W912EF21B0011 Bid Opening Results.pdf
PDF 191 KB Posted
- Attached to
- McNary Intake Bulkheads Replacement Federal contract opportunity
- Solicitation number
- W912EF21B0011
About this file
This document contains bid opening results for solicitation number W912EF21B0011 to replace intake bulkheads at the McNary Lock and Dam. Hydro Partners Joint Venture provided the lowest bid at $3,375,800.00, while the government estimate was $4,324,940.00. Eight contractors submitted bids ranging from $3,375,800.00 to $6,054,264.00 by the 1 April 2021 deadline.
The related federal contract opportunity notice describes the requirement to replace two intake bulkheads at the McNary Lock and Dam in Umatilla County, Oregon. Each new intake bulkhead must be approximately 23 feet wide, 55 feet tall, 3 feet deep and weigh 140,000 pounds. The fabrication contractor must be certified in structural steel work. The awarded contractor will be responsible for delivering the completed intake bulkheads to the dam site for installation. The performance period and bonding requirements are also specified. The solicitation was expected to be posted on beta.SAM.gov in February 2021 as a total small business set-aside with an estimated value between $5-10 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912EF21B0011 Bid Opening Results - UPDATE.pdf | ||
| B.08.03 TECHSPECS_21B0011_amd0002_24Mar21.pdf | ||
| B.08.03 W912EF21B0011 Amendment 0002.pdf | ||
| B.08.03 Plans_21B0011_amd0002.pdf | ||
| Site Visit Attendee List - W912EF21B0011 MNA Bulkheads.pdf | ||
| B.08.03 W912EF21B0011 Amendment 0001.pdf | ||
| B.08.02 Solicitaton - W912EF21B0011 MNA Bulkheads.pdf | ||
| B.08.02 McNary Bulkheads Resource Drawings_21B0011.pdf | ||
| B.08.02 McNary Bulkheads Contract Drawings_21B0011.pdf | ||
| B.08.02 Technical Specifications MNA Bulkheads_21B0011.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID OPENING WORKSHEET – 1 April 2021, 3:00 PM
Solicitation Number: W912EF21B0011 AMENDMENTS: 2 CONSTRUCTION: MNA Bulkheads
CONTRACT SPECIALIST: Karlyn Holland
CONTRACTOR Acknowledge Amendments
TOTAL BID
(Base Schedule plus
Optional Items)
BCI Construction USA, Inc.
Y $4,318,852.00
Derian, Inc. Y $4,361,660.00
Hydro Partners Joint Venture Y 3,375,800.00
King Fabrication LLC Y 3,917,509.00
Northbank Civil and Marine, Inc.
Y 3,691,300.00
Steward Machine Company, Inc.
6,054,264.00
Thompson Metal Fab
4,186,177.00
Transco Ind. Inc.
Y 5,460,152.00
WHH Nisqually-Garco JV Y 4,299,949.00
GOVERNMENT ESTIMATE
$4,324,940.00