A22_W912EE23B0006 Amendment 0004.pdf
PDF 1 MB Posted
- Solicitation number
- W912EE23B0006
About this file
This document provides details for Amendment 0004 to Solicitation Number W912EE23B0006 issued by the United States Army Corps of Engineers Vicksburg District. The amendment extends the bid opening date from 31 May 2023 to 7 June 2023 at 2:00 PM for a project to repaint the Narrows Access Bridge superstructure and bearings in Pike County, Arkansas. Work includes utility line relocation, mobilization, tack weld removal, abrasive blasting, bridge repainting, and environmental protection. The solicitation is for a firm fixed-price construction contract under NAICS code 237310 with a $45 million size standard. The project value is estimated between $1-5 million. The amendment also revises specifications and appendix requirements for utility attachments to USACE bridges.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Reference Solicitation No. W912EE23B0006;
SEE CONTINUATION PAGE FOR CHANGES.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-May-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EE23B0006
X 9B. DATED (SEE ITEM 11)
24-Apr-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-May-2023
CODE
VICKSBURG CONTRACTING OFFICE
4155 CLAY ST
VICKSBURG MS 39183-3435
W912EE 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EE23B0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 31-May-2023 02:00 PM to 07-Jun-2023 02:00 PM.
(End of Summary of Changes)
The following items are applicable to this modification:
SUMMARY OF CHANGES
SPECIFICATIONS: Appendix after Section 01 00 00.00 09 is revised and replaced in its entirety.
Specifications revised by this amendment have the notation “Revised by Amendment 0004” at the bottom of the page.
Bid opening date is hereby extended to 7 June 2023 at 2:00 pm local time.
US ARMY CORPS OF ENGINEERS
VICKSBURG DISTRICT
UTILITIY ATTACHMENTS ON OR ADJACENT TO BRIDGES
Approval is required for any utility attachment to US Army Corps of Engineers (USACE) bridge. The requesting utility company should contact the local office and the local USACE office will forward the application to the Vicksburg District office for review and coordination. No work shall proceed until approval of submitted details of all attachments is received from the Vicksburg District Bridge Program Manager or Chief of Engineer and Construction Division.
Requirements:
1. Show the location and spacing of the proposed attachment(s) to the existing bridge.
2. Install the utility line(s) on the upstream side of the bridge.
3. The proposed utility shall not hang below the lowest element of the bridge superstructure (i.e., bottom flange of beam).
4. Attachments to the side of deck or curb are allowed. Attachments to the primary structural steel (e.g., beam flanges, web, stiffeners) are not allowed.
5. Field welding to the existing bridge is not allowed.
6. Holes drilled in bridge concrete shall not cause damage to the primary reinforcing steel, and shall not be more than 2" deep. Provide 3" minimum distance from the edge of the drilled hole to the edge of concrete.
7. Steel anchorage embedded in the concrete shall be stainless steel or galvanized steel.
Provide technical information on the capacity of proposed concrete anchor inserts. The minimum distance between centers of adjacent fasteners embedded in concrete shall meet the requirements of the fastener manufacturer and shall in no case be less than 12" center to center.
Where post-installed adhesive anchors are deemed a necessity, they should be designed using ACI 318-14 or later editions for the given loading condition (vertical, horizontal, or overhead) and use only adhesive anchor systems qualified per ACI 355.4-11 or later editions for the same loading condition. Certification from an applicable certification program shall be provided for personnel installing the adhesive anchors.
Refer to FHWA Technical Advisory T 5140.34 for additional information.
8. If applicable, show and identify the type and location of planned expansion joints for the proposed utility. Provide the allowable movement rating for expansion devices.
Revised By Amendment 0004
9. Any longitudinal thrust transmitted by the utility (i.e., water hammer) must not be transmitted to the existing bridge. Provide details of any thrust blocks and joint restraints used.
10. Submit detailed engineering calculations showing the utility dead and live loads transmitted through the attachments to the bridge and, when requested, the structural adequacy of the affected bridge elements to support their design loads, any load(s) added to the structure since its construction, and these additional loadings from the proposed utility.
Revised By Amendment 0004
| W912EE23B0006 Amendment 0004 |
| AM_0004 |
File details come from the government source that posted it. Updated .