A.07.23._Solicitation_Attachment_2_Towboat_Inspection_Checklist.pdf

PDF 260 KB Posted

Attached to
Juvenile Fish Barge Transport Program Federal contract opportunity
Solicitation number
W912EF-16-R-0011
Issued by
Department of the Army Corps of Engineers Engineering District Walla Walla

About this file

Towboat Inspection Checklist

View the file

Other files for this federal contract opportunity

Other files attached to Juvenile Fish Barge Transport Program, newest first.
File Type Posted
A.07.24_Solicitation_Amendment_0001.pdf PDF
A.07.23._Solicitation_Attachment_3_Past_Performance_Info.pdf PDF
A.07.23._Solicitation_Attachment_4_PastPerformanceQuestionnaires.pdf PDF
A.07.23.__Solicitation_Attachment_1_Map.pdf PDF
A.07.23._Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3

TOWBOATS

TOWBOAT INSPECTION CHECK LIST

Item Additional to USCE Safety Manual – Bearing on capability of towboat to perform in intended service YES NO YES NO YES NO YES NO YES NO REMARKS

I.

Towboats to satisfy applicable U.S. Coast Guard Rules

1. Towboats to be considered under this contract must satisfy the U.S. Coast Guard Rules for Uninspected Vessels. 46 CFR Subchapter “C” Parts 24 thru 26.

II.

Power, Propulsion

1. Main Engines for multiple screw propulsion.

Total installed power to be 1000 SHP minimum at a variable rating where full throttle might be required for 30 minute periods, but followed by equal intervals at continuously rated rpm (reduced load).

2. Propellers sized to restrict engine RPM to 95% manufacturers top rated rpm at bollard condition and to develop sufficient towing speed at continuous rated rpm (85% top rated rpm) to complete USCE contract required 79 hour round trip with any two of the eight USCE Fish Transport Barges in tow at full load draft downstream and light upstream.

To verify satisfaction of these requirements the towboat free running rpm and rpm at the bollard should be recorded in an operational test. The engine manufactures model ratings should be submitted.

III.

Propeller Shafting Size Propeller shafting size is to satisfy the requirements of the ABS Rules* (Sect. 7 Part 7.7)

*American Bureau of Shipping “Rules for Building and Classing Steel Vessels for Service on Rivers and Intercoastal Waterways”

IV.

Rudders, Stocks and Steering Gears Steering systems are to satisfy the requirements of the ABS Rules* (Sect. 6 Parts 6.5.2, 3.a. and Sect. 7 Parts 7.15.1, 3, 4, 6, 7, 9, 10)

During operational trial of the Towboat, these requirements are to be verified.

V.

Hull Structure The towboat hull plating and framing system is to satisfy the requirement of the ABS Rules* (Sect. 6 Parts 6.7, 9, 11, 13, and 15.), including subdivision requirements.

*SEE Remarks – Previous page (Item III)

VI.

Deck Gear for Making-up Barges to Towboat

1. Each towboat shall be equipped with at least two barge connector winches (rated 25 ton static holding, min.)

with ¾” wire rope of sufficient length to leave two full layers on the drum after making up the tow. These winches are to be in addition to the two winches aft on the pushed barge which shall also be made up to fittings and fairleads available on the towboat.

2. Cleats, kevels, bitts, tailholds and winches shall be set on doublers or inserts with under deck strengthing to develop the breaking strength of the WR used.

VII.

Stability Criteria to be Satisfied

1. Angle of heel at downflooding shall not be less that 25°

2. Available initial metacentric height (GMa) shall not be less than the greater obtained from the following formulas:

B frGM Δ l10 BHP ⋅

(1.) or B fr AhGM

Δ

(2.)

BHP= Total installed A = Projected lateral area Brakehorsepower above waterline

NOTE: In lieu of the criteria detailed under VII, the towboat may qualify under this contract by compliance with USCG requirements detailed under 46 CFR Subchapter I Part 93.07-5 & 10 and subchapter S Part 174.145.

Δ Δ f f

= Displacement (lbs) = Displacement (lbs) = Minimum Freeboard (ft.) = Minimum Freeboard (ft.)

VII.

Stability Criteria to be satisfied (Cont.)

= Vertical Distance h = Vertical Distance l between center of between center of A and rudder and point of ½ mld. Draft (ft.)

attachment of barge connector wires (ft.)

B = Vessel Beam (ft.) B = Vessel Beam (ft.)

3. Available initial metacentric height (GMa) may be estimated by formula (3)

221.0 T

BGMa = (3)

B = Vessel Beam (ft.)

T = Rolling period (seconds)

4. In lieu of determination of vessel displacement (Δ ) by calculation and estimating available GMa by use of formula (3), the vessel may be subjected to a heeling moment {i.e.

WT (lbs.) x distance (ft.) off centerline} equal to the greater:

(1) or (2) lBHP10=HM 1 AhHM 10=

With this heeling moment imposed, the resulting list must not immerse more than ½ the freeboard at the minimum point.

The condition of the vessel for the test: 1. Fuel and water tanks about three-quarters full. 2. Vessel complete with all gear, stores and operating weights aboard and distributed to provide normal operating trim.

Item USCE SAFETY & HEALTH REQUIREMENT Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

VIII.

Access

1. Safe means of boarding & leaving

21.A.01.a,b,c,d 19.B.02.a,b 21.D.01

2. Non-slip surfaces 19.B.01.b

19.A.07.c 21.A.13.a, b, c

3. Accessways safe, clear, unobstructed, marked, and at least 18 inches wide.

21.A.05 14.C.01 14.C.02 14.C.03 19.B.01.c 21.B.08.a 19.A.05.j 21.A.13.a,b,c

4. Stumbling hazards painted yellow, or white 19.A.07.J

5. Deck openings protected 19.A.07.h

21.B.02.d 21.B.01 21.A.15.b 24.A.01 24.A.02 24.A.03 24.A.05

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

VIII.

6. Guardrails inflexible 42” +/- 3” high

19.A.07.h (2) 21.B.01 21.B.02.a,b,c,d

7. Ramps cleated if incline exceeds 1 to 5 21.F.01

8. Means provided to secure doors (open or closed) 19.A.05.i

9. Ladders 21.D.08.e (7” toe spaces)

21.D.02.e

10. Gate at stairway or ladderway entrance 21.A.15.b

11. Hinged floor opening cover with guardrails 24.A.01

24.A.03

12. Two means of escape from crew quarters 19.B.04.b

IX.

Protective Equipment & Medical Facilities

1. 03.B.01 Table 3-1 First aid kit type III (16-unit)

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

IX.

2. Coast Guard approved work vests, (PFD)

19.A.03.d 05.H.01.a, b, c, d, e (no inflatables)

3. Ring buoys w/70’ of 3/8” rope 05.H.03.b, c, d, (1,2,3,4)

4. Waterlights – on all ring buoys and work vests 05.H.01

05.H.02 05.H.03

5. Safety skiff (one on each towboat) USCG certified for floatation and capacity.

05.I.01 05.I.03 05.I.04 05.I.05 05.I.06 05.I.07 19.C.02.a, b, c, d, e

19.C.03.a

a. Four oars (two if the skiff is motor powered)

b. Oarlocks attached to gunwales or the oars

c. Ball-point boat hook

d. Ring buoy w/70’ of 3/8” rope

e. A PFD or work vests to accommodate capacity rating

f. One fire extinguisher (Dry Chemical)

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

6. Rescue ladder

19.B.04

21.D.02 21.D.03

7. Communications & transportation provided for injured workers

03.A.01.a, b, c

X.

Fire Prevention and Protection

1. Fire exits & fire protection equipment locations marked 09.A.01

09.A.04 09.A.06 19.A.04 19.C.03

2. Flammable storage area 09.B.01

09.B.12

a. No smoking signs 09.A.06

09.A.07 09.B.02

b. Source of ignition prohibited 14.C.09.a, b, c

c. Spills of flammable and combustible liquids cleaned up.

14.C.10

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

3. Fire extinguishers. Provided where needed, inspected and and maintained, distinctly marked and accessible.

09.E.01 09.E.02.a, b, c, d 09.E.03 09.B.03.b 10.C.01 10.C.02 19.A.05.b

4. Firefighting apparatus and equipment meets NFPA and USCG Regulations

09.G.01 09.G.02 09.G.03

5. Alarms 09.H.06

09.H.07 09.H.08

09.H.09.b

6. Telephone number and instructions posted 09.H.09.b

19.A.04.a, b, c, d, e, f, g, h

7. Temporary heating devices Installed according to code NFPA, USCG and GDA

Approved.

09.D.01.a, e, f, g 09.D.02.a, b, c, e 09.D.03 09.D.05 09.D.07

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

7. Temporary heating devices “continued”

09.D.08 09.D.09 09.D.11

8. Flammable liquids 09.B.01

09.B.02 09.B.03.b 09.B.04 09.B.07

XI. Machinery and Mechanized Equipment

1. Guards

16.B.03.a, b

2. Lubrication fittings safely located

16.B.13

XII.

Electrical Equipment

1. Protection of live and high voltage equipment 11.A.02.a, b, c

2. Switches, fuses, and automatic circuit breakers identified 11.4.02.d

3. Grounds 11.C.01.a, e, f, g

4. Maximum operating voltage marked on all boxes, cabinets 11.B.01.c

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

XII.

5. Circuits protected against overload

11.B.01.a, b, c, d

6. Provision made for locking switches or breakers in off position

11.B.01.e

7. Circuits, semi-portable equipment & work lights grounded according to code

11.C.01.a 11.C.01.e

8. Wires insulated from their supports 11.D.05

9. No exposed empty light sockets or broken bulbs 11.D.06.c

XIII.

Pressurized Equipment & Systems

1. Pressure vessels inspected, tested & maintained 20.A.01

20.A.02.a, b 20.A.03 20.A.04 20.A.05 20.A.06 20.A.07 20.A.08 20.A.09

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

2. Approved pressure gauge all pressure systems

20.A.12

3. Approved safety or relief valves on all pressure vessels 20.A.13

3. a. Safety valves, relief valves and blowouts safely and properly located

20.A.10 20.A.11 20.A.13.b, d 20.B.10

b. Relief valve setting not more than 10 percent above maximum working pressure

20.A.13.a

c. Relief and safety valves sealed after adjusting 20.A.13.c

4. Boilers and systems 20.C.01

a. Fusible plugs 20.C.04

5. Compressed gas cylinders

a. Visually inspected 20.D.01

b. Properly stored 20.D.03.a, b, c, d, e

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

5. Compressed gas cylinders (continued)

c. Secured 20.D.07

20.D.08 20.D.10

6. Safety lashings on quick connect pressurized hoses and tools

20.A.16.d

7. Compressed air and gas systems

a. Easy access to master valves and controls

20.B.02.a, b

8. Compressors and related equipment

a. Safe access for operation, maintenance and repair 20.B.02.a

b. Speed governor independent of unloader 20.B.07.a

c. Auxiliary control to governor if engine or turbine driven 20.B.07.b

d. High pressure cut-off 20.B.08.a, b

e. Flammables, toxic gases, vapors or dusts excluded form compressor and steam, water or waste from intake

21.B.09

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

8. f. Valves excluded on atmospheric air intake pipes

20.B.10

g. Air discharge piping from compressor to air receiver as large as discharge opening on air compressor

20.B.11

h. Stop valves installed 20.B.12

20.B.13.a

20.B.13.b safety valve settings 10% above working pressure

i. Provision for expansion and vibration 20.B.14

j. Piping equipped with means for removing liquid from lines

20.B.18

k. Air discharge piping installed, eliminate oil pockets 20.B.16

l. Drains and handholes easily accessible 20.B.17

m. Air receivers properly located (clearance, accessible) 20.B.17.a, b, c, d, e

n. Drain valve at lowest point 20.B.18

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

8. o. Hoses designed for operating pressures

20.B.23

XIV.

1. Ropes, slings and chains

a. Eye splices made up in approved manner, thimbles

15.A.04

b. Corroded wire rope at end fittings removed or Resocketed

15.B.01

c. Rope diameter proper size for drum, block, sheave, or pulley tread diameter

15.F.02 15.F.03

d. Connections, fittings, fastenings, parts, etc. for proper intended use

15.F.05

e. Drums, sheaves and pulleys free of defects

15.F.03 15.F.04

XV.

General Floating Plant & Marine Work

1. Signal Device 19.A.05.c

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

2. Fuel and grease on floors and in bilges prevented from accumulating

14.C.10 19.A.07.c

3. Shutoff valve at fuel tank connections 19.A.06.b

4. Shutoff valve at engine end of fuel line 19.A.06.c

5. Backfire trap or flame arrestor on carburetors on gasoline engines

19.A.06.d

6. Continuously emptied drip pan with flame screen on carburetor

19.A.06.e

7. Adequate Lighting

07.A.01 07.A.04 07.A.05 07.A.06 07.A.07 Tbl. 7 - 1

8. Personnel properly licensed (Vessels 26’ or over USCG) 19.A.02.a

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

9. CG License for motor boat operators transporting personnel

19.C.05.a, b, c

10. Fenders 19.A.05.a

11. Ear protection furnished

05.C.01.a, b

12. Materials safely stacked and secured 14.B.01.a, b

13. Drinking water 02.B.01.a

14. Toilet facilities 02.C.01

02.C.02 02.C.03 02.C.04 02.C.05

15. Emergency cutting equipment, axes

19.A.05.b

16. No gauge glasses or try cocks on fuel tanks or lines 19.A.06.a

17. Grab Bars (tugs, tenders, and launches) where there are no hand rails

19.B.01.c

Manual EM-385-1-1 2003 YES NO YES NO YES NO YES NO YES NO REMARKS

XV. 18. Inspection and certification as required by USCG for uninspected vessels

19.A.01.a

19. Equipment emergency controls protected and easily accessible but out of accidental contact

19.A.05.d

TOWBOAT INSPECTION CHECK LIST
Towboats to satisfy applicable U.S. Coast Guard Rules
Power, Propulsion
Propeller Shafting Size
Rudders, Stocks and Steering Gears
TOWBOAT INSPECTION CHECK LIST
Hull Structure
Deck Gear for Making-up Barges to Towboat
TOWBOAT INSPECTION CHECK LIST
TOWBOAT INSPECTION CHECK LIST
Access
TOWBOAT INSPECTION CHECK LIST
TOWBOAT INSPECTION CHECK LIST
TOWBOAT INSPECTION CHECK LIST
TOWBOAT INSPECTION CHECK LIST
Machinery and Mechanized Equipment
Electrical Equipment
7. Circuits, semi-portable equipment & work lights grounded
according to code
Pressurized Equipment & Systems
3. a. Safety valves, relief valves and blowouts safely and
properly located
20.A.16.d
7. Compressed air and gas systems
8. Compressors and related equipment
h. Stop valves installed
General Floating Plant & Marine Work
19.A.05.c
9. CG License for motor boat operators transporting personnel
17. Grab Bars (tugs, tenders, and launches) where there are no
hand rails

File details come from the government source that posted it. Updated .