This document is Amendment 0004 to solicitation W912EE26RA005, issued by the U.S. Army Corps of Engineers Vicksburg District on February 2, 2026. The amendment modifies specifications and drawings for the Bolivar County, Mississippi FC/MR&T East Bank Mississippi River Levee Seepage Remediation project (Francis to Round Lake, Item 615-L).

The amendment revises technical specifications in six sections: Section 01 00 00.00 09 (General Contract Requirements), Section 01 22 00.00 09 (Measurement and Payment), Section 31 11 00.00 09 (Clearing and Grubbing), Section 31 23 00.00 09 (Excavation), Section 31 24 00.00 09 (Embankment), and Section 33 42 29.01 09 (Water Control Structure and Culverts). Drawing sheets C-101, C-102, C-103, C-104, C-105, C-106, C-107, C-108, C-110, C-112, C-113, C-114, C-115, and C-602 are revised, while sheets C-301 and C-302 remain unchanged. The amendment adds nine new attachments including amended specifications and additional plan sheets. All revisions are marked within the specifications with underlined text for additions and overstruck text for deletions. The contract involves levee embankment construction, berm development, clearing and grubbing, water control structures, and culvert installation with associated survey, quality control, environmental protection, and safety requirements. Contractors must acknowledge receipt of this amendment prior to the deadline specified in the solicitation or as amended.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

J 1 4

0004 02 FEB 2026 MRL 615-L

W912EE

W07V ENDIST VICKSBURG

KO CONTRACTING DIVISION, 4155 CLAY STREET

VICKSBURG, MS 39183-3435

UNITED STATES

LAWREN BOOLOS, EMAIL: LAWREN.BOOLOS@USACE.ARMY.MIL TELEPHONE: 601-

631-5211

SCD: PAS:

W912EE26RA005

08 JAN 2026

SEE SECTION G - CONTRACT ADMINISTRATION DATA

See Schedule

ROBERT E. SCREWS

02 FEB 2026

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SPECIFICATIONS: Sections 01 00 Block 14 (Description of Amendment/Modification):

00.00 09, 01 22 00.00 09, 31 11 00.00 09, 31 23 00.00 09, 31 24 00.00 09, and 33 42 29.01 09 are revised.

DRAWINGS:

Drawing Sheets C-301 and C-302 are not being edited.

Drawing sheets C-310, C-311, C-312 C-313, C-314, C-315, C-316, C-317, C-318, C-319, C- 320, C-321, C-322, C-323, C-324, C-325, C-326, C-327, C-328, C-329, C-330, C-331, C-332, C-333, C-334, C-335, and C-336 remains the same.

Drawing sheets C-101, C-102, C-103, C-104, C-105, C-106, C-107, C-108, C-110, C-112 C- 113, C-114, C-115, and C-602 are revised.

Specifications revised by this amendment have the notation "Revised by Amendment 0004" at the bottom of the page. Text added by this amendment is shown as underlined. Text deleted by this amendment is shown as overstruck.

Drawings revised by this amendment have the notation "Revised by Amendment 0004" in the title block.

Section 00 01 15 - List of Drawing Sheets

The attachments table has changed from:

To:

The following contract documents were added:

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS

01 22 00.00 09 MEASUREMENT AND PAYMENT

01 32 01.00 09 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 09 QUALITY CONTROL

01 45 00.15 09 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 20.00 09 ENVIRONMENTAL PROTECTION

01 57 23.00 09 STORM WATER POLLUTION PREVENTION PLAN

DIVISION 31 - EARTHWORK

31 11 00.00 09 CLEARING AND GRUBBING

31 23 00.00 09 EXCAVATION

31 24 00.00 09 EMBANKMENT

31 37 00.00 09 STONE PROTECTION FOR STRUCTURES

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 15 00.00 09 LEVEE SURFACING

32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT

DIVISION 33 - UTILITIES

33 42 29.01 09 WATER CONTROL STRUCTURE AND CULVERTS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1 Revised by Amendment 0004

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00.00 09

GENERAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PARTNERING

1.4 RIGHTS-OF-WAY

1.5 SURVEY LAYOUT AND MARKING FOR RIGHTS-OF-WAY AND CONSTRUCTION

1.6 APPROVAL OF CONTRACTOR-FURNISHED RIGHTS-OF-WAY

1.7 PRECONSTRUCTION CONFERENCE

1.8 SUBMITTAL OF SUBCONTRACTING PLAN

1.9 NOTIFICATION OF AREA ENGINEER BEFORE BEGINNING WORK

1.10 PROHIBITED WORK DURING FLOOD STAGES

1.11 ORDER OF WORK

1.12 DESIGNATED BILLING OFFICE

1.13 PAYMENT INVOICES

1.14 TEMPORARY PROJECT FENCING

1.15 AS-BUILT DRAWINGS

1.16 PROJECT SIGN

1.17 MINIMUM REQUIRED INSURANCE

1.18 WORK IN QUARANTINED AREA

1.19 CERTIFICATES OF COMPLIANCE

1.20 PROCESS FOR OBTAINING CURRENT REQUIREMENTS OF THE U.S. ARMY CORPS

OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL (EM 385-1-1)

1.21 SAFETY SIGN

1.22 ACCIDENT PREVENTION PLAN

1.23 DAILY INSPECTIONS

1.24 ACCIDENT INVESTIGATIONS AND REPORTING

1.25 ACCOMMODATIONS FOR GOVERNMENT REPRESENTATIVES

1.26 MACHINERY AND MECHANIZED EQUIPMENT

1.27 VEHICLE WEIGHT LIMITATIONS

1.28 PUBLIC AND PRIVATE UTILITIES

1.29 DAMAGE TO WORK

1.30 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.31 EXCLUSION OF PERIODS IN COMPUTING COMPLETION SCHEDULES

1.32 CONTROL OF ACCESS TO CONSTRUCTION AREAS

1.33 MAINTENANCE OF TRAFFIC

1.34 HARBOR MAINTENANCE FEE

1.35 COOPERATION WITH OTHER CONTRACTORS

1.36 ACCEPTANCE OF COMPLETED WORK

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 00 00.00 09 Page 1

-- End of Section Table of Contents --

SECTION 01 00 00.00 09 Page 2

SECTION 01 00 00.00 09

GENERAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

19 CFR 24.24 Harbor Maintenance Fee

33 CFR 156 Oil and Hazardous Material Transfer Operations

1.2 SUBMITTALS

Government approval is required for all submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Accident Prevention Plan ; G, GA

1.3 PARTNERING

To enhance the potential for success on this contract, the Government encourages formation of a project partnership among all stakeholders (Government, Contractor, Subcontractors, Suppliers and Customer as appropriate). Project partnering provides a structured management approach to facilitate teamwork across contractual boundaries. This proposed partnership would strive to develop a cooperative working relationship to jointly establish and effectively reach mutual project execution goals. Participation in such a partnership will be totally voluntary. The partnering process would normally include an initial offsite kickoff meeting and follow-on maintenance meetings as agreed by the partnership. Costs of such meetings would be shared between the Government and the Contractor, based on a mutual agreement, without change to the contract price. The partnering process will in no way relax or stiffen the requirements of the contract, but will enhance the likelihood of success through improved working relationships.

SECTION 01 00 00.00 09 Page 3

1.4 RIGHTS-OF-WAY

a. The rights-of-way for Contractor performance under this contract, within the limits indicated on the drawings, will be provided by the Government without cost to the Contractor. It is the Contractor's responsibility to carefully review and determine the scope of the rights-of-way. Any questions should be clarified with the Government prior to use. If these rights-of-way are used by the Contractor, he shall, at his own expense, do all work necessary to make such rights-of-way suitable for safe travel to and from the worksite. Upon completion of the Contractor's work, any such rights-of-way furnished by the Government shall be left in a condition satisfactory to the Contracting Officer.

b. When so directed by the Contracting Officer, the Contractor shall, without expense to the Government, promptly vacate and clean up any part of the Government grounds or rights-of-way that have been allotted to or have been in use by the Contractor.

c. The Contractor shall not obstruct any existing roads or any other means of existing ingress or egress on lands controlled by the United States except with written permission of the Contracting Officer and shall maintain such roads and other means of ingress or egress in as good condition as exists at the time of commencement of work performance under this contract.

d. The Contractor shall procure, without expense to the Government, all additional lands, access roads, rights-of-way, and any other property rights necessary for his use in the performance of the work or as required by his method of operation. The Contractor shall provide the Contracting Officer with an authenticated copy of the conveyance under which the Contractor acquired such property rights, prepared and executed in accordance with the laws of the State in which the land is located. The Contractor shall also obtain from the property owners and present to the Contracting Officer a release of all claims against the Government which may result from the Contractor's use or possession of such real estate or property rights. The written conveyance and release shall be provided to the Contracting Officer prior to the Contractor's use of Contactor obtained real estate or property rights. If temporary rights-of-way are obtained by the Contractor the period of time for those rights shall coincide with Section 00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS, paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, plus a reasonable time for any extension granted for the completion of the work. Any agreements or permits with levee boards, counties, parishes, municipalities, or other political subdivisions for moving material and equipment will be the responsibility of the Contractor and shall be obtained at no expense to the Government. Any delays to the Contractor resulting from delays in procuring access roads, rights-of-way, permits, or other real estate and property rights necessary for moving material and equipment for his work under this contract will not be a basis for any claim for increase in the cost of this contract. The Contractor shall make his own investigations to determine the conditions, restrictions and difficulties which may be encountered in acquiring such real estate, rights-of-way, or other property rights and in the transportation of material and equipment. In addition, the Contractor shall be solely liable for any and all damages and claims of any nature whatsoever arising from, related to, or growing out of the acquisition and use of

SECTION 01 00 00.00 09 Page 4 this real estate, rights-of-way, property rights, etc.

e. Notwithstanding any language or drawings to the contrary in this contract, the United States will not provide access or rights-of-way over any public lands and will not be responsible for acquiring such.

f. The Contractor shall repair at no expense to the Government, any and all damage to any existing roads or other means of existing ingress or egress when such damage is a result of his operations under this contract.

1.5 SURVEY LAYOUT AND MARKING FOR RIGHTS-OF-WAY AND CONSTRUCTION

The contractor shall be required to obtain the services of a licensed professional surveyor that is licensed in the state of contract performance to perform the following:

a. Field verify all control before start of construction activities.

The contractor's surveyor shall be required to document any discrepancies discovered and any additional control that is required to facilitate construction activities. This information shall be submitted in writing to the Contracting Officer prior to initiating construction activities.

b. The Contractor shall layout and mark the rights-of-way limits as indicated on the drawings prior to beginning any other work, unless otherwise approved. The marking shall be placed at intervals approved by the Contracting Officer. The rights-of-way limits shall be marked by stakes, flagging or other approved means. The marking shall be highly visible from a distance of at least 100 feet, and shall be maintained for the duration of the contract. If the rights-of-way marking should fade significantly in color, become damaged or lost as a result of the Contractor's operation or as a result of vandalism, or in any other way cease to function as a highly visible marker of the rights-of-way limits, the Contractor shall layout and restore the marking to the original condition. After all work is complete and upon approval of the Contracting Officer, the Contractor shall remove all marking. No separate payment will be made for layout, marking and maintaining the rights-of-way limits or for removing the marking.

c. Crown stakes referenced to the project centerline shall be placed at 100 foot intervals and at event points along the centerline alignment of the project. These stakes shall be labeled with the station number and proposed fill elevation. The stakes shall be maintained at a minimum on a monthly basis for all reaches under construction.

d. Cut and fill stakes shall be placed on all toe of slopes at 200 foot intervals at both the toe of berms and the toe of levee. The stakes shall be labeled with the proposed slope, indicate the direction of slope, and the horizontal distance from centerline. The stakes shall be maintained at a minimum on a monthly basis for all reaches under construction.

e. Stakes shall be placed at the midpoint or breakpoint of the slopes at 200 foot intervals. The midpoint stakes or breakpoint shall be labeled with the proposed grade elevation at the midpoint and the

SECTION 01 00 00.00 09 Page 5 horizontal distance from the centerline levee enlargement. The stakes shall be maintained at a minimum on a monthly basis for all reaches under construction.

f. No separate payment will be made for layout, marking and maintaining the rights-of-way limits or for removing the marking.

g. All partial and final surveys shall consist of cross sections conducted every 100 feet with offsets and elevations for the toe of slope intercepts with existing ground of berms, levee, and ramps; and break points at the subgrade shoulder lines. Additional shots shall be taken with no more than 25 foot (horizontal distance) between points, Cross Sectional data shall be mapped and electronically plotted at a horizontal and vertical scale of 1:20 with a baseline laid out and shown, as on the typical cross sections in the contract drawings, A sufficient horizontal and vertical scale, as determined by the Contracting Officer, shall be shown ascending from zero at the baseline in the horizontal direction and ascending from the existing ground elevation(s) in the vertical direction.

1.6 APPROVAL OF CONTRACTOR-FURNISHED RIGHTS-OF-WAY

In addition to the requirements found in paragraph RIGHTS-OF-WAY, subparagraph d., pertaining to additional lands, access roads, or rights-of-way, the Government reserves the right to approve or disapprove the Contractor's use of additional lands, access, or rights-of-way dependent on environmental or cultural resource impacts and the Contractor's compliance under the Contract Clause PERMITS AND RESPONSIBILITIES for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. Environmental and cultural resource impacts that could be basis for disapproval include, but are not limited to, clearing of additional trees, destruction of wildlife habitat, fill or other disturbance of wetlands, and disturbance of cultural sites.

1.7 PRECONSTRUCTION CONFERENCE

a. A preconstruction conference will be arranged by the Area Engineer as soon after contract award as possible, and the conference will be conducted before work is allowed to commence. The Area Engineer will notify the Contractor of the time, date, and location for the meeting. At this conference, the Contractor will be oriented with respect to contract administration procedures, lines of authority, opportunity for formation of project partnerships including joint risk management, and construction matters. All known subcontractors performing at least 20 percent of the contract are required to attend this conference. Additional conferences may be established by the Area Engineer for any major subcontractors unknown at the time of the initial conference.

b. Submission by the Contractor of the items listed below will determine the date of the conference. The following items shall be submitted to the Area Engineer in hard copy and electronic (pdf) format for review at least seven (7) calendar days prior to the preconstruction conference:

(1) Accident Prevention Plan

SECTION 01 00 00.00 09 Page 6

(2) Quality Control Plan

(3) Environmental Protection Plan

(4) One copy of the certified Large Notice of Intent (LNOI) for each site

(5) Submittal register

(6) Project Schedule

c. The Contractor shall bring to this conference, in completed form, the following:

(1) Letter of superintendent appointment and authority

(2) List of subcontractors

d. Minutes of this conference will be taken and prepared by the Area Engineer and sent to the Contractor for his concurrence and signature.

1.8 SUBMITTAL OF SUBCONTRACTING PLAN

a. This paragraph does not apply to small business concerns.

b. After bid opening, and within 7 days, the apparent low bidder, upon telephone notification by the Small and Disadvantaged Business Utilization Specialist, shall submit a Small and Disadvantaged Business Subcontracting Plan. The plan shall be submitted in accordance with the Contract Clauses SMALL BUSINESS SUBCONTRACTING PLAN - ALTERNATE I. The person responsible for administering the plan shall be named in paragraph AGENT FOR SUBMITTING SMALL BUSINESS SUBCONTRACTING PLAN of the Representations and Certifications.

1.9 NOTIFICATION OF AREA ENGINEER BEFORE BEGINNING WORK

At least 7 days before beginning work, and at least one day before resuming work after a period of 7 days or more when no work has been performed, the Contractor shall notify U.S. Army Corps of Engineers, Mr.

Jason Overstreet, Area Engineer, Greenwood Area Office, 100 Moore Street, Greenwood, Mississippi 38930-4512, telephone (662) 453-5531 .

1.10 PROHIBITED WORK DURING FLOOD STAGES

Any work performed during flood stages is prohibited unless approved by the Contracting Officer. Any work with the potential to threaten the integrity of the levee will not be allowed. Working in areas of heavy seepage or operations causing pumping of the material on or near the levee are some examples of activities that would be prohibited. Upon notice of forecasted flood stages, Contractor shall take actions to ensure their ongoing work does not impact the levee system. Delays due to flood stages will be considered excusable delays and granted time extensions as provided for under the DEFAULTS clause. No additional compensation will be provided for flood stage delays or impacts except as provided for under DAMAGES to work clause.

1.11 ORDER OF WORK

The work shall be carried on in accordance with the Project Schedule in

SECTION 01 00 00.00 09 Page 7 accordance with SECTION 01 32 01.00 09 PROJECT SCHEDULE. In preparing the Project Schedule, the Contractor shall adhere to the following order of work:

a. Construction of required berm embankment shall begin at is between Sta. 68+00 and proceed continuously downstream until embankment construction is completed to Sta. 300+00. Embankment construction, including vegetation removal of the levee surface, shall not be performed more than 5,000 feet in advance of the beginning station until a section of embankment is complete, and shall not be performed more than 5,000 feet in advance of the completed embankment. Levee crown and berm can be used for hauling operations. Levee crown will be used as the hauling route.

b. Construction borrow area shall be excavated beginning downstream and continuing upstream to the permissible depths and to the full riverside limits shown on the drawings. Contractor will use over-the-road trucks on the levee crown and berm for hauling operations.

c. Existing gravel on levee crown will not be removed at any point during construction. Existing gravel surfacing material shall be removed from each ramp and stockpiled immediately before berm embankment is placed on each ramp.

d. Ramps shall be constructed concurrently with adjacent berm embankment construction.

e. Water control structure, culverts, grading adjacent to the borrow area and farm field road will be constructed as shown in the plans.

g. Levee crown will be resurfaced with an additional 3/8 tons per linear foot (TN/LF)of gravel surfacing after completion of berm embankment construction as shown in the plans. Hauling will not be permited on the resurfaced levee crown. New cattle guards and bedding beams shall be installed after placement of resurfacing material so that resurfacing material is not hauled over the new cattle guards.

1.12 DESIGNATED BILLING OFFICE

The designated billing office for this contract shall be U.S. Army Corps of Engineers, Greenwood Area Office, 100 Moore Street, Greenwood, Mississippi 38930-4512 .

1.13 PAYMENT INVOICES

a. The Federal Acquisition Regulation requires that the "REMIT TO" address on the invoice match the "REMIT TO" address on the contract or a proper notice of assignment. The Payment Office will verify a match of the "REMIT TO" address in the contract and Contractor’s invoice prior to payment. If the addresses do not match, the invoice will be determined improper and returned to the Contractor for correction and resubmission. If an invoice is improperly returned, the original invoice receipt date shall be used as the basis for determining interest to be paid in accordance with the PROMPT PAYMENT ACT.

b. Among other things, the Contract Clause PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS requires that a proper invoice for payment include substantiation of the amounts requested. As required in

SECTION 01 00 00.00 09 Page 8

Office of Management and Budget, 5 CFR Part 1315, September 29, 1999, PROMPT PAYMENT, substantiation of the amount requested for progress payments under construction contracts includes the following:

(1) An itemization of the amounts requested related to the various elements of work required by the contract covered by the payment request;

(2) A listing of the amount included for work performed by each subcontractor under the contract;

(3) A listing of the total amount of each subcontract under the contract;

(4) A listing of the amounts previously paid to each such subcontractor under the contract; and,

(5) Additional supporting data in a form and detail required by the Contracting Officer.

c. Failure to include the above information in a Contractor’s invoice will result in the invoice being considered defective under the provisions of the PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS clause of the contract, and it will be returned to the Contractor for correction and resubmission.

1.14 TEMPORARY PROJECT FENCING

Temporary project fencing as required by Section 4, "Temporary Facilities", paragraph 04.A.04 of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual, is not required on this project.

1.15 AS-BUILT DRAWINGS

This paragraph supplements the Contract Clause SPECIFICATIONS AND DRAWINGS

FOR CONSTRUCTION.

a. As-Built Contract Drawings. The Contractor shall maintain two (2) full-size sets of blueline prints of the contract drawings depicting in red a record of as-built conditions. These drawings shall be maintained in current condition at all times during the entire contract period. The blueline drawings shall be updated daily by the Contractor showing all changes from the contract plans which are made in the work, additional information which might be uncovered in the course of construction, and information for future construction reference (such as debris disposed by burying). For berm construction, the riverside toe of completed berm sections shall be plotted on profiles of construction drawings. Berm toe profiles shall depict elevations of newly constructed slope intersection with natural ground and depressions which extend the toe line between routine section surveys. This information shall be recorded on the blueline prints accurately and neatly by means of details and notes. Each month, prior to submitting a request for progress payment, the Contractor shall review the blueline as-built drawings with the Contracting Officer, and the Contractor shall certify that the as-built drawings are accurate and up-to-date before progress payment is made. The Contractor shall deliver to the Contracting Officer the two (2) original full-size completed sets of as-built marked blueline prints at the time of the final inspection of the project. In

SECTION 01 00 00.00 09 Page 9 addition, the Contractor shall provide two CD-ROM's, each containing a full-size, 400 dpi PDF (portable document format) set of as-built drawings, to the Contracting Officer at the time of final inspection.

The as-built drawings shall be identified by entering the words "AS-BUILT DRAWINGS" in letters at least 3/16-inch high, placed in the lower right corner of each drawing.

b. No separate measurement or payment will be made for providing as-built drawings, electronic drawings and plates, or for any of the work required by this clause, and all costs therefor shall be included in the applicable contract prices contained in the Bidding Schedule.

1.16 PROJECT SIGN

The Contractor shall fabricate, erect and maintain one sign for project identification. The sign shall be displayed and positioned for reading by passing viewers. The exact location is subject to Contracting Officer's approval. Information for the right side of the project sign shall be as follows:

Title: Bolivar County, MississippiFC/MR&T East Bank Mississippi River Levee Seepage Remediation Francis to Round Lake, Item 615-L

Contract No: W912EE-26-B-0XXX

Contractor: (Contractor's name and city)

The project identification sign shall meet the requirements specified in the U.S. Army Corps of Engineers Sign (USACES) Standards Manual, EP 310-1-6a and EP 310-1-6b. A copy of the sign standards manual is available for review at the office of the Vicksburg District Sign Program Manager and questions concerning manufacture and installation of the project identification sign may be addressed to:

Vicksburg District Sign Program Manager (Aaron Posner)

ATTN: CEMVK-OD-MN

4155 Clay Street Vicksburg, MS 39183-3435 Telephone: (601) 631-5287

1.17 MINIMUM REQUIRED INSURANCE

The following paragraph is applicable if the services involved are performed on a Government Installation. Government Installation is defined as property where the Government holds by fee simple title, by construction rights-of-way, or perpetual easement, etc., an interest in real property. See the Contract Clause INSURANCE-WORK ON A GOVERNMENT

INSTALLATION.

a. Workmen's Compensation and Employer's Liability Insurance. The Contractor shall comply with all applicable workmen's compensation Statutes of the State of Mississippi and shall furnish evidence of Employer's Liability Insurance in an amount of not less than $100,000.

SECTION 01 00 00.00 09 Page 10

b. General Liability Insurance. Bodily injury liability insurance in the minimum limits of $500,000 per occurrence on the comprehensive form of policy.

c. Automobile Liability Insurance. Minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. This insurance shall be on the comprehensive form of policy and shall cover the operation of all automobiles used in performance of the contract.

1.18 WORK IN QUARANTINED AREA

The work called for by this contract involves activities in counties quarantined by the Department of Agriculture to prevent the spread of certain plant pests which may be present in the soil. The Contractor agrees that all construction equipment and tools to be moved from such counties shall be thoroughly cleaned of all soil residues at the construction site with water under pressure and that hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, if this contract involves the identification, shipping, storage, testing, or disposal of soils from such quarantined area, the Contractor agrees to comply with the provisions of ER 1110-1-5, "Plant Pest Quarantined Areas and Foreign Soil Samples" attachments, a copy of which will be made available by the Contracting Officer upon request. The Contractor agrees to assure compliance with this obligation by all subcontractors.

1.19 CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of material with specification requirements shall be executed in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

1.20 PROCESS FOR OBTAINING CURRENT REQUIREMENTS OF THE U.S. ARMY CORPS OF

ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL (EM 385-1-1)

Contractors are required to comply with the latest version, and all posted changes, of the U.S. Army Corps of Engineers Safety and Health Requirements Manual in effect on the issue date of this solicitation.

EM 385-1-1 version 2014 and changes are available on the Internet at http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx, Search for EM_385-1-1, then click on EM_385-1-1 2014 english version.

Prior to making an offer, offerors should check the referenced website for the latest changes. No separate payment will be made for compliance with the requirements of this paragraph, or for compliance with other safety requirements of the contract.

SECTION 01 00 00.00 09 Page 11

1.21 SAFETY SIGN

The Contractor shall fabricate, erect and maintain a safety sign at the site, as located by the Contracting Officer. The sign shall be erected as soon as practicable, but not later than 15 calendar days after the date established for commencement of work. The data required shall be current. The safety sign shall meet the requirements specified in the U.S. Army Corps of Engineers Sign (USACES) Standards Manual, EP 310-1-6a and EP 310-1-6b. A copy of the sign standards manual is available for review at the office of the Vicksburg District Sign Program Manager and questions concerning manufacture and installation of the safety sign may be addressed to:

Vicksburg District Sign Program Manager (Jonathan Harrell)

ATTN: CEMVK-OD-MN

4155 Clay Street Vicksburg, MS 39183-3435 Telephone: (601) 631-5287

1.22 ACCIDENT PREVENTION PLAN

Refer to the Contract Clause ACCIDENT PREVENTION (Alternate I). Within 15 days after receipt of award of the contract, an Accident Prevention Plan shall be submitted to the Contracting Officer for review and acceptance.

The plan shall be prepared as specified in Appendix A, "Minimum Basic Outline for Accident Prevention Plans" of EM 385-1-1. In addition to the requirements listed, the Contractor shall also submit the required information on the forms outlined below, which can be found on the Vicksburg District Construction Division home page, http://www.mvk.usace.army.mil/Missions/EngineeringandConstructionDivision.aspx, click on Construction Services Branch, then click on Forms.

a. An executed LMV Form 358-R, "Administrative Plan".

b. An executed MVK Form 385-359-R, "Hazard Analysis" for each definable feature of work.

c. When marine plant and equipment are in use under a contract, the method of fuel oil transfer shall be submitted on LMV Form 414R, "Fuel Oil Transfer-Floating Plant". (Refer to 33 CFR 156 .)

d. The Contractor shall not commence physical work at the site until the plan has been accepted by the Contracting Officer, or his authorized representative. At the Contracting Officer's discretion, the Contractor may submit his Hazard Analysis only for the first phase of construction provided that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase.

Also, refer to Section 1, "Program Management", paragraph 01.B, "Indoctrination and Training" of EM 385-1-1.

1.23 DAILY INSPECTIONS

Refer to Section 01 45 00.00 09 QUALITY CONTROL and the Contract Clause INSPECTION OF CONSTRUCTION. The Contractor shall perform daily safety inspections and record them on the forms approved by the Contracting Officer. Reports of daily inspections shall be maintained at the job site. The reports shall be records of the daily inspections and resulting actions. As a minimum each report shall include the following:

SECTION 01 00 00.00 09 Page 12

a. Phase(s) of construction underway during the inspection.

b. Locations or areas inspections were made.

c. Results of inspection, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

1.24 ACCIDENT INVESTIGATIONS AND REPORTING

Refer to EM 385-1-1, Section 1, "Program Management", paragraph 01.D, "Accident Reporting and Recordkeeping". Accidents shall be investigated and reports completed by the immediate supervisor of the employee(s) involved and reported in writing to the Contracting Officer or his representative within one working day after the accident occurs.

1.25 ACCOMMODATIONS FOR GOVERNMENT REPRESENTATIVES

a. Accommodations. The Contractor shall furnish and maintain a temporary building for the exclusive use of the Government Representatives at an approved location. The building shall be of light, but weatherproof construction, approximately 240 square feet in size with not less than 7 feet of headroom. The building shall either be divided into two separate rooms or have a lockable storage closet on the opposite end from the workbench. It shall have a substantial workbench along one side and sufficient number of windows to admit ample working light. Windows shall be arranged to open and to be securely fastened from the inside. The door shall be of wood panel or solid core construction and be equipped with a padlock and heavy duty hasp bolted to the door. Insect screens shall be provided for windows. Glass panels in windows shall be equipped with bars or heavy mesh screens which will prevent easy access to the building through these panels. The Contractor shall heat the building by means of heaters and shall cool the building by means of an air conditioning unit. Electric current shall also be provided for operation of lights, appliances, computers, and electric calculators at 115 volts AC. Electric current may be provided by use of a portable generator.

A minimum of four wall outlets and two ceiling drops shall be provided in the building. Electrical surge protection is required at all wall outlets. One office desk and a minimum of two chairs shall be provided in the building. Internet service shall be provided capable of a minimum transfer data rate of 10 Mbps for downloading and 2 Mbps for Uploading. When available, a data line shall be provided to the facility, capable of providing the required service above. When there is an unavailability of a hard data line, a wireless service shall be provided to the Government capable of providing the data transfer indicated above. Permanent toilet facilities shall be provided within the building. The building shall remain the property of the Contractor and upon completion of all work under the contract shall be removed as provided in the Contract Clause OPERATIONS AND STORAGE AREAS. An office trailer meeting the above requirements will be acceptable.

b. Janitor Services. The Contractor shall furnish daily janitorial services for the above office and perform any required maintenance of subject facility and adjacent grounds during the entire life of the contract. Toilet facilities shall be clean and sanitary at all times.

Services shall be performed at such a time and in such a manner to

SECTION 01 00 00.00 09 Page 13 least interfere with the operations but will be accomplished only when the office is in daily use. The Contractor shall also provide daily trash collection and cleanup of the building and adjacent outside areas, and shall dispose of all discarded debris in a manner approved.

c. No separate measurement or payment will be made for providing and maintaining the prescribed building, accommodations, utilities and janitor services, and all costs associated therewith shall be distributed throughout the existing bid items. Should the Contractor refuse, neglect, or delay compliance with the above requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amount due or to become due the Contractor.

1.26 MACHINERY AND MECHANIZED EQUIPMENT

Machinery and mechanized equipment used under this contract shall comply with the following:

a. When mechanized equipment is operated on floating plant, the Contractor shall provide positive and acceptable means of preventing this equipment from moving or falling into the water. The type of equipment addressed by this clause includes front-end loaders, bulldozers, trucks (both on- and off-road), backhoes, hydraulic excavators (track hoes), and similar equipment. If the Contractor plans to use such equipment on floating plant, an activity hazard analysis must be developed for this feature of work. The plan must include a detailed explanation of the type or types of physical barriers, curbs, structures, etc., which will be incorporated to protect the operator and prevent the equipment from entering the water. Nonstructural warning devices may be considered for situations where the use of structural barriers is determined to be impracticable. The activity hazard analysis must thoroughly address the procedure and be submitted to the Corps for review and acceptance prior to start of this feature of work.

b. The stability of crawler, truck, and wheel-mounted cranes shall be assured.

(1) The manufacturer's load-rating chart may be used to determine the maximum allowable working load for each particular crane's boom angle provided a test load, with a boom angle of 20 degrees, confirms the manufacturer's load-rating table.

(2) Stability tests are required if:

(i) there is no manufacturer's load-rating chart securely fixed to the operator's cab;

(ii) there has been a change in boom or other structural member;

or

(iii) there has been a change in the counterweight.

The test shall consist of lifting a load with the boom in the least stable undercarriage position and at an angle of 20 degrees above the horizontal. The test shall be conducted under close supervision on a firm, level surface. The load that tilts the machine shall be identified as the test load. The test load

SECTION 01 00 00.00 09 Page 14 moment (in ft-lbs) shall then be calculated by multiplying the horizontal distance (in feet) from the center of rotation of the machine to the test load, times the test load (in lbs).

Three-fourths of this test-load moment shall then be used to compute the maximum allowable operating loads for the boom at 20, 40, 60, and 80 degrees above horizontal. From these maximum allowable operating loads, curve shall be plotted and posted in the cab of the machine in sight of the operator. These values shall not be exceeded except in the performance test described below. The test load shall never exceed 100 percent of the manufacturer's maximum rated capacity.

(3) In lieu of the test and computations above, the crane may be load tested for stability at each of the four boom positions listed above.

c. Performance tests shall be performed in accordance with Section 18.G, "Machinery and Mechanized Equipment" of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual, except as specified below. Performance tests shall be conducted after each stability test, when the crane is placed in service on a project, and at least every 12 months.

(1) When conducting a performance load test which is required of a new crane or a crane in which load sustaining parts have been altered, replaced, or repaired (excluding replacement of the rope), the test load shall be as specified in ASME/ANSI B30 Series. That is, for overhead, gantry, portal, pillar, tower, monorail, and underhung cranes, the test load shall not exceed 125 percent of the manufacturer's load rating capacity chart at the configuration of the test; and for hammerhead tower, mobile, and floating cranes and boom trucks, the test load shall not exceed 110 percent of the manufacturer's load rating capacity chart at the configuration of the test.

(2) When conducting a performance load test which is required because a crane is reconfigured, or reassembled after disassembly, or because the crane requires an annual load test, the test loads shall not exceed 100 percent of the manufacturer's load rating capacity chart at the configuration of the test.

(3) All load tests are required to be conducted in accordance with the manufacturer's recommendations.

d. Inspections shall be made which will ensure a safe and economical operation of both cranes and draglines with inspection documented.

Copies of the inspections and tests shall be available at the job site for review. All stability and performance tests on cranes and all complete dragline inspections shall be witnessed by the Contracting Officer or his authorized representative.

e. A complete dragline inspection shall be made:

(1) at least annually;

(2) prior to the dragline being placed in operation; and

(3) after the dragline has been out of service for more than 6 months.

SECTION 01 00 00.00 09 Page 15

f. All heavy equipment moved onto the worksite shall be inspected for compliance with this contract. The CEMVK-SO Inspection forms attached at the end of this section shall be completed by the Contractor. All completed forms, including abatement schedule of any violations, shall be maintained at the job site for continued review and update as needed.

1.27 VEHICLE WEIGHT LIMITATIONS

Vehicle weight limitations for operation on rural roads and bridges may affect the prosecution of work in this contract. The Contractor will be responsible for obtaining all necessary licenses and permits in accordance with the Contract Clause PERMITS AND RESPONSIBILITIES. Current information regarding road and bridge weight limits may be obtained by contacting the Mississippi Department of Transportation and the president of the county Board of Supervisors for the counties through which equipment and materials will be transported as a result of this contract.

1.28 PUBLIC AND PRIVATE UTILITIES

a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not remove or disturb any public or private utilities. Such removals, alterations, and relocations, where necessary, will be made by others. The locations, if any, shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.

b. The attention of the Contractor is directed to the possibility that he may encounter, within the right-of-way limits, utilities, some of which may be buried, and the existence of which is presently not known. Should any such utilities be encountered, the Contractor shall immediately notify the Contracting Officer so that he may determine whether they shall be removed, relocated, or altered. After such determination is made, the Contractor shall, if so directed by the Contracting Officer, remove, relocate, or alter them as required, and an equitable adjustment will be made in accordance with the Contract Clause CHANGES. In event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latter's removal, alteration, or relocation operations in accordance with the Contract Clause OTHER CONTRACTS.

1.29 DAMAGE TO WORK

a. The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause PERMITS AND RESPONSIBILITIES. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood (see Section 00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS, paragraph PHYSICAL DATA, subparagraph FLOODS) or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make repairs as ordered by the Contracting Officer and full compensation for such repairs to permanent work will be made at the applicable contract unit or lump sum prices as fixed and established

SECTION 01 00 00.00 09 Page 16 in the contract. If, in the opinion of the Contracting Officer, for any part of such damaged permanent work, there is no applicable contract unit or lump sum price, then an equitable adjustment pursuant to the Contract Clause CHANGES will be made as full compensation for the repairs for that part of the permanent work for which there is no applicable contract unit or lump sum price.

b. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment, and plant shall be repaired to the satisfaction of the Contracting Officer, at the Contractor's expense, regardless of the cause of such damage.

1.30 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Contract Clause DEFAULT (FIXED PRICE CONSTRUCTION). In order for the Contracting Officer to award a time extension under this paragraph, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's project schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON FIVE (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

(NA) (NA) (NA ) (NA) (NA) (7 ) (6 ) (7 ) ( 1) (3 ) ( 4) (9 )

c. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.