate[0]:
NoCopies[0]: 1
Amended[0]: Yes
OffrExt[0]: Off
OffrNoEx[0]: No
ApprData[0]:
ChgeOrd[0]: Off
ChgeOrder[0]:
Modify[0]: Off
SuppAgre[0]: Off
SuppAuth[0]:
ModOthr[0]: Off
OthrSpec[0]:
NoReq[0]: Off
Require[0]: Off
Copies[0]:
Descript[0]:
SignName[0]:
SignTitl[0]:
ContDate[0]:
CoName[0]:
CoTitle[0]:
CODate[0]:

File details come from the government source that posted it. Updated .