Spillway 480v Bus Pictures and Information.pdf

PDF 5 MB Posted

Attached to
McNary Dam Cantilever Scaffolding Rental
Solicitation number
W912EF25QA057
Issued by

About this file

These images document detailed scaffolding and structural measurements for a spillway crane installation, likely at a dam facility. The photos provide critical dimensional details for scaffolding placement, including: 41.5 inches from deck to crane rail concrete surface, 107 inches between toe board and curbing, 5'9" from curb face to dam face, and 96 inches clearance height for scaffolding assembly. The images show a complex industrial infrastructure with a large crane system positioned on a concrete bridge-like structure, situated against a backdrop of arid mountainous terrain. Additional notes indicate that current spillway crane personnel baskets are unavailable as they are hooked to spillway leafs, and scaffolding work platforms must carefully navigate structural constraints like pier noses and overhead pipes that are part of the spillway hoist system.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Photo orientation looking north

East crane rail concrete measures 41.5 inches from the deck to the concrete surface that the crane rail is attached to. Scaffolding must clear this.

107 inches between toe board and curbing

41.5 inches from deck to surface of crane rail concrete

This space could be used to build the scaffolding.

Vehicle turnout

G4OWMVKC

Highlight

G4OWMVKC

Highlight

G4OWMVKC

Highlight

<---5'9" from face of curb to face of dam--->

Spillway crane personnel basket used for inspecting the bus. Both spillway cranes are hooked up to spillway leafs and can not be moved thus making these baskets unavailable.

This photo shows the pier noses for the spillway.

The scaffolding work platform must clear them.

From top of crane rail concrete to the floor of the scaffold work platform is approximately 6 feet.

<---------------------------------------------TOP of concrete with crane rail

41.5 inches from deck to surface of the crane rail concrete.

<---- Scaffolding assembly must roll under this. The measurement from the deck to the bottom of this is 96 inches. This cannot be removed.

This pipe is also part of the spillway hoist

G4OWMVKC

Highlight

Spillway 480v Bus Pictures and Information.pdf
Spillway Deck South.pdf
Spillway Deck Looking North.pdf
Spillway Crane Rail.pdf
View of Upstream Pier Noses for Work Platform.pdf
Spillway 480v Bus Good Upstream View.pdf
Spillway Upstream Concrete Height.pdf
Spillway Hoist Height Restriction.pdf

File details come from the government source that posted it. Updated .