This is Standard Form 30 (Amendment of Solicitation/Modification of Contract), Amendment 0002, issued by the U.S. Army Corps of Engineers (USACE) Vicksburg District on May 26, 2026, for solicitation W912EE26QA021. The amendment replaces the statement of work in its entirety and extends the dates for response.

The contract requires an in-frame major overhaul of two Caterpillar 3512 marine propulsion engines (Serial Numbers S2J00211 & S2J00214, Arrangement 2322505) aboard the M/V William James at USACE Vicksburg Harbor (2577 Haining Road, Vicksburg, MS 39183). Work must be completed by December 31, 2026. The contractor must perform disassembly, repairs, and reassembly onsite in accordance with Caterpillar maintenance manual specifications, using only new OEM Caterpillar parts or approved reconditioned parts with minimum one-year factory warranty. Major overhaul components include turbo cartridges, oil coolers, oil pumps, lifters, cylinder heads, fuel injectors with harnesses, cylinder packs, pumps, seals, bearings, thermostats, breathers, filters, and valve components. The scope also requires replacing cracked oil pan groups for each engine with contractor-arranged marine alignment services performed to industry standard tolerances and new chockfast installation, plus replacement of engine control room displays (CMD Display Group with drop harness and wiring kit). A detailed parts list of 129 line items per engine and oil pan components is provided. USACE will provide crane/lifting assistance. Core charges for unreusable parts require separate modification requests. The contractor must comply with extensive security requirements including personnel vetting, E-Verify employment eligibility verification, security training, and approval for any non-U.S. citizen workers through the Vicksburg District Security Officer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Continuation of Description

Miscellaneous text in this section has been modified to:

M/V William James - Major Overhauls of Two (2) 3512 Main Engines

Scope of Work

The USACE MVK Revetment Branch requires an in-frame major overhaul of two (2) Caterpillar 3512 marine propulsion engines on the M/V William James along with replacement of the leaking oil pan groups. The contractor will be required to disassemble, make repairs, and reassemble onsite onboard the M/V William James. Replacing the oil pan group will require breaking existing chockfast and lifting the engines for access. The contractor will be required to provide alignment and installing in new chockfast. USACE will be responsible for crane/lifting. All aspects of the major overhauls shall be performed and completed in accordance with the manufacturer's specifications/maintenance manual for a Caterpillar 3512 marine propulsion engine. All parts to be replaced shall be new OEM Caterpillar parts or Caterpillar reconditioned parts where allowed by the Caterpillar service manual recommendations. All reconditioned parts shall meet Caterpillar specifications. All new or reconditioned parts replaced and any service required to replace said parts shall have no less than a one-year factory Caterpillar warranty on parts and labor. All work shall be completed by Caterpillar certified technicians.

Requirements

Perform in-frame major overhaul of two (2) Caterpillar 3512 marine propulsion engines

Both 3512 marine propulsion engines located onboard M/V William James

Arrangement number: 2322505

Serial numbers: S2J00211 & S2J00214

Perform overhauls in accordance with Caterpillar maintenance manual for major overhaul

All parts shall be new or reconditioned (where specified in the manual)

Part List is attached at the end of this scope of work, though some part numbers could have changed

Replace the following parts as part of major overhauls in conjunction with attached parts list:

Turbo Cartridges

W912EE26QA0210002

Oil Coolers

Oil Pumps

Lifters & Lifter Springs

Cylinder Heads

Fuel Injectors w/New Harnesses

Cylinder Packs

Fuel Transfer Pumps

Water Pump

Auxiliary Water Pump

Fuel Priming Pump

Front/Rear Seals

Main Bearings

Rod Bearings

Thrust Bearings

Camshaft Bearings

Rocker Arm Bearings

Temperature Regulators

Crankcase Breathers

All Air, Fuel, and Oil filters

Relief Valves

Oil Duplex Check Valves

Steel Spacer Plates

Valve Bridges

Rocker Arm Buttons & Rings

Engine Dampers

Turbo Inlet & Outlet Bellows

All seals and gaskets to replace above listed parts

Replace all engine oil with Caterpillar approved oil

Replace all ELC coolant

Inspect the following to acceptable Caterpillar tolerances and suggest for replacement if necessary

Camshafts

Crankshafts

Perform the following as part of major overhauls

Clean & Test Aftercoolers

Test run engines after completion

Replace cracked oil pan groups for each engine

USACE will provide crane/lifting to allow access to oil pan group

Breakout chockfast mounting system to be able to remove and install oil pan group

Replace oil pan group - parts list included at end of scope of work

Alignment of engines shall be arranged by contractor, performed by specialty marine alignment contractor

Documentation/qualifications/capability statement about alignment contractor shall be provided with bid

Alignment shall be performed within proper industry standard tolerances

New chockfast shall be reinstalled/reset by contractor

Replace display in engine control room for both engines

Replace CMD Display Group including

Display drop harness

CMD Wiring Connection Kit

Contractor shall provide all materials and labor necessary for all work in requirements

Government will provide crane/lifting assistance as needed Core Charges

Any old parts that cannot be reused by Caterpillar and will require a core charge to be applied shall be figured at completion of the job. A modification request with quote shall be issued by the contractor to the USACE Vicksburg contracting office. If the core charges are deemed valid by the government and cost is reasonable, a contract modification shall be issued by the USACE Vicksburg contracting office.

Period and Location of Performance

All work shall be completed no later than December 31, 2026, and will be completed onboard the M /V William James at the USACE Vicksburg Harbor at 2577 Haining Rd, Vicksburg, MS, 39183.

Security Requirements

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as "NCIC-III") and Terrorist Screening Database (commonly referred to as "TSDB"). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA. Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity. Escorting in classified and /or sensitive areas: In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas. Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in RFO clause 52.222-54 Employment Eligibility Verification and RFO 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with RFO 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file. Non-U.S. Citizens working on Government Contracts:

Government Approval MUST be obtained PRIOR to any non-U.S. Citizen being permitted to work on a government contract. The Contractor must submit a letter requesting approval via the Contracting Officer/Contracting Officer Representative to the Vicksburg District Security Officer.

The letter must include the contract number, period of performance, location(s) of work performance and attach a copy of the individual's passport and visa/work authorization documents.

Parts List Per Engine

Line No Part Number & Description Quantity Engine Overhaul Parts List:

0001 422-9537 Explosion Relief Valve Kit 2

0002 4P-0710 Engine Air Filter 2

0003 115-3634 Air Cleaner Soot Filter 2

0004 1R-0726 Standard Efficiency Engine Oil Filter 4

0005 554-3009 97.5mm Long Check Valve 1

0006 5D-5957 104.37mm Inner Diameter Seal O Ring 3

0007 9M-2610 46.2mm Inside Diameter Seal-O-Ring 1

0008 5P-4892 3.53 x 59.92mm 75A FKM O-Ring 4

0009 6V-3907 3.53 x 183.74mm 75A FKM O-Ring 6

0010 6V-5048 1.83 x 8.92mm 75A FKM O-Ring 5

0011 6V-8001 85.32mm Inside Diameter Seal-O-Ring 1

0012 6V-8002 88.49mm Inside Diameter Seal-O-Ring 1

0013 2G-6303 30mm Internal Diameter Circular Seal 1

0014 214-7568 STOR O-Ring Seal (SAE 9/16-18) 2

0015 5P-5846 40.64mm Inside Diameter Seal-O-Ring 2

0016 112-3540 23.16mm Inside Diameter Seal-O-Ring 4

0017 272-2583 2.62 x 53.64mm 75A FKM O-Ring 2

0018 1R-0756 Element Assembly 7

0019 5D-5957 Seal O-ring 2

0020 162-3906 188.4cc Fuel Priming Pump 1

0021 9Y-8389 1.2mm Thick Fuel Pump Gasket 1

0022 238-5081 2.46 x 19.18mm 90A FKM O-Ring 1

0023 238-5080 2.21 x 16.36mm 90A FKM O-Ring 1

0024 4W-3027 Engine Crankcase Breather 3

0025 033-6031 3.53 x 69.44mm 75A FKM O-Ring 3

0026 0R-5519 Cat(r) Reman Oil Cooler 1

0027 475-0905 Crankshaft-Bearing KIT - Main 1

0028 569-7729 272.288mm Outer Crankshaft Seal 1

0029 569-7728 272.288mm Diameter Crankshaft Seal 1

0030 20R-3545 Cat(r) Reman Cylinder Head 12

0031 265-7537 97mm Long Floating Bridge Inlet 12

0032 265-7538 Steel Exhaust Floating Bridge 12

0033 519-7297 212.5mm Diameter Spacer Plate 12

0034 7N-3368 0.8mm Thick Cylinder Block Gasket 1

0035 8N-1991 70.28mm Maximum OD Plastic Retaining Ring 1

0036 230-1072 0.8mm Thick Gasket 1

0037 6J-2680 3.53 x 69.44mm 90A NBR O-Ring 1

0038 8T-1919 62.87mm Inside Diameter Seal-O-Ring 1

0039 6V-1454 72.39mm Inside Diameter Seal-O-Ring 2

0040 3S-9643 Rotating Shaft Lip Type Seal 2

0041 649-0847 Temperature Regulator 2

0042 428-9130 118.50mm Maximum Inner Diameter Gasket 20

0043 7L-6443 3/8''-16 x 2 1/4'' Hex Head Bolt 80

0044 110-8314 3/8'' Steel Flat Washer 160

0045 2N-2766 3/8''-16 Cone Lock Nut 80

0046 1W-1564 190mm Long Engine Oil Pan Suction Screen 1

0047 9L-1480 0.8mm Thick Prelubrication Lines Gasket 1

0048 10R-9224 Cat(r) Reman Cylinder Pack 12

0049 355-8509 Bearing-Connecting Rod 12

0050 0R-3230 Cat(r) Reman Engine Oil Pump 1

0051 298-6387 3.53 x 164.69mm 75A FKM O-Ring 1

0052 9M-4355 Steel Bolt Damper for Transmission Planetary 3

0053 20R-1272 Reman Electronic Fuel Injector 12

0054 1H-9696 3.53 x 44.04mm 75A NBR O-Ring 1

0055 10R-9838 Cat(r) Reman Fuel Transfer Pump 1

0056 10R-1669 Cat(r) Reman Water Pump 1

0057 3B-8453 18.42mm Inner Diameter Seal O Ring 1

0058 235-3546 3.53 x 234.54mm 75A FKM O-Ring 1

0059 20R-8813 Cat(r) Reman Auxiliary Water Pump 1

0060 5N-1940 1.6mm Thick Flange Gasket 1

0061 418-4163 Water Temperature Regulator 4

0062 6V-1943 3/8''-16 x 1 1/8'' Hex Head Bolt 12

0063 6V-6753 3/8''-16 x 1 3/8'' Hex Head Bolt 8

0064 5M-2894 3/8" ID Steel Flat Washer 20

0065 207-1390 96mm Overall Length Stainless Steel Bellows 2

0066 10R-2340 Cat(r) Reman Turbocharger Cartridge 2

0067 287-7207 236.02mm Inside Diameter Seal-O-Ring 2

0068 289-4079 4.5mm Thick Spiral Wound Turbine Housing Gasket 2

0069 7E-6508 Unit Injector Cap 12

0070 9X-0352 2 Pin Connector Receptacle 12

0071 132-6469 Cylinder Head Valve Mechanism Wiring Harness 12

0072 9F-7707 19mm Long Retainer Ring 36

0073 154-6389 14.73mm Outer Diameter Rocker Arm Button 36

0074 10R-3139 Cat(r) Reman Upgrade-to-New (UTN) Valve Lifter 12

0075 7N-4782 31.38mm Free Length Lifter Guide Spring 24

0076 20R-1626 Cat(r) Reman Valve Lifter 24

0077 599-7275 Single Cylinder Head Install Kit 12

0078 457-6112 Turbocharger Installation Gasket Kit 2

0079 306-2351 Main Water Pump Install Gasket Kit 1

0080 126-4175 EXPANSION TANK INSTALL KIT 1

0081 427-0371 Block & Oil Pan Gaskets Kit - Central Lower Structure 1

0082 426-3622 WATER LINES GROUP GASKETS KIT 1

0083 464-0329 Oil Cooler and Lines Gasket Kit 1

0084 464-2432 Aftercooler & Lines Install Kit 1

Oil Pan Parts List

0085 1W-1564 190mm Long Engine Oil Pan Suction Screen 1

0086 4B-2363 1 1/2-12-2A Thread Square-Drive Plug 2

0087 6F-4868 1.6mm Thick Oil Pan Cover Gasket 2

0088 7C-4715 80mm Inner Diameter Flange Connector 1

0089 7W-0129 Flange Adapter 1

0090 111-2081 Oil Pan Tube Housing 1

0091 114-2413 85.6mm Inner Diameter Deep Sump Oil Pan Tube 1

0092 149-9298 Oil Pan Drain Cover 1

0093 228-8926 3/8" Engine Oil Pan Adapter 1

0094 229-8875 TUBE-SUCTION 1

0095 229-8877 1909.42mm Long Oil Pan 1

0096 231-5867 88.9mm Diameter Saddle Clamp 4

0097 0L-1351 3/8 - 16 Thread Hex Head Bolt 5

0098 0S-1585 1/2''-13 x 1 1/2'' Hex Head Bolt 2

0099 165-3928 3/8''-16 x 1 1/4'' Hex Head Bolt 4

0100 165-3932 3/8''-16 x 2'' Hex Head Bolt 2

0101 0S-1594 3/8-16 Hexagonal Head Bolt 2

0102 259-4598 3.53 x 120.24mm 75A FKM O-Ring 1

0103 1A-2029 3/8''-16 x 1 1/8'' Hex Head Bolt 4

0104 1K-6872 1/2''-13 Cone Lock Nut 2

0105 259-4600 5.33 x 85.09mm 75A FKM O-Ring 2

0106 4B-3140 10mm Thick Two Bolt Mounting Cover 1

0107 5M-2894 3/8" ID Steel Flat Washer 11

0108 5P-7818 91.44mm Inner Diameter O-Ring Seal 1

0109 5P-8245 M12 ID Steel Flat Washer 6

0110 5P-8872 113.66mm Inside Diameter Seal-O-Ring 1

0111 6V-5101 107.32mm Inner Diameter Seal O Ring 1

0112 7B-3235 1/2-13 Thread Hex Head Bolt 2

0113 310-3954 5.33 x 123.19mm 75A FKM O-Ring 2

0114 8M-9024 10.2mm Inner Diameter Washer 2

0115 8T-6762 1/2-14 NPTF Thread Square Drive Plug 1

0116 9L-1480 0.8mm Thick Prelubrication Lines Gasket 1

0117 7E-2630 Gasket Oil 1

0118 7W-0129 Flange Adapter 1

0119 261-5615 Bolt Hex Head 18

0120 165-3928 Bolt Hex Head 2

0121 245-3804 Bolt Hex Head 38

0122 3P-0654 Seal O-Ring 1

0123 5M-2894 Washer 40

0124 6V-5101 Seal 1

0125 8M-9124 Washer 18

Display Additions

0127 CMD13 Display Group 1

0128 Display Drop Harness 1

0129 CMD Wiring Connector Kit 1

IDCode: J
Page: 1
Pages: 12
AmendNo: 0002
EffDate: 26 MAY 2026
ReqNo:
ProjNo:
IssCode: W912EE
AdmCode:
IssuedBy: W07V ENDIST VICKSBURG

KO CONTRACTING DIVISION, 4155 CLAY STREET

VICKSBURG, MS 39183-3435

UNITED STATES

JEFFREY SMITH-LYON, EMAIL: JEFFREY.L.SMITH-LYON@USACE.ARMY.MIL TELEPHONE: 601-631-7264 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912EE26QA021
SolDate: 08 MAY 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: SEE CONTINUATION
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: Solicitation W912EE26QA021 is amended to replace the statement of work in it's entirety and to extend the dates for response.
ContNameTitle:
CoNameTitle: DUSTIN G. CANNADA
ContDate:
CODate: 26 MAY 2026

File details come from the government source that posted it. Updated .