Performance Work Statement (PWS).pdf
PDF 162 KB Posted
- Attached to
- McNary Dam Cantilever Scaffolding Rental
- Solicitation number
- W912EF25QA057
About this file
This Performance Work Statement (PWS) is for cantilever scaffolding rental services at McNary Lock and Dam for a Spillway Crane Bus Inspection. The government seeks a contractor to install and disassemble two rolling cantilever scaffolds on the Spillway Deck for a 5-year bus inspection, with specific requirements including a maximum 8-foot width, ability to support over 500 lbs, mounted on wheels, and featuring two 10' x 3' work platforms. The period of performance will be four weeks in October 2025, with the government providing forklift support for loading and unloading.
Key contractor responsibilities include providing engineered drawings for approval, ensuring safe scaffolding assembly with proper entrance and exit points, employing qualified personnel at least 18 years old, complying with U.S. Army Corps of Engineers safety requirements, completing required security and antiterrorism training, and mobilizing/demobilizing equipment during normal business hours (Monday-Thursday, 7:30AM-4:00PM). The contract will be a firm-fixed price commercial service contract, with all scaffolding to be delivered to McNary Lock and Dam in Umatilla, Oregon.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
McNary Lock and Dam
Cantilever Scaffolding Rental Service for Spillway Crane Bus Inspection
1.0 GENERAL INFORMATION
1.1 Type of Contract. The Government anticipates award of a firm-fixed price commercial service contract.
1.2 Period of Performance. The period of performance will be for FOUR (4) weeks in October 2025 after critical spill season is over. Exact dates TBD. Government personnel will be available to unload material with our inhouse forklift.
1.3 McNary Lock and Dam requires cantilever scaffolding rental services for the inspection of the Spillway Crane Bus. The cantilever rolling scaffolding will be used north and south parallel to the bus located upstream from the road deck of the Spillway. This will be out of the normal capability of the McNary maintenance crew and will require a competent contractor to provide the material and labor to assemble and disassemble the cantilever scaffolding.
2.0 SCOPE OF WORK
2.1 Install and disassemble two (2) rolling cantilever scaffolds on the Spillway Deck for a 5-year bus inspection. Contractor must provide all labor, supplies, materials, tools, and engineered drawings, for the installation of scaffolding. Prior to installation, the Contractor must provide engineered drawings for the cantilever scaffold construction that must be reviewed and approved by McNary Technical and Safety personnel.
2.1.2 The cantilever scaffolding work assembly must not be wider than 8 feet on the spillway road deck surface.
2.1.3 The work platform must be able to support greater than 500lbs.
2.1.4 The entire scaffold assembly must be mounted on wheels so that 2 or 3 craftsmen can wheel the assembly to desired work location along the spillway crane bus located on the upstream (east) side of the spillway.
2.1.5 Two (2) work platforms of 10’ x 3’ adjacent to the spillway crane bus.
2.1.6 Scaffolding will require a safe and reasonable means of entrance and exit for McNary personnel.
2.1.7 The bus inspection is estimated to take 4 weeks. McNary Lock and Dam will provide approximately one week’s notice for removal. Contractor must remove scaffolding and demobilize all materials.
3.0 CONTRACTOR PERSONNEL:
3.1 Employees who perform this work must be qualified persons on the Contractor’s own payroll. All Contractor employees must be at least 18 years of age.
3.2 Subcontracting: No work may be subcontracted without written approval of the Contracting Officer (KO).
Compliance with the provisions of this contract by subcontractors must be the responsibility of the Contractor.
4.0 PRE-WORK CONFERENCE. Prior to beginning work under this contract, the Contractor must attend a pre-work conference at a time, date, and location established by the government. The purpose of this meeting is to review the requirements of this contract and furnish points of emergency communication. The purpose of the pre-work meeting is to discuss and assure the Contractor’s understanding of the contract requirements, safety, and quality control program.
5.0 SAFETY. The Contractor and their employees must comply with all pertinent provisions of the most recent version of the U.S Army Corps of Engineers Manual EM 385-1-1 "Safety and Health Requirements Manual" (a copy is available for prospective bidders’ information and for successful contractors use), available at:
https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf
5.1 Incident/Accident Report: An accident constitutes an incident or act involving the Contractor, which may or may not have caused obvious damage to persons or property. This includes injuries to Contractor employees, members of the public, or damage to Government or personal property. The Contractor must notify the COR by telephone within 30 minutes of any incident or accident, followed by a written report. These reports must include, but are not limited to, location, nature of the injury or accident, authorities notified, and the action taken along with any other pertinent information such as who was injured and how it may have happened. These reports must be accompanied by sketches, graphs, drawings, and photographs, as needed, and forwarded to the COR within 1 working day following the injury or accident.
6.0 SAFE CLEARANCE TRAINING
6.1 Each individual Contractor and employee must take the appropriate level of HECP training commensurate with their job duties. Contractors must have at a minimum, one individual trained as Authorized Individual. All contractor personnel working in areas under a Safe Clearance must be trained as Affected Persons. Any non-working personnel, vendors and visitors that will be entering an area under Safe Clearance must take awareness level training. Individual training and written tests for the modules below must be completed on-line.
7.0 SECURITY
7.1 General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters must be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel must complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor must provide written documentation (e.g., email or memorandum) to the Government representative. The documentation must include the names of contract personnel trained and which training they completed; the Contractor must maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel must comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor must ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
7.2 Antiterrorism (AT) Level I training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access must complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).
7.3 Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility must comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US must be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel must comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities must coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property must comply with key and lock control procedures of the RA.
7.4 Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel must receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
7.5 Escorting in classified and/or sensitive areas: In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.
7.6 Pre-screen candidates using E-Verify Program: Contractors must comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.ea-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates must be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
8.0 QUALITY ASSURANCE. The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
9.0 SHIPMENT AND DELIVERY. All scaffolding must be mobilized and demobilized by Contractor during normal business hours of Monday-Thursday 7:30AM-4:00PM, excluding federal holidays. The Government will provide forklift support for loading/unloading equipment.
All shipments must be delivered to:
McNary Lock and Dam 82790 Devore Rd.
Umatilla OR 97882
| PERFORMANCE WORK STATEMENT (PWS) |
| McNary Lock and Dam |
| Cantilever Scaffolding Rental Service for Spillway Crane Bus Inspection |
| 1.0 GENERAL INFORMATION |
| 1.1 Type of Contract. The Government anticipates award of a firm-fixed price commercial service contract. |
| 1.2 Period of Performance. The period of performance will be for FOUR (4) weeks in October 2025 after critical spill season is over. Exact dates TBD. Government personnel will be available to unload material with our inhouse forklift. |
| 1.3 McNary Lock and Dam requires cantilever scaffolding rental services for the inspection of the Spillway Crane Bus. The cantilever rolling scaffolding will be used north and south parallel to the bus located upstream from the road deck of the Spillw... |
| 2.0 SCOPE OF WORK |
| 5.0 SAFETY. The Contractor and their employees must comply with all pertinent provisions of the most recent version of the U.S Army Corps of Engineers Manual EM 385-1-1 "Safety and Health Requirements Manual" (a copy is available for prospective bid... |
| https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf |
File details come from the government source that posted it. Updated .