B.08.Solicitation Amendment W912EE26RA0030004 SF 30.pdf

PDF 6 MB Posted

Attached to
TENSAS PARISH, LOUISIANA, LEVEE ENLARGEMENT AND BERMS, ITEMS 393-R, FC/MR&T, WBMRL
Solicitation number
W912EE26RA003
Issued by

About this file

This document is a Standard Form 30 (SF 30) Amendment to Solicitation W912EE26RA003 for the Tensas Parish, Louisiana Levee Enlargement and Berms project. Amendment 0004, issued on 29 December 2025, revises specifications for sections 01 57 23.01 09, 33 42 29.01 09, and 31 24 00.00 09, and updates drawings C-503-1. The amendment modifies the project's technical requirements, with changes noted by underlining new text and striking through deleted text.

The solicitation is part of a Multiple Award Task Order Contract (MATOC) for Mississippi River Levees, with proposals accepted only from four pre-selected contractors: Affolter Contracting Company, B&K Construction Company, Circle LLC, and Tarpan Construction. The project involves levee enlargement and berm construction in Tensas Parish, Louisiana, with work to be completed within 345 calendar days after the notice to proceed. The contract includes various construction activities such as clearing, embankment, surfacing, erosion control, and environmental protection, with a total estimated quantity of work detailed in the bidding schedule.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

INFORMATION FROM TO

Offer Guarantee Required true

Section 00 01 15 - List of Drawing Sheets

The attachments table has changed from:

Identi fier

Document Name

Document Description Referen ce Ident ifier

Date Line Item

Page Num bers

Docu ment Type

Provi ded Unde r Sep arate Cove r

0001 A.02.PUBLI

SH_AM_00

02 Specs_

W912EE26

RA003

Statement of Work 03 Dec

Attac hmen t

No

0002 A.02.MRL

Item 393R_ Solicitation-

PLANS

26RA003

Drawings 13 Nov

Attac hmen t

No

0003 B.04.Davis Bacon Wage Deter mination_L A20250004

Wage Determination 03 Dec

Attac hmen t

No

W912EE26RA0030004

Tensas Parish_3 Dec 2025

0004 A.02.

AM_0002

PLAN SHE

ETS_26RA

Drawings Amend ment 0002 - Amende d Drawi ng Sheets

03 Dec

Attac hmen t

No

To:

Identi fier

Document Name

Document Description Referen ce Ident ifier

Date Line Item

Page Num bers

Docu ment Type

Provi ded Unde r Sep arate Cove r

0001 A.02.PUBLI

SH_AM_00

04 Specs_

W912EE26

RA003

Statement of Work 29 Dec

Attac hmen t

No

0002 A.02.MRL

Item 393R_ Solicitation-

PLANS

26RA003

Drawings 13 Nov

Attac hmen t

No

0003 B.04.Davis Bacon Wage Deter mination_L A20250004 Tensas Parish_3 Dec 2025

Wage Determination 03 Dec

Attac hmen t

No

0004 A.02.

AM_0002

PLAN SHE

ETS_26RA

Drawings Amend ment 0002 - Amende d Drawi ng Sheets

03 Dec

Attac hmen t

No

0005 A.02.AM

0004 Drawi ngs_MRL Item 393R_

CSCTYP-C-

503amd4

Drawings Amend ment 0004 Dr awings

29 Dec

Attac hmen t

No

The following contract documents were added:

A.02.AM 0004 Drawings_MRL Item 393R_CSCTYP-C-503amd4 A.02.PUBLISH_AM_0004 Specs_W912EE26RA003

The following contract documents were deleted:

A.02.PUBLISH_AM_0002 Specs_W912EE26RA003

The following contract documents Page Counts were changed:

DOCUMENT PAGE COUNTS

DOCUMENT NAME FROM TO

A.02.PUBLISH_AM_0004 Specs_W912EE26RA003 none

TENSAS PARISH, LOUISIANA

LEVEE ENLARGEMENT AND BERMS, ITEMS 393-R

FC/MR&T, WBMRL

BIDDING SCHEDULE

ITEM DESCRIPTION EST

QTY

U/M UNIT

PRICE

AMOUNT

0001 MOBILIZATION AND DEMOBILIZATION 1 JOB FOR $______

0002 CLEARING AND GRUBBING 1 JOB FOR $______

0003 LEVEE EMBANKMENT, SEMICOMPACTED 574,880 CY $______ $______

0004 SEEPAGE BERM EMBANKMENT,

UNCOMPACTED

179,000 CY $______ $______

0005 STABILITY BERM EMBANKMENT,

SEMICOMPACTED

81,000 CY $______ $______

0006 RAMPS

1 JOB $______ $______

0007 MOWING, TURFING, AND EROSION

CONTROL MATTING

1 JOB $______ $______

0008 REPLACEMENT OF EXISTING GRANULAR

SURFACING

1 JOB FOR $______

0009 LEVEE AND RAMPS SURFACING, CRUSHED

STONE

14,350 TN $______ $______

0010 ENVIRONMENTAL PROTECTION FEATURES 1 JOB FOR $______

0011 CATTLE GUARDS 1 JOB FOR $______

0012 CULVERTS

1 JOB FOR $______

0013 DITCHES 1 JOB FOR $______

Total $______

W912EE26RA003

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS

01 22 00.00 09 MEASUREMENT AND PAYMENT

01 32 01.00 09 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 09 QUALITY CONTROL

01 45 00.15 09 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 20.00 09 ENVIRONMENTAL PROTECTION

01 57 23.01 09 STORM WATER POLLUTION PREVENTION PLAN

DIVISION 05 - METALS

05 59 00.00 09 CATTLE GUARDS

DIVISION 31 - EARTHWORK

31 11 00.00 09 CLEARING AND GRUBBING

31 23 00.00 09 EXCAVATION

31 24 00.00 09 EMBANKMENT

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 15 00.00 09 LEVEE SURFACING

32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT

32 92 04.00 09 EROSION CONTROL MATTING

DIVISION 33 - UTILITIES

33 42 29.01 09 CULVERTS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1 Revised by Amendment 0004

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 80 00.00 09

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1.3 LIQUIDATED DAMAGES-CONSTRUCTION

1.4 EXCEPTION TO LIQUIDATED DAMAGES

1.5 CONTRACT DRAWINGS AND SPECIFICATIONS

1.6 CORRESPONDENCE AND ELECTRONIC COMMUNICATION

1.7 (S-102) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR

PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS

1.8 PERFORMANCE OF WORK BY THE CONTRACTOR

1.9 WORK TO BE PERFORMED BY CONTRACTOR'S OWN ORGANIZATION

1.10 PHYSICAL DATA

1.11 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION

1.12 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.13 OBSTRUCTION OF NAVIGABLE WATERWAYS

1.14 GENERAL SECURITY REQUIREMENTS AND GUIDANCE

1.15 SUSPICIOUS ACTIVITY REPORTING TRAINING (E.G., IWATCH, CORPSWATCH,

OR SEE SOMETHING, SAY SOMETHING)

1.16 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM

1.17 NON-U.S. CITIZENS WORKING ON GOVERNMENT CONTRACTS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

DOCUMENT 00 80 00.00 09 Page 1

SECTION 00 80 00.00 09

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule

1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 345 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.211-10)

1.3 LIQUIDATED DAMAGES-CONSTRUCTION

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,250.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (FAR 52.211-12)

1.4 EXCEPTION TO LIQUIDATED DAMAGES

Since the Contractor's obligations specified in Section 32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT may extend beyond the completion time specified in paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, these periods and the additional work, if required, will be exempt from liquidated damages provided all other work has been completed.

1.5 CONTRACT DRAWINGS AND SPECIFICATIONS

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall --

DOCUMENT 00 80 00.00 09 Page 2

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general --

(1) Large-scale drawings shall govern small scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the INDEX TO DRAWINGS shown on Drawing No.

G-001 entitled COVER SHEET.

(DFARS 252.236-7001)

1.6 CORRESPONDENCE AND ELECTRONIC COMMUNICATION

For ease and speed of communications, both the Government and Contractor shall exchange correspondence and all other documents duplicate in both hard paper copy and electronic format. Inclusion of an electronic copy is in addition to any other parts of the contract that may specify a minimum number of hard copies to be submitted, such as for shop drawing transmittals. Electronic submission can be accomplished by one of the following methods: email, file upload to the following DoD Safe website https://safe.apps.mil/, or through the Resident Management System - Contractor Mode (RMS-CM) software interface with the Resident Management System (RMS). Format for electronic submissions will be in portable document format (.pdf). File naming will be determined by the Contracting Officer and presented at the Preconstruction Conference. Documents include all general correspondence, administrative plans, all material submittals including shop drawings, progress schedules, submittal registers, requests for information (RFIs), Quality Control (QC) test results, pay requests, etc. Paper documents will govern, in the event of discrepancy with the electronic version. Generally, paper documents will also govern where effective receipt dates are required, such as contractor claims submitted under the Disputes clause of the contract and progress payment requests. However in the case of administrative plans, shop drawings and other submittals transmitted for government review, both the electronic and hard copies are required to begin the review process, so the effective date of receipt will be the date when both the electronic

DOCUMENT 00 80 00.00 09 Page 3 and hard copies are received by the government.

1.7 (S-102) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR

PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS

The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8, PAYROLLS AND BASIC RECORDS and FAR 52.222-13, COMPLIANCE

WITH DAVIS-BACON AND RELATED ACT REGULATIONS.

If the contractor elects to use an electronic Davis-Bacon payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon and related Act regulations.

When the contractor uses an electronic Davis-Bacon payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic Davis-Bacon payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Davis-Bacon and related Act regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.

The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria: commercially available; compliant with appropriate Davis Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at http://rmssupport.helpserve.com/) for export in an Excel spreadsheet to be imported into the Contractor's Resident Management System - Contractor Mode (RMS-CM), that in turn shall export payroll data to the Government's Resident Management System (RMS);

demonstrated security of data and data entry rights; ability to produce contractor-certified electronic versions of weekly payroll data; ability to identify erroneous entries and track the data/time of all versions of the certified Davis Bacon payrolls submitted to the government over the life of the contract; capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic Davis-Bacon payroll processing system shall be provided to the Government during contract closeout.

All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid/proposed or reimbursed item under this contract.

FAR 52.222-8 and FAR 52.222-13

DOCUMENT 00 80 00.00 09 Page 4

1.8 PERFORMANCE OF WORK BY THE CONTRACTOR

The Contractor shall perform on the site and with its own organization, work equivalent to at least twenty (20) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government. (FAR 52.236-1)

1.9 WORK TO BE PERFORMED BY CONTRACTOR'S OWN ORGANIZATION

Within 10 days after award, the successful Bidder/Contractor must furnish the Contracting Officer a description of the items of work which will be performed with its own forces and the estimated cost of those items. (See paragraph PERFORMANCE OF WORK BY THE CONTRACTOR.)

1.10 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and borings.

(b) Weather Conditions. Information with respect to temperatures and precipitation may be obtained from the National Weather Service.

(c) Transportation Facilities.

(1) Roads. Interstate 20, Louisiana Highway No. 65, and local roads serve the general area.

(2) Railroads. The Contractor is responsible for determining the availability of railroad service.

(d) Floods.

(1) High water stages or events are not to be considered a "flood," and damages resulting therefrom are not compensable under Section 01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS, paragraph DAMAGE TO WORK unless river or stream stages exceed channel capacity and overtop the natural or artificial banks. High water stages and/or high water events at stages below ordinary top bank of a river or stream are not floods, even if such water reaches the project. For example, water flowing through or over low points in the river or stream bank, such as drains, are not floods.

(e) Additional Data. Additional data consisting of additional cross sections, records of borings, and boring samples are available for

DOCUMENT 00 80 00.00 09 Page 5 inspection at:

U.S. Army Engineer District, Vicksburg 4155 Clay Street

Vicksburg, Mississippi 39183-3435

(FAR 52.236-4)

1.11 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION

(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.

(1) Sixty percent of the lump sum price upon completion of the Contractor's mobilization at the work site.

(2) The remaining forty percent upon completion of demobilization.

(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in subparagraphs (a)(1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.

(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of--

(i) Actual mobilization costs at completion of mobilization;

(ii) Actual demobilization costs at completion of demobilization;

and

(iii) The remainder of this item in the final payment under this contract.

(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.

(DFARS 252.236-7004)

1.12 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

(a) This special contract requirement does not apply to terminations. See 52.249-500, Basis for Settlement of Proposals and FAR Part 49.

(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the Contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region III.

DOCUMENT 00 80 00.00 09 Page 6

Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the Contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

(USACE Acquisition Instruction ("UAI") 31.105-101)

NOTE: EP-1110-1-8 , "Construction Equipment Ownership and Operating Expense Schedule" is available on the Internet at http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx, then search for EP 1110-1-8, then click on the link and then choose EP_1110-1-8_Vol-03.pdf or may be purchased from the Government Printing Office on CD-ROM by calling (202) 512-1800.

1.13 OBSTRUCTION OF NAVIGABLE WATERWAYS

(a) The Contractor shall-

(1) Promptly recover and remove any material, plant, machinery, or appliance which the Contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation;

(2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer; and

(3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.

(b) The Contracting Officer may--

(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and

(2) Deduct the cost of removal from any monies due or to become due to the Contractor; or

(3) Recover the cost of removal under the Contractor's bond.

DOCUMENT 00 80 00.00 09 Page 7

(c) The Contractor's liability for the removal of a vessel wrecked or sunk without fault or negligence is limited to that provided in Sections 15, 19, and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C. 410 et. seq). (DFARS 52.236-7002)

1.14 GENERAL SECURITY REQUIREMENTS AND GUIDANCE

The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts.

The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations.

Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures.

The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures, to include identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

1.15 SUSPICIOUS ACTIVITY REPORTING TRAINING (E.G., IWATCH, CORPSWATCH, OR

SEE SOMETHING, SAY SOMETHING)

All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

1.16 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM

Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject

DOCUMENT 00 80 00.00 09 Page 8 to change) to meet the contract employment eligibility requirements.

Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/ eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

1.17 NON-U.S. CITIZENS WORKING ON GOVERNMENT CONTRACTS

Government Approval MUST be obtained PRIOR to any non-U.S. Citizen being permitted to work on a government contract. The Contractor must submit a letter requesting approval via the Contracting Officer/Contracting Officer Representative to the Vicksburg District Security Officer. The letter must include the contract number, period of performance, location(s) of work performance and attach a copy of the individual’s passport and visa/work authorization documents.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

DOCUMENT 00 80 00.00 09 Page 9

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00.00 09

GENERAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 PARTNERING

1.3 RIGHTS-OF-WAY

1.4 SURVEY LAYOUT AND MARKING FOR RIGHTS-OF-WAY AND CONSTRUCTION

1.5 APPROVAL OF CONTRACTOR-FURNISHED RIGHTS-OF-WAY

1.6 PRECONSTRUCTION CONFERENCE

1.7 SUBMITTAL OF SUBCONTRACTING PLAN

1.8 NOTIFICATION OF AREA ENGINEER BEFORE BEGINNING WORK

1.9 PROHIBITED WORK DURING FLOOD STAGES

1.10 ORDER OF WORK

1.11 DESIGNATED BILLING OFFICE

1.12 PAYMENT INVOICES

1.13 TEMPORARY PROJECT FENCING

1.14 AS-BUILT DRAWINGS

1.15 PROJECT SIGN

1.16 MINIMUM REQUIRED INSURANCE

1.17 WORK IN QUARANTINED AREA

1.18 CERTIFICATES OF COMPLIANCE

1.19 PROCESS FOR OBTAINING CURRENT REQUIREMENTS OF THE U.S. ARMY CORPS

OF ENGINEERS SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS (EM

385-1-1)

1.20 SAFETY SIGN

1.21 DAILY INSPECTIONS

1.22 ACCIDENT INVESTIGATIONS AND REPORTING

1.23 ACCOMMODATIONS FOR GOVERNMENT REPRESENTATIVES

1.24 MACHINERY AND MECHANIZED EQUIPMENT

1.25 VEHICLE WEIGHT LIMITATIONS

1.26 PUBLIC AND PRIVATE UTILITIES

1.27 DAMAGE TO WORK

1.28 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.29 EXCLUSION OF PERIODS IN COMPUTING COMPLETION SCHEDULES

1.30 CONTROL OF ACCESS TO CONSTRUCTION AREAS

1.31 MAINTENANCE OF TRAFFIC

1.32 HARBOR MAINTENANCE FEE

1.33 COOPERATION WITH OTHER CONTRACTORS

1.34 ACCEPTANCE OF COMPLETED WORK

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

SECTION 01 00 00.00 09 Page 1

SECTION 01 00 00.00 09

GENERAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

19 CFR 24.24 Harbor Maintenance Fee

1.2 PARTNERING

The Government encourages formation of informal project partnerships on all projects. A project partnership strives to utilize a cooperative working relationship to jointly establish and effectively reach mutual project execution goals. The partnering process will in no way relax or stiffen the requirements of the contract, but will enhance the likelihood of success through improved working relationships and joint risk management. The possibility of an informal partnership may be discussed at the Pre-construction Conference for this project.

1.3 RIGHTS-OF-WAY

a. The rights-of-way for Contractor performance under this contract, within the limits indicated on the drawings, will be provided by the Government without cost to the Contractor. It is the Contractor's responsibility to carefully review and determine the scope of the rights-of-way. Any questions should be clarified with the Government prior to use. If these rights-of-way are used by the Contractor, he shall, at his own expense, do all work necessary to make such rights-of-way suitable for safe travel to and from the worksite. Upon completion of the Contractor's work, any such rights-of-way furnished by the Government shall be left in a condition satisfactory to the Contracting Officer.

b. When so directed by the Contracting Officer, the Contractor shall, without expense to the Government, promptly vacate and clean up any part of the Government grounds or rights-of-way that have been allotted to or have been in use by the Contractor.

c. The Contractor shall not obstruct any existing roads or any other means of existing ingress or egress on lands controlled by the United States except with written permission of the Contracting Officer and shall maintain such roads and other means of ingress or egress in as good condition as exists at the time of commencement of work

SECTION 01 00 00.00 09 Page 3 performance under this contract.

d. The Contractor shall procure, without expense to the Government, all additional lands, access roads, rights-of-way, and any other property rights necessary for his use in the performance of the work or as required by his method of operation. The Contractor shall provide the Contracting Officer with an authenticated copy of the conveyance under which the Contractor acquired such property rights, prepared and executed in accordance with the laws of the State in which the land is located. The Contractor shall also obtain from the property owners and present to the Contracting Officer a release of all claims against the Government which may result from the Contractor's use or possession of such real estate or property rights. The written conveyance and release shall be provided to the Contracting Officer prior to the Contractor's use of Contactor obtained real estate or property rights. If temporary rights-of-way are obtained by the Contractor the period of time for those rights shall coincide with Section 00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS, paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, plus a reasonable time for any extension granted for the completion of the work. Any agreements or permits with levee boards, counties, parishes, municipalities, or other political subdivisions for moving material and equipment will be the responsibility of the Contractor and shall be obtained at no expense to the Government. Any delays to the Contractor resulting from delays in procuring access roads, rights-of-way, permits, or other real estate and property rights necessary for moving material and equipment for his work under this contract will not be a basis for any claim for increase in the cost of this contract. The Contractor shall make his own investigations to determine the conditions, restrictions and difficulties which may be encountered in acquiring such real estate, rights-of-way, or other property rights and in the transportation of material and equipment. In addition, the Contractor shall be solely liable for any and all damages and claims of any nature whatsoever arising from, related to, or growing out of the acquisition and use of this real estate, rights-of-way, property rights, etc.

e. Notwithstanding any language or drawings to the contrary in this contract, the United States will not provide access or rights-of-way over any public lands and will not be responsible for acquiring such.

f. The Contractor shall repair at no expense to the Government, any and all damage to any existing roads or other means of existing ingress or egress when such damage is a result of his operations under this contract.

1.4 SURVEY LAYOUT AND MARKING FOR RIGHTS-OF-WAY AND CONSTRUCTION

The contractor shall be required to obtain the services of a licensed professional surveyor that is licensed in the state of contract performance to perform the following:

a. Field verify all control before start of construction activities.

The contractor's surveyor shall be required to document any discrepancies discovered and any additional control that is required to facilitate construction activities. This information shall be submitted in writing to the Contracting Officer prior to initiating construction activities.

SECTION 01 00 00.00 09 Page 4

Any discrepancy submitted to the Contracting Officer shall include, as a minimum, the following information:

(1) The methods used to collect the data. That is VRS, GPS static, RTK, traverse, and /or levels.

(2) The control point used to compute the data, including Northing, Easting and Elevation.

(3) The processed files and reports.

(4) The raw data files.

(5) Copies of field books used to do the survey.

b. The Contractor shall layout and mark the rights-of-way limits as indicated on the drawings prior to beginning any other work, unless otherwise approved. The marking shall be placed at intervals approved by the Contracting Officer. The rights-of-way limits shall be marked by stakes, flagging or other approved means. The marking shall be highly visible from a distance of at least 100 feet, and shall be maintained for the duration of the contract. If the rights-of-way marking should fade significantly in color, become damaged or lost as a result of the Contractor's operation or as a result of vandalism, or in any other way cease to function as a highly visible marker of the rights-of-way limits, the Contractor shall layout and restore the marking to the original condition. After all work is complete and upon approval of the Contracting Officer, the Contractor shall remove all marking. No separate payment will be made for layout, marking and maintaining the rights-of-way limits or for removing the marking.

c. Crown stakes referenced to the project centerline shall be placed at 100 foot intervals and at event points along the centerline alignment of the project. These stakes shall be labeled with the station number and proposed fill elevation. The stakes shall be maintained at a minimum on a monthly basis for all reaches under construction.

d. Cut and fill stakes shall be placed on all toe of slopes at 200 foot intervals at both the toe of berms and the toe of levee. The stakes shall be labeled with the proposed slope, indicate the direction of slope, and the horizontal distance from centerline. The stakes shall be maintained at a minimum on a monthly basis for all reaches under construction.

e. Stakes shall be placed at the midpoint or breakpoint of the slopes at 200 foot intervals. The midpoint stakes or breakpoint shall be labeled with the proposed grade elevation at the midpoint and the horizontal distance from the centerline levee enlargement. The stakes shall be maintained at a minimum on a monthly basis for all reaches under construction.

f. No separate payment will be made for layout, marking and maintaining the rights-of-way limits or for removing the marking.

1.5 APPROVAL OF CONTRACTOR-FURNISHED RIGHTS-OF-WAY

In addition to the requirements found in paragraph RIGHTS-OF-WAY, subparagraph d., pertaining to additional lands, access roads, or

SECTION 01 00 00.00 09 Page 5 rights-of-way, the Government reserves the right to approve or disapprove the Contractor's use of additional lands, access, or rights-of-way dependent on environmental or cultural resource impacts and the Contractor's compliance under the Contract Clause PERMITS AND RESPONSIBILITIES for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. Environmental and cultural resource impacts that could be basis for disapproval include, but are not limited to, clearing of additional trees, destruction of wildlife habitat, fill or other disturbance of wetlands, and disturbance of cultural sites.

1.6 PRECONSTRUCTION CONFERENCE

a. A preconstruction conference will be arranged by the Area Engineer as soon after contract award as possible, and the conference will be conducted before work is allowed to commence. The Area Engineer will notify the Contractor of the time, date, and location for the meeting. At this conference, the Contractor will be oriented with respect to contract administration procedures, lines of authority, opportunity for formation of project partnerships including joint risk management, and construction matters. All known subcontractors performing at least 20 percent of the contract are required to attend this conference. Additional conferences may be established by the Area Engineer for any major subcontractors unknown at the time of the initial conference.

b. Submission by the Contractor of the items listed below will determine the date of the conference. The following items shall be submitted to the Area Engineer in hard copy and electronic (pdf) format for review at least seven (7) calendar days prior to the preconstruction conference:

(1) Accident Prevention Plan

(2) Quality Control Plan

(3) Environmental Protection Plan

(4) Six copies of the certified Large Construction Notice of Intent (LCNOI) for each site

(5) Submittal register

(6) Network Analysis System

c. The Contractor shall bring to this conference, in completed form, the following:

(1) Letter of superintendent appointment and authority

(2) List of subcontractors

d. Minutes of this conference will be taken and prepared by the Area Engineer and sent to the Contractor for his concurrence and signature.

1.7 SUBMITTAL OF SUBCONTRACTING PLAN

a. This paragraph does not apply to small business concerns.

SECTION 01 00 00.00 09 Page 6

b. After bid opening, and within 7 days, the apparent low bidder, upon telephone notification by the Small and Disadvantaged Business Utilization Specialist, shall submit a Small and Disadvantaged Business Subcontracting Plan. The plan shall be submitted in accordance with the Contract Clauses SMALL BUSINESS SUBCONTRACTING PLAN - ALTERNATE I. The person responsible for administering the plan shall be named in paragraph AGENT FOR SUBMITTING SMALL BUSINESS SUBCONTRACTING PLAN of the Representations and Certifications.

1.8 NOTIFICATION OF AREA ENGINEER BEFORE BEGINNING WORK

At least 7 days before beginning work, and at least one day before resuming work after a period of 7 days or more when no work has been performed, the Contractor shall notify U.S. Army Corps of Engineers, Mr.

Robin Blake, Chief, Vidalia Area Office, 100 Advocate Row, Vidalia, Louisiana 71373-3032, telephone (318) 336-5226 .

1.9 PROHIBITED WORK DURING FLOOD STAGES

Any work performed during flood stages is prohibited unless approved by the Contracting Officer. Any work with the potential to threaten the integrity of the levee will not be allowed. Working in areas of heavy seepage or operations causing pumping of the material on or near the levee are some examples of activities that would be prohibited. Upon notice of forecasted flood stages, Contractor shall take actions to ensure their ongoing work does not impact the levee system. Delays due to flood stages will be considered excusable delays and granted time extensions as provided for under the DEFAULTS clause. No additional compensation will be provided for flood stage delays or impacts except as provided for under DAMAGES to work clause.

1.10 ORDER OF WORK

The work shall be carried on in accordance with the Network Analysis System (schedule) required by paragraph (a) of the Contract Clause SCHEDULES FOR CONSTRUCTION CONTRACTS. In preparing the Network Analysis System (schedule), the Contractor shall adhere to the following order of work:

a. Construction of required levee and berm embankment is located between Sta. 5866+00 to Sta. 6129+01. Berm construction may begin concurently with the start of levee embankment construction.

Embankment construction, including vegetation removal of the levee surface, shall not be performed more than 5,000 feet in advance of the beginning station until a section of embankment is complete, and shall not be performed more than 5,000 feet in advance of the completed embankment.

b. Existing gravel and cattle guards shall not be removed until embankment construction reaches the approximate elevation of the adjacent existing levee crown. No more than 2,000 feet of levee crown shall be without surfacing, either new or existing, at any time.

Existing gravel surfacing material shall be removed from each ramp and stockpiled immediately before embankment is placed on each ramp.

SECTION 01 00 00.00 09 Page 7 c.Levee surfacing shall not be removed from the levee crown 45 days prior to the beginning of the exclusion periods (Paragraph EXCLUSION

OF PERIODS IN COMPUTING COMPLETION SCHEDULES).

d. No section of levee crown or ramp shall be left without surfacing during the exclusion periods. Temporary surfacing will be provided at the Contractor's expense on any uncompleted reach of levee if the work progress has ceased or prior to entering an exclusion period. The term "work progress has ceased" is defined by failure of the Contractor to pursue work progress when conditions are suitable.

e. The stockpiled existing levee surfacing may be used as temporary surfacing during period that work progress has ceased and during the excluded periods. Any temporary levee surfacing must be placed to the density requirements specified for new levee surfacing. Temporary surfacing shall be removed and re-stockpiled upon resumption of work.

f. Ramps shall be constructed concurrently with adjacent levee embankment construction.

g. Existing levee gravel shall be removed from the stockpile and placed on the new levee crown after each reach of levee embankment has been completed, and before levee embankment has been completed more than 2,000 feet in advance of the reach that has already received existing gravel.

h. New surfacing material shall be placed on completed embankment so that the completed new surfacing shall be no less than 3,000 feet and no more than 5,000 feet behind the completion of the levee embankment. New cattle guards and bedding beams shall be installed after placement of new surfacing material so that new surfacing material is not hauled over the new cattle guards.

i. The existing levee crown shall not be used as a haul road until existing gravel has been removed as required in Section 32 15 00.00 09 LEVEE SURFACING. Completed levee embankment (with or without surfacing material) shall not be used as a haul road.

1.11 DESIGNATED BILLING OFFICE

The designated billing office for this contract shall be U.S. Army Corps of Engineers, Vidalia Area Office, 100 Advocate Row, Vidalia, Louisiana 71373-3032 .

1.12 PAYMENT INVOICES

a. The Federal Acquisition Regulation requires that the "REMIT TO" address on the invoice match the "REMIT TO" address on the contract or a proper notice of assignment. The Payment Office will verify a match of the "REMIT TO" address in the contract and Contractor’s invoice prior to payment. If the addresses do not match, the invoice will be determined improper and returned to the Contractor for correction and resubmission. If an invoice is improperly returned, the original invoice receipt date shall be used as the basis for determining interest to be paid in accordance with the PROMPT PAYMENT ACT.

b. Among other things, the Contract Clause PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS requires that a proper invoice for payment

SECTION 01 00 00.00 09 Page 8 include substantiation of the amounts requested. As required in Office of Management and Budget, 5 CFR Part 1315, September 29, 1999, PROMPT PAYMENT, substantiation of the amount requested for progress payments under construction contracts includes the following:

(1) An itemization of the amounts requested related to the various elements of work required by the contract covered by the payment request;

(2) A listing of the amount included for work performed by each subcontractor under the contract;

(3) A listing of the total amount of each subcontract under the contract;

(4) A listing of the amounts previously paid to each such subcontractor under the contract; and,

(5) Additional supporting data in a form and detail required by the Contracting Officer.

c. Failure to include the above information in a Contractor’s invoice will result in the invoice being considered defective under the provisions of the PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS clause of the contract, and it will be returned to the Contractor for correction and resubmission.

1.13 TEMPORARY PROJECT FENCING

Temporary project fencing as required by Section 4, "Temporary Facilities", paragraph 04.A.04 of EM 385-1-1, U.S. Army Corps of Safety and Occupational Health Requirements, is not required on this project.

1.14 AS-BUILT DRAWINGS

This paragraph supplements the Contract Clause SPECIFICATIONS AND DRAWINGS

FOR CONSTRUCTION.

a. As-Built Contract Drawings. The Contractor shall maintain two (2) full-size sets of blueline prints of the contract drawings depicting in red a record of as-built conditions. These drawings shall be maintained in current condition at all times during the entire contract period. The blueline drawings shall be updated daily by the Contractor showing all changes from the contract plans which are made in the work, additional information which might be uncovered in the course of construction, and information for future construction reference (such as debris disposed by burying). For levee and berm construction, the riverside toe of completed levee and berm sections shall be plotted on profiles of construction drawings. Levee and berm toe profiles shall depict elevations of newly constructed slope intersection with natural ground and depressions which extend the toe line between routine section surveys. This information shall be recorded on the blueline prints accurately and neatly by means of details and notes. Each month, prior to submitting a request for progress payment, the Contractor shall review the blueline as-built drawings with the Contracting Officer, and the Contractor shall certify that the as-built drawings are accurate and up-to-date before progress payment is made. The Contractor shall deliver to the Contracting Officer the two (2) original full-size completed sets of

SECTION 01 00 00.00 09 Page 9 as-built marked blueline prints at the time of the final inspection of the project. In addition, the Contractor shall provide two CD-ROM's, each containing a full-size, 400 dpi PDF (portable document format) set of as-built drawings, to the Contracting Officer at the time of final inspection.