This modification amends a solicitation to replace evaluation language and extend the quote due date. The solicitation seeks quotes to furnish and deliver diesel fuel for the MV Fred Lee. Offerors must submit quotes by November 9, 2023 at 12:00 PM CST and address technical capability to meet requirements and fixed price markup rates. The Army Corps of Engineers will evaluate quotes on technical acceptability and price, awarding to the lowest priced technically acceptable offer. Details on submission and evaluation processes are provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amended_Bid Schedule.pdf | ||
| W912EE24Q0006-0001.pdf | ||
| Bid Schedule.pdf | ||
| A22_Solicitation_24Q0006.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This modif ication, 0002, serves to replace the requirements and evaluation language pertaining to submittals. The due date for quotes is hereby extended to Thursday, November 09, 2023 at 12:00 PM CST. No other changes w ill be made. All other terms and conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Nov-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EE24Q0006
X 9B. DATED (SEE ITEM 11)
27-Oct-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Nov-2023
CODE
VICKSBURG CONTRACTING OFFICE
4155 CLAY ST
VICKSBURG MS 39183-3435
W912EE 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EE24Q0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 06-Nov-2023 03:00 PM to 09-Nov-2023 12:00 PM.
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
INSTRUCTIONS FOR BIDDERS
INSTRUCTIONS to Bidders
L.1. These instructions are a guide for preparing your quote. Offerors are expected to review the Statement of Work (SOW) contained in this Request for Quote (RFQ) for further insight into the information that your quote must include.
Offerors shall include in the quote sufficient information to enable the evaluators to determine your understanding of the requirements.
L.1.1 All Offerors shall submit a quote with content as specified herein. Quotes submitted without the specified content may be determined non-compliant and removed from further consideration. Quotes must be received no later than the date and time indicated on block 8 of Standard Form 1449. Offerors may submit their quote packages via email to the following address:
genna.s.wall@usace.army.mil
L.1.2 All quotes submitted shall address the following evaluation factors:
(i) technical capability of the item offered to meet the Government requirement
(ii) price.
It is incumbent upon the offeror to submit sufficient documentation and information for the Government to determine technical acceptability and proposed price. Failure to submit sufficient information for the government to determine technical acceptability or price may be cause for rejection of your quote.
NOTE: All quotes must be valid for 60 days.
L.1.3 Acceptance: A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
Solicitation Inquiries:
All inquiries regarding this solicitation are to be submitted via ProjNet. Telephone and email inquiries will not be accepted. ProjNet is a web-based program that allows offerors to post questions regarding the solicitation and view all questions by other offerors and responses by the government.
1. Offerors shall only submit one question per inquiry. All inquiries containing multiple questions will be rejected.
2. Offerors will receive an acknowledgement of their question(s) via email, followed by an answer to their question(s) after it has been processed. Offerors may view all inquiries through ProjNet.
3. Inquiries must be submitted not later than 3 days prior to the close of this solicitation. Any inquiries submitted after this date may not be answered.
4. To submit and review inquiries, offerors will need to use the inquiry key presented below and follow the instructions listed below the key for access.
5. The Inquiry Key is: 4A55YR-AU7TI5
ProjNet Title: W912EE24Q0006, Fuel for MV Fred Lee
a. From the ProjNet home page link: https://www.projnet.org/projnet/ click on Quick Add on the upper right side of the screen.
b. Identify the Agency: This should be marked as USACE.
c. Key: Enter the Inquiry Key listed above.
d. Email: Enter the email address you would like to use for communication.
e. Click Continue. A page will then open saying that a user account was not found, and it will ask you to create one using the provided form.
f. Enter your first name, last name, company, city, state, phone, email, secret question, secret answer, and time zone.
g. Make sure to remember your secret question and answer, as they will be used from this point on to access the ProjNet system Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
h. Submit questions or review questions and answers. An offeror who submits a question will receive an automated email notification that its question has been received. When an answer is posted to a question, the question and answer are then available for all other offerors to review.
L.2. FORMAT AND CONTENTS. The offerors’ quote shall consist of two (2) sections. The sections are I – Technical Capability, II –Price.
L.2.1 Section 1, Technical Capability. In the Technical Capability Section, each Offeror shall submit documentation of the quote in accordance with the terms and conditions defined in the Statement of Work and in compliance with the attached drawings. Please submit a description of the materials to be supplied.
L.2.2 Section 2, Price. The offeror shall fully complete Attachment C, the Bid Schedule. A detailed breakdown and description of the fixed markup rate pricing must be included with the bid schedule. For each fuel delivery, the contractor will be paid the market price for the diesel #2, plus the per gallon markup rate applicable to the delivery location. In addition, an authorized official of the firm shall sign the SF 1449 and all solicitation amendments.
Section A – Standard Form 1449 (SF 1449), Solicitation, Offer and Award Section K – All fill-in provisions listed in Section K.
SECTION M - EVALUATION FACTORS FOR AWARD
The following have been modified:
52.212-2 EVALUATION--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
(a) The Government will award a contract to the lowest priced technically acceptable proposal. Proposals will be evaluated for technical acceptability. In order for an Offeror to be considered for award, the proposal must receive an “Acceptable” rating. A proposal receiving a rating of “Unacceptable” will not be eligible for award.
FACTOR 1 - TECHNICAL CAPABILITY
To be determined technically acceptable the offeror must provide documentation that demonstrates that the offeror can provide the necessary supplies as outlined in the statement of work.
FACTOR 2 – PRICE
Pricing shall be provided for all line items listed. An authorized official of the firm shall sign the SF 1449 and all solicitation amendments (if any).
(b) Options. The government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the government to exercise the option(s).
For each fuel delivery, the contractor will be paid the market price for the diesel #2, plus the per gallon markup rate applicable to the delivery location. The lowest quote will be evaluated based on the fixed mark up rate for each location listed in the bid schedule. Quotes will be examined to determine the extent to which quoted prices are comparable with the government estimates, previous procurement history, and a determination made of Price Reasonableness. The government may reject any price quote that is determined to be Not Fair and Reasonable, unrealistically high, or low in price when compared to government estimates, or are unbalanced, such that the price quote is deemed to reflect an inherent lack of competence or failure to comprehend the requirements.
AWARD:
It is incumbent upon the offeror to submit sufficient documentation and information for the government to determine technical acceptability and the quoted pricing. Failure to submit sufficient information for the government to determine technical acceptability and price may be cause for rejection of your quote.
Award will be made to the contractor whose price is the lowest of all offers determined to be technically acceptable.
The Government will evaluate the lowest priced offer for technical acceptability. If the lowest priced offer is determined to be unacceptable, the next lowest offer will be evaluated for technical acceptability until an acceptable offer is determined.
(c) A written notice of award or acceptance of an offer mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.
Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of provision)
(End of Summary of Changes)