This is an amendment to a solicitation for the rehabilitation of miter gate hydraulic cylinders at the Peoria Lock and Dam. The scope of work requires the contractor to transport five miter gate cylinders and associated manifolds from the site, refurbish them at their facility, and return four cylinders by September 13th and the fifth by October 15th, 2020. The work includes disassembly, inspection, reconditioning of components, installation of new seals and coatings, and pressure testing. There are also options to replace manifolds with stainless steel and rehabilitate Tainter valve cylinders, with response deadlines extended to January 22nd, 2020. Pricing is provided for base and option items. The amendment includes responses to contractor questions, revised specifications and schedules, and photos of equipment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
96514793542477
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this amendment is to provide a revised Schedule of Prices, a revised Scope of Work (changes are provided in red font), provide Questions and Answ ers to industry and photos of the spare cylinder.
As a result of this amendment, the required response date/time has changed from 21-Jan-2020 02:00 PM to 22-Jan-2020 02:00 PM and the time for Questions and Answ ers has been extended to no later than 21 January 2019 at 12:00pm Central Time.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Jan-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK20T0028
X 9B. DATED (SEE ITEM 11)
09-Jan-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Jan-2020
CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
1500 ROCK ISLAND DRIVE
ROCK ISLAND IL 61201
W912EK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EK20T0028
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 21-Jan-2020 02:00 PM to 22-Jan-2020 02:00 PM.
MVR.03
QUESTION AND ANSWER
via email
Technical inquiries and questions relating to this solicitation are to be submitted to Jacob Toft at jacob.j.toft@usace.army.mil no later than 21 January 2019 at 12:00pm Central Time.
The following have been modified:
SCHEDULE OF PRICES
BASE BID
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT DELIVERY DATE
0001 Miter Gate Cylinder Rehab 4 EA $ $ 13-Sep-20
Miter Gate Cylinder Manifold Rehab
4 EA $ $ 13-Sep-20
0003 Miter Gate Cylinder Rehab 1 EA $ $ 15-Oct-20
Miter Gate Cylinder Manifold Rehab
1 EA $ $ 15-Oct-20
TOTAL OF BASE BID (ITEMS 0001 THRU 0004): $
OPTION ONE
Replace manifolds for all 5 Miter Gate Cylinders
5 EA $ $
TOTAL OF OPTION ONE (ITEMS 0101): $
The Government reserves the right to award Option One up to five weeks after date of Base Bid Award. Delivery date will remain the the same as Items 0001 & 0003.
OPTION TWO
Rehabilitate 1 of 5 Tainter Valve Hydraulic Cylinders.
1 EA $ $
TOTAL OF OPTION TWO (ITEMS 0201): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The Contractor will have 20 Weeks to complete the Option work from date of contract modification.
OPTION THREE
Rehabilitate 2 of 5 Tainter Valve Hydraulic Cylinders
1 EA $ $
TOTAL OF OPTION THREE (ITEMS 0301): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The Contractor will have 20 Weeks to complete the Option work from date of contract modification.
OPTION FOUR
Rehabilitate 3 of 5 Tainter Valve Hydraulic Cylinders
1 EA $ $
TOTAL OF OPTION FOUR (ITEMS 0401): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The Contractor will have 20 Weeks to complete the Option work from date of contract modification.
OPTION FIVE
Rehabilitate 4 of 5 Tainter Valve
TOTAL OF OPTION FIVE (ITEMS 0501): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The Contractor will have 20 Weeks to complete the Option work from date of contract modification.
OPTION SIX
Rehabilitate 5 of 5 Tainter Valve
TOTAL OF OPTION SIX (ITEMS 0601): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The Contractor will have 20 Weeks to complete the Option work from date of contract modification.
OPTION SEVEN
Replace manifold with SS manifold for Option 1 of 5 Hydraulic Valve Cylinder
EA
TOTAL OF OPTION SEVEN (ITEMS 0701): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The Contractor will have 19 weeks to complete the Option work from date of contract mod
OPTION EIGHT
for Option 2 of 5 Hydraulic Valve
TOTAL OF OPTION EIGHT (ITEMS 0801): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The Contractor will have 19 weeks to complete the Option work from date of contract mod.
OPTION NINE
for Option 3 of 5 Hydraulic Valve
TOTAL OF OPTION NINE (ITEMS 0901): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The
OPTION TEN
for Option 4 of 5 Hydraulic Valve
TOTAL OF OPTION TEN (ITEMS 1001): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The
OPTION ELEVEN
for Option 5 of 5 Hydraulic Valve
TOTAL OF OPTION ELEVEN (ITEMS 1101): $
The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. The Contractor will have 19 weeks to complete the Option work from date of contract mod.
TOTAL OF ALL OPTIONS (ITEMS 0101 THRU 1101): $
TOTAL OF ALL ITEMS BASE BID & ALL OPTIONS (ITEMS 0001 THRU 1101): $
SCOPE OF WORK
Peoria Lock Hydraulic Cylinder Repair
SOW
Background:
The U.S. Army Corps of Engineers (USACE) Rock Island District (MVR) has been coordinating temporary closures of five locks on the Illinois Waterway to address aging infrastructure needs.
Through cooperation with navigation industry and Illinois Waterway stakeholders, MVR developed a consolidated repair schedule, which includes a short closure to locks in 2020. The simultaneous closure of multiple locks will provide time for much needed critical repairs and maintenance while reducing impacts to navigation. The Peoria Lock will be closed to navigation from 6 July 2020 to 29 September 2020 at which time critical repairs are needed for the rehabilitation of the Peoria Lock and Dam Miter Gate Hydraulic Cylinders.
BASE BID (see schedule of prices for further details):
Miter Gate Hydraulic Cylinders - Five (5): The base bid consists of rehabilitating five (5) miter gate hydraulic cylinders. The existing hydraulic cylinder rods are ceramic coated, which has failed and is no longer authorized for use by USACE. The new laser cladding on cylinder rod must be able to be field welded/repaired. The Government will remove the five cylinders from the Lock and Dam no later than (NLT) 12 July 2020. All five cylinders will be ready the following day for shipment to the awarded contractor’s facility. The Government will load/unload the cylinders at the Government destination. The contractor is responsible for the means, method and expense of shipment to the contractor’s facility. Once shipped, the cylinders are to be refurbished in accordance with the specifications provided below in the SOW. Once work is completed, four of the five cylinders must be shipped back and onsite at Peoria Lock and Dam NLT 13 September 2020. The contractor is responsible for providing and loading a flatbed truck or similar for shipment to Illinois Waterway Project Office 257 Grant Street, Peoria, IL 61603 where the Government will be responsible for unloading. The fifth cylinder shall be shipped back and onsite at Peoria Lock and Dam NLT 15 October 2020. The contractor is responsible for providing and loading/unloading a flatbed truck or similar for shipment to Illinois Waterway Project Office 257 Grant Street, Peoria, IL 61603 where the Government will be responsible for unloading. FOB Destination is the Peoria Lock and Dam, IL. Contractor is responsible for safely shipping the cylinders and is responsible for any damages occurred during shipping.
OPTIONS (see schedule of prices for further details):
Stainless Steel Upgrade for Miter Gate Hydraulic Cylinder Manifolds (Option 1): Replace all five miter gate hydraulic cylinder manifolds with stainless steel. The Government reserves the right to exercise the stainless steel options within five (5) weeks of the date of contract award. The manifold shall be assembled to the hydraulic cylinder upon arrival.
Tainter Valve Hydraulic Cylinders - Five (5) (Options 2 – 6): Rehabilitate five (5) Tainter valve hydraulic cylinders. The Government reserves the right to exercise the option(s) for the Tainter valve hydraulic cylinders until 1 December 2020. If the option(s) to rehabilitate the Tainter valve hydraulic cylinders are awarded, the contractor shall have 20 weeks to complete the work from the date of the award.
Stainless Steel Upgrade for Tainter Valve Hydraulic Cylinders (Options 7 – 11): Replace Tainter valve hydraulic cylinder manifolds with stainless steel. The Government reserves the right to exercise the stainless steel option(s) until 1 December 2020. If the option(s) for the stainless steel upgrade are exercised, the contractor shall have 19 weeks to complete the work from the date of the award. The manifold shall be assembled to the hydraulic cylinder upon arrival.
Specifications: The hydraulic miter gate cylinders, Tainter valve hydraulic cylinders, and hydraulic manifolds are to be prepared for shipment by the U.S. Army Corps of Engineers, Illinois River Operations Division. The cylinder assemblies will be removed and loaded onto the contractor’s flatbed or similar for shipment. The contractor is then responsible for the cylinder assemblies and manifold blocks to be shipped to the contractor’s repair facility at the contractor’s expense. Once work is complete, the contractor is responsible for loading a flatbed truck or similar for shipment to Illinois Waterway Project Office 257 Grant Street, Peoria, IL 61603.
The following items, but not limited to, are to be included in an inspection report with photographic evidence and detailed description of components condition and any components that are outside their allowable tolerances.
Original Manufacturer: Bosch Rexroth Corporation
MG Cylinder TV Cylinder
Bore 11.024 in 11.024 in
Rod Dia. 8.661 in 5.511 in
Stroke 280.988 in 67.484 in
Design Pressure 3000 psi 3000 psi
Test Pressure 3000 psi 3000 psi
Hyd. Fluid Mobil DTE Excel 15 Mobil DTE Excel 15
While at the repair facility, the following work is to be performed:
1. Hydraulic Cylinders
a. Disassembly/Inspection
i. Cylinder shell is to be cleaned and inspected. If corrosion or damage is found, blast area to raw metal, inspect, and verify cylinder shell has adequate wall thickness for operating at maximum system pressure of 3000 psi.
ii. Bore dimensions are to be taken every 12”, at a minimum.
iii. Cylinder piston is to be removed, cleaned, and chrome plating inspected.
iv. All internal seals and guiding strips are to be removed and inspected.
v. Cylinder end caps are to be cleaned and inspected. If corrosion or damage is found, blast area to raw metal, inspect, and verify cylinder cap has adequate wall thickness for operating at maximum system pressure of 3000 psi.
vi. Stainless steel piping is to be cleaned and inspected.
vii. All threaded connections and sealing grooves are to be cleaned and inspected.
b. Rehabbed/Reassembled
i. Cylinder bore is to be honed and polished. If cylinder shell is found to be damaged/corroded and wall thickness does not meet required thickness, replace cylinder shell.
ii. New cylinder rods are to be fabricated.
1. Rods are to be made out of one of the following substrate materials:
Material Standard
S355x EN 10025/ EN 10250 / EN 10210/ EN 10297/ others 25CrMo4 (Q+T) EN 10083
S460NH EN 10210
2. Rods must be machined to be compatible with CIMS (Cylinder
Integrated Measuring System) units.
3. Rods are to have anti-corrosion laser cladding (Enduroq 3i or comparable) applied to substrate material.
iii. Install new seals and guiding strips that are compatible with new rod coating.
iv. Provide new CIMS units with stainless steel bodies.
v. Install new stainless steel hardware for all bolted connections.
vi. Repaint cylinders per USGS 09 97 02, 5-E-Z paint system.
vii. Cylinders are to be filled with Mobil DTE 10 Excel 15 hydraulic fluid, to be compatible with fluid used on site.
viii. Cylinders are to be tested by contractor at the repair facility in prior to return shipment. Testing to include pressure testing to 3000 psi checking for leaks, note break-free pressure, and operation of cylinder throughout entire stroke length. Give a minimum of two weeks notice prior to testing to allow for USACE personnel to witness.
ix. “Spare” cylinders (one miter gate hydraulic cylinder and one Tainter valve hydraulic cylinder” are to be prepped for long term storage before shipment. When returned to site, spare cylinders are to be placed on existing stands.
2. Hydraulic Cylinder Manifolds Manifolds are to be rehabilitated:
i. Manifolds are to be cleaned and inspected for corrosion damage. If corrosion or damage is found, blast area to raw metal, inspect, and verify manifold is able to operate at maximum system pressure of
3000 psi.
ii. Clean all threaded connections and sealing grooves.
iii. Stainless steel valve bodies are required. If they are not available at the time of procurement, marine grade units are to be installed. Once stainless steel units are available, they are to be provided and installed.
iv. Provide new stainless steel hardware for all bolted connections.
v. Repaint manifold per USGS 09 97 02, 5-E-Z paint system.
b. Option work (if exercised):
i. This option will be included with the award of the miter gate cylinders if chosen.
ii. Manifolds are to be replaced with units of 316 stainless steel construction. These units are to be built with stainless steel hardware.
iii. Stainless steel valve bodies are required. If they are not available at the time of procurement, marine grade units are to be installed. Once stainless steel units are available, they are to be provided and installed.
iv. If the manifolds are replaced with new 316 stainless steel units, the existing manifolds are to be demolished.
3. Cardanic Ring Assemblies
a. Inspect components for deficiencies. If excessive wear is found on components, they are to be replaced, per USACE instruction.
b. Cardanic ring, trunnion, and pins are to be cleaned and blasted exposing raw substrate material.
c. Repaint body of trunnion and cardanic ring per USGS 09 97 02, 5-E-Z paint system.
4. The following items are to be provided for the above work items.
a. Inspection report with detailed pictures and descriptions of components condition.
b. Complete drawings of rehabbed cylinders to include all internal and external components.
c. Complete material summary list.
d. Overhaul report stating the work that was completed.
e. All materials that are replaced are to be disposed of properly by the contractor.
5. Schedule
a. The overall schedule is to take Peoria Lock out of operation week 28 (July 6th to July 12th) at which time USACE will remove the cylinders. USACE will place cylinder assemblies on a contractor’s transportation method as soon as July 16th but as late as July 23rd to be shipped to contractor’s repair facility, certified to perform original manufacturer’s specification rehabilitation. The contractor will have from week 29 to 37 (September 13th) to preform repairs on 4 out of 5 miter gate hydraulic cylinders. Once work is complete, the contractor is responsible for loading a flatbed truck or similar for shipment to Illinois Waterway Project Office 257 Grant Street, Peoria, IL 61603.The cylinders must be back onsite at Peoria Lock and Dam by 13 September 2020. The remaining miter gate cylinder must be back to Peoria Lock and Dam by 15 October 2020.
The following items are applicable to this modification:
Questions & Answers (as of 1/16/20) – Amendment 0002
Q1: What is the target award date?
A1: 31 January 2020
Q2. CIMS/CIPS System is not compatible with laser cladding, there must to be a thermal spray layer to cover up the grooves in the rod that the sensors read. Laser welding (cladding) will melt the sharp edges of the grooves and the CIMS/CIPS system will not function correctly.
A2. Per other cylinder manufacturers, laser cladding is possible over a CIMS style of measurement profile.
Q3. Because there are no installation or part drawings and with the timeline requirement on the contract would it be possible to receive the spare cylinder?
A3. Due to the necessity for the lock to remain operational, the spare cylinder must remain on site, in case one of the cylinders goes down. Pictures of the spare cylinder have been included with amendment 0002.
Q4. Are there other options for stroke measurements if we are not able to use Ceramic? For example MTS/Balluf LVDT for horizontal applications with these stroke lengths.
A4. Ceramic coating is not authorized for use by USACE. The use of a LDT is also not desired due to the length of the stroke, as well as the length of time the cylinder is in the extended position, MTS (LVDT manufacturer) did not recommend it for our current use. An externally mounted LDT is not feasible due to the conditions seen at Peoria (ice, flooding, debris, etc....)
Q5. Can a different line measuring system, e.g. linear transducers or sensors be proposed?
A5. If the Government changes from CIMS to a LVDT, a substantial amount of changes to the plans and specifications would have to be made. The type of contract would change from a firm fixed supply contract to a firm fixed construction contract. The level of reviews, clauses, specifications, post-award administration, etc. would all significantly change. The following would most definitely require the change from a supply contract to a construction contract:
a. The new position indication system will require changes to the electrical system on site.
b. The new position indication system will require reprograming of the PLC system.
The change of position indication would add more work to an already compressed schedule.
Q6. Schedule of Prices – 0101 Replace manifolds for all 5 miter gates. Should this be “Manifolds are to be rehabilitate?”
A6. See revised Schedule of Prices.
Q7. SOW Specifications: “Illinois River Operations Division. This includes: drained, removed, and loaded”: Why would (USACE) drain the cylinders? (This creates corrosion on internal parts, will allow piston to move more freely during shipment, and can cause damage).
A7. The cylinders themselves will not be drained, just the lines from the manifold to the cylinder to prevent hydraulic oil getting into the river. See revised SOW.
Q8. SOW: Hydraulic Cylinders; a. Disassembly/Inspection; i. Cylinder shell to be cleaned and blasted to raw material, and inspected for corrosion and damage to the bore. Does this pertain to only the Shell bore (ID) or is this pertaining to the outside of the Shell (OD)? One would never shot blast the Shell bore (ID), that would be an uncontrolled process. Typically you do not shot blast the outside (OD) of the shell until after final assembly. Shot blasting prior to final assembly would result in corrosion and one would either have to immediately need to apply a primer coat or have to re-shot blast after final assembly. This will result in added time and cost to the process.
A8. Cylinder shell is to be cleaned and inspected. If corrosion or damage is found, blast area to raw metal, inspect, and verify cylinder shell has adequate wall thickness for operating at maximum system pressure of 3000 psi. See revised SOW.
Q9. SOW: Hydraulic Cylinders; a. Disassembly/Inspection; iv. Cylinder end caps are to be cleaned blasted and inspected. Typically you do not shot blast the outside (OD) of the end caps until after final assembly. Shot blasting prior to final assembly would result in corrosion and one would either have to immediately need to apply a primer coat or have to re-shot blast after final assembly. This will result in added time and cost to the process.
A9. Cylinder end caps are to be cleaned and inspected. If corrosion or damage is found, blast area to raw metal, inspect, and verify cylinder cap has adequate wall thickness for operating at maximum system pressure of 3000 psi.
See revised SOW.
Q10. SOW: b. Rehabbed, i. Cylinder bore is to be honed and polished. If cylinder shell is found to be damaged/corroded and wall thickness does not meet required thickness, replace cylinder shell. If cylinder shell is damaged beyond repair will (USACE) apply pg. 12 clause 52.211-11 (c)? Lead-time for new cylinder shell is 28-32 weeks.
A10. Yes.
Q11. SOW: b. Rehabbed, iv. Provide all new valving with stainless steel bodies. What valving is this referring to?
Cylinder itself has no vales, just rod side and bottom side ports.
A11. This was in error and has been removed.
Q12. SOW: b. Rehabbed, vii. Repaint Cylinders per specification. What paint specification does the (USACE) want to utilize? Please provide paint specification.
A12. Items are to be painted using UFGS 09 97 02, paint system 5-E-Z. See revised SOW.
Q13. SOW: b. Rehabbed, ix. Cylinders are to be tested by contractor at repair facility in prior to return shipment.
What is the (USACE) requirement for testing the cylinder? The cylinder will be tested at contractor’s cylinder service facility. Does USACE want to witness the testing or assembly?
A13. USACE will want to note the break-free pressures, test cylinders to 3000 psi and check for leaks, and witness operation of the cylinders throughout stroke. Yes, USACE will witness testing, and possibly assembly depending on timeframe. See revised SOW.
Q14. SOW: b. Rehabbed, x. “Spare” cylinders (one miter gate hydraulic cylinder and one Tainter valve hydraulic cylinder are to be prepped for long term storage before shipment. Will the (USACE) want to use VSI (Vapor Space Inhibiting) inside the spare cylinders for long term storage? Typical preparation for long term storage is 100% filled with hydraulic medium and 2% VSI.
A14. Yes, that is acceptable. See revised SOW.
Q15. Does the (USACE) wish to have the spare cylinder crated for storage?
A15. No, the cylinder is to be placed on the existing stand, which is on casters, onsite. See revised SOW.
Q16. SOW: Hydraulic Cylinder Manifolds, a. Manifolds are to be rehabilitated: i. Replace all valving stainless steels units. If a stainless steel valve body option is available it will be provide, if stainless steel option is not available, will a marine grade equivalent be acceptable?
A16. Stainless steel valve bodies are required. If they are not available at the time of procurement, marine grade are to be installed. Once stainless steel units are available, they are to be provided and installed. See revised SOW.
Q17. SOW: Hydraulic Cylinder Manifolds, a. Manifolds are to be rehabilitated: v. Repaint manifolds per specifications. What paint specification does the (USACE) want to utilize? Please provide paint specification.
A17. Items are to be painted using UFGS 09 97 02, paint system 5-E-Z. See revised SOW.
Q18. SOW: Cardanic Ring Assemblies; a. Cardanic ring, trunnion, and pins are to be cleaned and blasted exposing raw substrate. Shot blasting prior to final assembly would result in corrosion and one would either have to immediately need to apply a primer coat or have to re-shot blast after final assembly. This will result in added time and cost to the process.
A18. These are to be blasted and painted after final assembly. See revised SOW.
Q19. SOW: Cardanic Ring Assemblies; b. Inspect components for deficiencies. If excessive wear is found on components they are to be replaced, per USACE instruction. We would expect the cylinder to be received without complete trunnion.
A19. The cylinder is to be shipped with entire cardanic ring assembly. See revised SOW.
Q20. SOW: Cardanic Ring Assemblies; c. Repaint body of trunnion and cardanic ring. Shot blasting prior to final assembly would result in corrosion and one would either have to immediately need to apply a primer coat or have to re-shot blast after final assembly. This will result in added time and cost to the process. What paint specification does the (USACE) want to utilize? Please provide paint specification.
A20. These are to be blasted and painted after final assembly. Items are to be painted using UFGS 09 97 02, paint system 5-E-Z. See revised SOW.
Q21. SOW: Schedule. Please advise firm shipment date. July 16th – July 23rd is an 8 day window.
A21. The Government intends to have the cylinders ready for shipment by July 16th but reserves the right to have them ready as late at July 23rd. The Government will make every to have them ready by the 16th and will be in contact on a daily basis with the awarded contractor on status.
(End of Summary of Changes)