Solicitation Amendment 0001 24B0010.pdf
PDF 378 KB Posted
- Attached to
- Jackson Levee Culvert Repair and Replacement Federal contract opportunity
- Solicitation number
- W912EF24B0010
About this file
This document is a Solicitation Amendment for federal contract opportunity W912EF24B0010, which is for the Jackson Levee Culvert Repair and Replacement project. The purpose of this amendment is to revise the technical specifications for the project. Key changes include updates to sections on submittals, activity hazard analysis, disposition of removed equipment, site restrictions, measurement and payment, submittal procedures, environmental protection, and culvert installation. The solicitation remains open and all other terms and conditions are unchanged. The revised technical specifications provide detailed requirements for the culvert repair and replacement work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SAM Abstract of Offerors.xlsx | XLSX spreadsheet | |
| Solicitation Amendment 0002 24B0010.pdf | ||
| 24B0010 - Technical Specifications Amendment 0001.pdf | ||
| A.03.09 Plans JHL Culvert Repair.pdf | ||
| B.08.02 Solicitation 24B0010.pdf | ||
| A.02.10 Technical Specifications JHL Culvert Repair.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this solicitation amendment is to revise the technical specifications. See summary of changes in Section 00 10 00 - Solicitation. See also revised specif ications for details.
All other terms and conditions of this solicitation remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Jun-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EF24B0010
X 9B. DATED (SEE ITEM 11)
30-May-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Jun-2024
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
MELITA S. DOYLE
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF24B0010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 01 10 - TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Technical Specifications 14-MAY-2024 Attachment 2 Plans 14-MAY-2024 to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 3 24B0010 - Technical
Specifications 0001
10-JUN-2024
SECTION 00 10 00 - SOLICITATION
The following have been added by full text:
SUMMARY OF CHANGES - AMENDMENT
Summary of changes for Amend -0001 JHL Repair and Replace Project Culverts
24B0010
1. Revise the following Specifications:
a. SPECIAL CLAUSES Fill In Clause Information was deleted from the specification package.
b. BID SCHEDULE
Bid schedule was deleted from the specification package.
c. SECTION 01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS Revised paragraph 1.3 SUBMITTALS.
Revised paragraph 1.6.6 ACTIVITY HAZARD ANALYSIS (AHA).
Added paragraph 1.6.6.1 AHA SIGNATURE LOG.
Revised paragraph 1.11 DISPOSITION OF REMOVED EQUIPMENT.
Revised paragraph 1.13 PRE-WORK AND POST WORK CONDITIONS INSPECTIONS.
d. SECTION 01 14 00.10 28 PROJECT SITE RESTRICTIONS
W912EF24B0010
Revised paragraph 1.4.1 Main Stockpile Site.
e. SECTION 01 22.00.00 28 MEASUREMENT AND PAYMENT Revised paragraph 1.11 CLIN 0008 SITE WORK AT FEDERAL EXTENSION 06+25.
Revised paragraph 1.12 CLIN 0009 SITE WORK AT JOHN DODGE 60+58.
f. SECTION 01 33 00 SUBMITTAL PROCEDURES
Revised paragraph 1.1.1 Submittal Descriptions (SD) Revised SUBMITTAL REGISTER.
g. SECTION 01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
Revised paragraph 1.2 ORDERING INFORMATION
h. SECTION 01 57 20.01 28 ENVIRONMENTAL PROTECTION Revised paragraph 1.1 SUBMITTALS.
Added paragraph 1.8 ON-SITE CONCRETE WASH OUT AREA PLAN.
Revised paragraph numbering 1.8 to end of section.
i. SECTION 03 30 00.01 28 CAST-IN-PLACE CONCRETE
Deleted section.
j. SECTION 03 45 33.00 28 PRECAST STRUCTURAL CONCRETE Deleted section.
k. SECTION 35 41 10.61 28
Revised paragraph 1.1 SCOPE OF WORK.
Revised paragraph 1.3 SUBMITTALS.
Revised paragraph 2.7.1 General.
Deleted paragraph 2.7.2 Seat.
Deleted paragraph 2.7.3 Cover.
Deleted paragraph 2.7.4 Fasteners.
Revised paragraph 3.1 CULVERT REMOVAL.
Revised paragraph 3.3.2 Precast Headwalls.
Revised paragraph 3.4 SLIDE GATE INSTALLATION.
See revised and highlighted specifications for details.
(End of Summary of Changes)