RFP A.1 SOW Div01 FY27 ShopAdams 260826.pdf
PDF 845 KB Posted
- Solicitation number
- W912DY27ACPAVB
About this file
This is a Statement of Work (SOW) for Division 01 (General Requirements) of a design-build construction project to install Active Vehicle Barrier Control Systems (AVBCS) and associated infrastructure improvements at Shop Gate and Adams Gate at Fort Lee, Virginia. The project encompasses design and construction of crash-rated active vehicle barriers, guard booth demolition and replacement, passive vehicle barriers in response zones, electrical system integration, and ID check area reconfiguration. The work is structured across eleven Contract Line Item Numbers (CLINs): CLIN 0001-0002 cover mandatory AVBCS design and construction at Shop ACP; CLINs 0003-0004 are optional AVBCS design and construction at Adams ACP; CLINs 0005-0010 are optional passive vehicle barrier design/construction and ID check reconfiguration; and CLIN 0011 addresses optional transformer coordination at Adams Road. All active vehicle barriers must be selected from the DOD Anti-Ram Barrier List and comply with ASTM F2656 or DoS SD-STD-02.01 standards.
The contractor must complete extensive design documentation including vehicle threat scenario calculations, tailored UFGS 34 75 13.13 specifications, and electrical system designs, with designs certified by registered professional engineers. Critical requirements include Performance Verification Testing and commissioning witnessed by the USACE Protective Design Center within 60 days of PVT plan submission, endurance testing, and operator training. The contractor must maintain continuous ACP operations during construction through phased, coordinated work on one roadway at a time. Key personnel include a Project Manager (minimum 5 years experience), Quality Control Manager (minimum 5 years combined experience, minimum 2 years as QC Manager for controls systems), Designer of Record (minimum 5 years military security design experience), and Site Safety and Health Manager (minimum 5 years safety experience on military projects). Mobilization requires approval of the Issued for Construction design package, preconstruction meeting completion, and acceptance of long lead time items, accident prevention plans, activity hazard analyses, and product data for the first 45 days of work. The Government will coordinate with the USACE Protective Design Center and ARTRANS for technical inquiries and maintain government staffing at both ACPs throughout construction except during approved testing and booth installation periods.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Lee Shop and Adams 20261105.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHOPPADAMS
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00.10 09/25 STATEMENT OF WORK
01 14 00 11/22, CHG 5: 05/25 WORK RESTRICTIONS
01 20 00 11/20, CHG 5: 02/25 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 5: 02/25 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 08/23, CHG 1: 08/24 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 16.00 10 05/16 DESIGN DATA (DESIGN AFTER AWARD)
01 35 26 05/24, CHG 1: 05/25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 3: 08/25 QUALITY CONTROL
01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22, CHG 2: 08/25 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23, CHG 1: 05/25 OPERATION AND MAINTENANCE DATA
01 78 24.00 10 05/23 FACILITY DATA REQUIREMENTS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00.10
STATEMENT OF WORK
09/25
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Title and Location
1.2.2 Project Description
1.2.3 TASK ELEMENTS
1.2.3.1 AVBCS DESIGN SHOP ACP - CLIN 0001
1.2.3.2 AVBCS CONSTRUCTION SHOP ACP - CLIN 0002
1.2.3.3 OPTIONAL AVBCS DESIGN ADAMS ACP - CLIN 0003
1.2.3.4 OPTIONAL AVBCS CONSTRUCTION ADAMS ACP - CLIN 0004
1.2.3.5 OPTIONAL ID CHECK RECONFIGURATION DESIGN - CLIN 0005
1.2.3.6 OPTIONAL ID CHECK RECONFIGURATION CONSTRUCTION - CLIN 0006
1.2.3.7 OPTIONAL PVB DESIGN ADAMS ACP - CLIN 0007
1.2.3.8 OPTIONAL PVB CONSTRUCTION ADAMS ACP - CLIN 0008
1.2.3.9 OPTIONAL PVB DESIGN SHOP ACP - CLIN 0009
1.2.3.10 OPTIONAL PVB CONSTRUCTION SHOP ACP - CLIN 0010
1.2.3.11 OPTIONAL TRANSFORMER SHOP ACP - CLIN 0011
1.2.4 DETAILED TASK ELEMENTS
1.2.5 EXISTING INSTALLATION INFORMATION
1.3 SECURITY REQUIREMENTS
1.4 GOVERNMENT OCCUPANCY OF PREMISES
1.5 CONTRACTOR ACCESS AND USE OF PREMISES
1.6 EXISTING WORK
1.7 LOCATION OF UNDERGROUND FACILITIES
1.8 DESIGN REQUIREMENTS
1.9 CERTIFICATION OF WORK
PART 2 PRODUCTS
PART 3 EXECUTION
PART 4 ADDENDUMS/ENGINEERING CHANGE PROPOSALS (ECP)
-- End of Section Table of Contents --
SECTION 01 11 00.10 Page 1
01 11 00.10
STATEMENT OF WORK
09/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only. Unless a specific document version or date is indicated, use criteria from the most current references as of the date of issue of the contract or task order, including any applicable addenda, unless otherwise stated in the task order. In the event of conflict between References and/or Applicable Military Criteria, apply the most stringent requirement, unless otherwise specifically noted in the contract or task order.
U.S. ARMY (DA)
Army ECBs Army Engineering & Construction Bullletins (ECBs)
Army Standard for ACPs (2012) The Army Standard for Access (ACPs)
Army Standard Design (2024)Army Standard Design
DOD Anti-Ram Barrier List (2026) DOD Anti-Ram Barrier List
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-200-01 (2022; with Change 4, 2024) DoD Building Code
UFC 4-010-06 (2023) Cybersecurity of Facility-Related Control Systems
UFC 4-022-01 (2017) Entry Control Facilities/Access Control
Unless a specific document version or date is indicated, use criteria from the most current references as of the date of issue of the contract or task order, including any applicable addenda, unless otherwise stated in the task order. In the event of conflict between References and/or Applicable Military Criteria, apply the most stringent requirement, unless otherwise specifically noted in the contract or task order.
SECTION 01 11 00.10 Page 2
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Title and Location
Fort Lee, Virginia (VA), Shopp and Adams Gates Active Vehicle Barrier Control System (AVBCS)and Passive Vehicle Barrier Installation.
The work associated with this contract is located at Shopp Gate and Adams Gate, Fort Lee, VA. Shop Gate is located on Shop Road near the intersection of Shop Road and Quartermaster Road. Adams Gate is located on Adams Road near the intesection of Adams Road and Valley Forge Lane.
1.2.2 Project Description
The work is under a design-build (DB) type contract and includes design and construction phases. The AVBCS and guard booth install is defined under 0001, 0002 for Shop ACP and 0003 and 0004 for Adams ACP. Passive Vehicle Barriers will be included under optional CLINs 0005 and 0006 for Shop Road and 0007 and 0008 at Adams ACP, CLINS 0009 and 0010 will also include ID Check area reconfiguration. CLINs 0005-0010 are optional.
The contractor shall provide all materials, equipment, and labor for the design and installation of an Active Vehicle Barrier Control System (AVBCS), guard booth demolition and replacement, crash beam installation at the maintenance road in response zone, optional response zone passive vehicle barriers and ID Reconfiguration. This work covers a total of four
(4) AVBs: two (2) at Shop ACP and two (2) at Adams ACP (one inbound and one outbound at each of the two ACPs, installation of one crash rated drop arm and demolition of guard booth under ID Check Canopy and installation of new guard booth. Additional it includes work to install Passive Vehicle Barriers in the response zone and reconfiguration on the ID Check area at Adams ACP to accomodate an additional concrete island and guard booth.
This work includes site grading, subgrade preparation, site utilities, paving, reinforced concrete, electrical, landscaping, security and communications, security equipment, passive vehicle barriers to support the safety scheme, guardrails (to support safety scheme), passive vehicle barrier in response zone, roadway design, and other items defined in the contract documents and required by accepted design. All work included in the contract documents is the responsibility of the Contractor unless stated otherwise.
Comply with the requirements included in and referenced by the contract documents, which include the Division 01 Specifications, this Statement of Work (SOW), the Contractor's final accepted proposal, and the Government's responses to pre-award bidder inquires. (See also, UAI 5152.236-9011 Design-Build Construction Contracts)
See the attached PDF file in Appendix A, Shop ACP, for a Government approved conceptual safety and security scheme that shows concept number of AVBs, location of AVBs, for general project area information and approved conceptual layouts and calculations intended to address the defeat of various vehicle threat scenarios. Appendix B outlines the same information for Adams ACP.
The Project Definition Report (PDR) shows the layout and calculations that address response zone length and are part of a cursory assessment of threat detection, threat delay, barrier deployment, and defeat of threat are provided to aid the Contractor in the development of a compliant and
SECTION 01 11 00.10 Page 3 complete design solution suitable for the installation project. The Project Definition Report is a conceptual document and the compliant design solution is the responsbility of the Contractor. All calculations must be verified, and all information provided must be field verified by the contractor.
FT Lee Design Stanrdards are available in Appendix B of this SOW, FT Lee Vision - Installation Planning Standards Final. Applicable design standards and specifications (02-49) should be adhered to, utilized in Design development, and included in the Design package. If the design requires a UFGS that has not been tailored for FT Lee and provided in Appendix B, utilize and tailor the UFGS Masterformat version for the project.
Gate will be closed during testing and downtime is to cause minimal impact.
1.2.3 TASK ELEMENTS
1.2.3.1 AVBCS DESIGN SHOP ACP - CLIN 0001
Prepare and submit the design packages and Design Complete package and the work plans in accordance with Section 01 33 16.00 10 DESIGN DATA and other requirements of the contract documents. This CLIN includes all design effort required to install a new AVBCS and guard booth.
1.2.3.2 AVBCS CONSTRUCTION SHOP ACP - CLIN 0002
Implement the Design. This task element includes construction (including commissioning and testing) and closeout activities. Work includes preconstruction meeting, mobilization, construction, inspection, testing, commissioning, training, endurance testing, O&M data, closeout, and all other work that does not involve design. This CLIN shall include all construction efforts necessary to install the new AVBCS, testing/ commissioning and training efforts for the new AVBCS, and demolition of existing guard booth and installation of new guard booth, and all final administrative closeout actions/documentation required by the SOW.
1.2.3.3 OPTIONAL AVBCS DESIGN ADAMS ACP - CLIN 0003
Prepare and submit the design packages and Design Complete package and the work plans in accordance with Section 01 33 16.00 10 DESIGN DATA and other requirements of the contract documents. This CLIN includes all design effort required to install a new AVBCS.
1.2.3.4 OPTIONAL AVBCS CONSTRUCTION ADAMS ACP - CLIN 0004
Implement the Design. This task element includes construction (including commissioning and testing) and closeout activities. Work includes preconstruction meeting, mobilization, construction, inspection, testing, commissioning, training, endurance testing, O&M data, closeout, and all other work that does not involve design. This CLIN shall include all construction efforts necessary to install the new AVBCS, testing/ commissioning and training efforts for the new AVBCS, and all final administrative closeout actions/documentation required by the SOW.
1.2.3.5 OPTIONAL ID CHECK RECONFIGURATION DESIGN - CLIN 0005
Prepare and submit the design packages and Design Complete package and the
SECTION 01 11 00.10 Page 4 work plans by following the requirements in Section 01 33 16.00 10 DESIGN DATA and other requirements of the contract documents. This CLIN will include all design efforts to install the responze zone PVBs.
1.2.3.6 OPTIONAL ID CHECK RECONFIGURATION CONSTRUCTION - CLIN 0006
Implement the Design. This task element includes construction closeout activities. Work includes pre-construction meeting, mobilization, construction, inspection, O&M data, closeout, and all other work that does not involve design. This CLIN will include all construction efforts to install, and all closeout requirements for the response zone PVB.
1.2.3.7 OPTIONAL PVB DESIGN ADAMS ACP - CLIN 0007
Prepare and submit the design packages and Design Complete package and the work plans by following the requirements in Section 01 33 16.00 10 DESIGN DATA and other requirements of the contract documents. This CLIN will include all design efforts to install the responze zone PVBs.
1.2.3.8 OPTIONAL PVB CONSTRUCTION ADAMS ACP - CLIN 0008
Implement the Design. This task element includes construction closeout activities. Work includes pre-construction meeting, mobilization, construction, inspection, O&M data, closeout, and all other work that does not involve design. This CLIN will include all construction efforts to install, and all closeout requirements for the response zone PVB.
1.2.3.9 OPTIONAL PVB DESIGN SHOP ACP - CLIN 0009
Prepare and submit the design packages and Design Complete package and the work plans by following the requirements in Section 01 33 16.00 10 DESIGN DATA and other requirements of the contract documents. This CLIN will include all design efforts to reconfigure the existing ID Check area (under canopy) to accomodate and install a new concrete island that will support the new guard booth outlined in CLIN 0001 and 0002.
1.2.3.10 OPTIONAL PVB CONSTRUCTION SHOP ACP - CLIN 0010
Implement the Design. This task element includes construction closeout activities. Work includes pre-construction meeting, mobilization, construction, inspection, O&M data, closeout, and all other work that does not involve design. This CLIN will include all construction efforts to reconfigure the existing ID Check area (under canopy) to accomodate and install a new concrete island that will support the new guard booth outlined in CLIN 0001 and 0002.
1.2.3.11 OPTIONAL TRANSFORMER SHOP ACP - CLIN 0011
Provide all coordination with the local utility provider for new service transformer installation.
1.2.4 DETAILED TASK ELEMENTS
The work can be more specifically described as:
a. (CLIN 0001, 0002) Active Vehicle Barriers (AVB). Design and install compliant AVBCS(s) in accordance with an approved design for a
SECTION 01 11 00.10 Page 5 commissionable barrier. All AVBs must be selected off the DOD Anti-Ram List in effect at the time of contract award. All aspects of the AVB design shall conform to, but not be limited to, the standards outlined in ACP-SD, UFC 4-022-02, and Army Transportation (ARTRANS) Command Pamphlet 55-15. Work will include installation of new overwatch pads (1 each at Shop and Adams ACPs) with pedestal racks.
The most recent DOD Anti-Ram Vehicle Barrier List features vehicle barriers that have been successfully tested and validated under ASTM F2656 or DoS SD-STD-02.01. (See the "Library" link at https://www.nwo.usace.army.mil/pdc/home for the latest DOD Anti-Ram Vehicle Barrier List)
b. (CLIN 0001) Vehicle Threat Scenario Calculations. Prepare vehicle threat scenario calculations for at least the four vehicle threat path scenarios included in the Standard for ACPs to validate the concept layouts provided. Verify that the AVBs are located where defeat is possible for the shortest timed path of travel through the ACP for each threat scenario. Include the calculations in the design analysis starting with the first design package submittal. All calculations must be shown not just the controlling threat path.
c. (CLIN 0005, 0006, 0007, 0008) Passive Vehicle Barriers (PVB). Design and install compliant PVB(s) in accordance wtih an approved design.
All aspects of the PVB design shall conform to applicable standards.
All AVBs must be selected off the DOD Anti-Ram List in effect at the time of contract award.
The most recent DOD Anti-Ram Vehicle Barrier List features vehicle barriers that have been successfully tested and validated under ASTM F2656 or DoS SD-STD-02.01. (See the "Library" link at https://www.nwo.usace.army.mil/pdc/home for the latest DOD Anti-Ram Vehicle Barrier List)
d. (CLIN 0001, 0002, 0003, 0004) Demolition - Provide required demolition to support a fully compliant ARTRANS Safety Scheme AVBCS design and construction.
e. (CLIN 0009 and 0010) Demolition - Provide required demolition to reconfigure ID Check to install new concrete island to support the new guard booth installation. This work shall occur under the exisitng canopy.
f. (CLIN 0001,0002) Directly coordinate with the USACE Protective Design Center (PDC) and the ARTRANS for any technical inquiries. Include the COR and Project Engineer in all discussions/correspondence. Obtain the points of contact information from the COR.
g. (CLIN 0001, 0003) The DOR shall tailor UFGS 34 75 13.13 CRASH RATED ACTIVE VEHICLE BARRIERS AND CONTROL. This specification shall be completed/tailored by the DOR and submitted with each design package with other applicable construction specifications. A copy of this specification should be completed/tailored and submitted with each design package as part of the construction specifications.
Section 34 75 13.13 will be completed to align with the prepared design and warranty management plans.
SECTION 01 11 00.10 Page 6
All updates to Section 34 75 13.13 shall be clearly annotated by highlighted and strike through font with the first Design submission.
Update annotations can be removed once intermediate design submittal package is approved. Any changes to unbracketed text are considered as variations to the contract requirements.
h. (CLIN 0001, 0002, 0003, and 0004) Electrical Power for the AVBCS.
Design and construct infrastructure, conduit and wiring as needed to support the new AVBCS. Integrate this additional power with the existing systems. Contractor shall investigate the current electrical capacity and provide the electrical requirements for a fully functional
AVBCS.
Provide all required panelboards and electrical equipment to support the new AVBs, overwatch pads, roadway lighting, and associated systems.
Pricing for all efforts should be included in the Contractor's proposal.
Shop Road (CLIN 0001 and 0002): The local utility provider is solely responsible for the procurement and installation of the new service transformer. The Contractor shall coordinate with the local utility provider for scheduling and technical interface related to this new service transformer installation. The Contractor is also responsible for providing all labor, materials, and equipment for a complete and operational electrical system integration. This encompasses, but is not limited to, the installation of a generator quick connect system; the installation, termination, and connection of electrical panels and equipment, both existing and new, including PNL1615, PNL1613, GB1, GB2, BCP1, BCP2, and the procurement and installation of one (1) main service disconnect for the new transformer service ; the installation of all necessary conduit, wiring, and associated terminations to connect the new transformer to the facility's distribution system and all specified equipment; and the integration of the AVB system to the new transformer service.
Adams Road Optional CLIN 0011: The local utility provider is solely responsible for the procurement and installation of the new service transformer. The Contractor shall coordinate with the local utility provider for scheduling and technical interface related to this new service transformer installation. The Contractor is also responsible for providing all labor, materials, and equipment for a complete and operational electrical system integration. This encompasses, but is not limited to, the installation of a generator quick connect system; the installation, termination, and connection of electrical panels and equipment, both existing and new, including PNL1615, PNL1613, GB1, GB2, BCP1, BCP2, and the procurement and installation of one (1) main service disconnect for the new transformer service ; the installation of all necessary conduit, wiring, and associated terminations to connect the new transformer to the facility's distribution system and all specified equipment; and the integration of the AVB system to the new transformer service.
i. (CLIN 0002 and 0004) Perform verification testing and commissioning of the new AVBCSs. Provide training. Perform endurance testing.
SECTION 01 11 00.10 Page 7
A Performance Verification Testing (PVT) Plan shall be submitted to the Government for review and must be approved no later than 60 days prior to the commissioning. PDC will have 21 calendar days to review the PVT Plan. The Contractor shall fully perform the PVT plan, during a Contractor verification test, prior to the commissioning witnessed by the Government (ideally this happens 1-2 weeks prior to the planned PVT Test). The commissioning (PVT) will be witnessed by the Protective Design Mandatory Center of Expertise (PD-MCX). The Contractor shall notify the Contracting Officer Representative, Project Manager of the planned commissioning date at least 60 days prior to requested commissioning date, to allow for proper Government coordination. The Government will coordinate the requested scheduled date with PDC.
Commissioning shall be repeated if the first effort fails. The Contractor shall notify the Contracting Officer a planned date for repeating the commissioning effort at least 30 days prior.
Commissioning shall be repeated until it is successful at no additional cost to the Government.
Endurance testing is to be performed per requirements oulined in 34 75 13.13.
j. (CLIN 0001, 0002, 0003, and 0004) AVBCS Components. The AVBCS is defined in the Army ACP Standard Design, paragraph 3.9 COMMUNICATIONS AND SECURITY SYSTEMS: F. ACTIVE VEHICLE BARRIER CONTROL SYSTEM. Table "AVBCS & Related Components Included in This Project" identifies the AVBCS components that are part of this contract. This listing does not include all of required work (for example, all telecommunications cabling in concrete encased duct bank, EFO switches and buttons, overspeed & wrong way warning annunciator) and are included for clarification. Contractor must provide a complete system that meets the Army ACP Standard Design and is successfully commissioned. Furnish and install a complete and functional crash rated active vehicle barrier system for the ACP including crash rated active vehicle barriers, active vehicle barrier controls, traffic signals, traffic signal controls, traffic warning signals, traffic signs and pavement markings, vehicle overspeed detectors, wrong-way detectors, vehicle presence detectors, tamper switches, alarm displays, sequence of events recorder, data transmission, and all interconnecting conduit and wiring. This includes all components required to install the compliant AVBCSs as shown in the Government accepted design package.
Crash rated active vehicle barrier types covered by this specification and are included in the project are retractable electric finger wedge type barriers and crash beams.
Note UFGS 34 75 13.13 paragraph 2.3.4. all roadway components are to be capable of supporting a 32,000-pound axle load or 16,000-pound wheel load.
k. (CLIN 0001, 0002, 0003, 0004, 0009, 0010) New Guard Booth. Install one
(1) new guard booth at Shop Road in the location of the demoed existing guard booth. Guard booth should be sized to accomodate required guard booth activities as well as house the AVBCS master operating panel.
There is currently not a compliant gatehouse at Shop ACP.
Install two (2) new guard booths. Size should be at maximum 4’x10’ but dimensioned to fit onto each island with all appropriate standoff
SECTION 01 11 00.10 Page 8 requirements. One each on the existing island and the planned new island.
l. (CLIN 0009 and 0010) Reconfigured ID Check. Design and install all necessary components to reconfigure the ID Check Canopy to accommodate a new concrete median under ID Canopy adjacent to Lane 2. New Guard Booth at Adams ACP from section k. will be installed on the median.
Median should accommodate 1 new Guard booth to process POV traffic in the farthest lane from the existing guard booth. Appropriate conduit and wiring should be provided for new guard booth connections. Minimum safety offsets from curb should be accommodated at Guard booth door(s). Design may include road alignment and new curbing and gutter to maximize space underneath the ID Check Canopy.
m. (All CLINs) Ensure Design is compliant with all Federal, State, Local standards and regulations. Specifically IAW the Army Standard for ACPs and Army Standard Design and DOD Anti-Ram Barrier List. This includes also applicable UFGS, Army ECBs, UFCs (UFC 1-200-01, UFC 4-010-06, UFC 4-022-01].
1.2.5 EXISTING INSTALLATION INFORMATION
The Government may provide historical information as available. Available existing condition information may include as-built drawings, photographs, study reports and similar information about the physical characteristics of the site. The contractor shall field-verify all Government-provided documentation of existing site conditions.
1.3 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Alt II, Security Requirements applies.
Maintain the site and all other contractor-controlled areas in such a manner as to minimize the risk of theft, vandalism, injury, or accident.
Contractor shall comply with installation security regulations.
1.4 GOVERNMENT OCCUPANCY OF PREMISES
The Government's staffing and occupancy of the Shop and Adams Access Control Points (ACPs) during the construction period will be as follows:
Shop Access Control Point The Government will staff the Shop ACP to maintain full operational capacity throughout all phases of construction. The only exception will be during periods of approved and scheduled system testing that require temporary gate closure. In addition, temporary gate closure is expected during the booth installation and demolition. The Contractor is required to coordinate all construction activities with the Government to prevent disruption to the Shop ACP's daily operations and to schedule the aforementioned testing periods with minimal impact.
Adams Access Control Point The Government will staff the Shop ACP to maintain full operational capacity throughout all phases of construction. The only exception will be during periods of approved and scheduled system testing that require temporary gate closure. In addition, temporary gate closure is expected during the ID Check reconfiguration and booth installation and demolition.
The Contractor is required to coordinate all construction activities with the Government to prevent disruption to the Adams ACP's daily operations
SECTION 01 11 00.10 Page 9 and to schedule the aforementioned testing periods with minimal impact.
1.5 CONTRACTOR ACCESS AND USE OF PREMISES
The contractor shall provide for necessary coordination with Government personnel to ensure that construction activities do not interfere with the continuous operation of the ACP. Any work that may disrupt the ACP's normal functioning must be coordinated in advance with the Government and must be conducted in a manner that minimizes impact.
For Shop ACP: The contractor shall schedule construction activities to avoid conflicts with ACP operations and maintain continuous traffic flow.
The contractor shall perform construction activities on one roadway at a time to ensure that traffic flow on the other roadway remains uninterrupted, using a phased approach. The only exception will be during periods of approved and scheduled system testing that require temporary gate closure. In addition, temporary gate closure is expected during the booth installation and demolition. All work shall be scheduled and managed in a manner that minimizes disruption to traffic and allows for continuous use of at least one road throughout the construction period.
For Adams ACP: The contractor shall schedule construction activities to avoid conflicts with ACP operations and maintain continuous traffic flow.
The contractor shall perform construction activities on one roadway at a time to ensure that traffic flow on the other roadway remains uninterrupted, using a phased approach. The only exception will be during periods of approved and scheduled system testing that require temporary gate closure. In addition, temporary gate closure is expected during the ID Check reconfiguration and booth installation and demolition. All work shall be scheduled and managed in a manner that minimizes disruption to traffic and allows for continuous use of at least one road throughout the construction period.
The contractor is responsible for maintaining safety and security at all times during their work on-site. This includes restricting access to construction zones, implementing necessary safety measures, and ensuring that the operation of the ACP is not interrupted.
The contractor must notify the Government immediately in the event of any unplanned disruption to ACP operations and provide a plan for mitigating the disruption or returning the ACP to normal operation as quickly as possible.
Ensure that Contractor personnel employed on the contract become familiar with and obey all regulations including safety, fire, traffic and security regulations required by the contract. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.
See additional specific contractor access and use of premises requirements in Section 01 14 00 WORK RESTRICTIONS. These regulations are contract requirements.
1.6 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements"
SECTION 01 11 00.10 Page 10
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.7 LOCATION OF UNDERGROUND FACILITIES
Obtain digging permits from the Installation prior to start of excavation and comply with Installation requirements for locating and marking underground utilities. Contact and coordinate with the local utility locating service prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.
Verify existing utility locations indicated on Contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
Notify the Contracting Officer and the Installation at least 14 days prior to starting excavation work.
1.8 DESIGN REQUIREMENTS
Follow all contract requirements for the AVBCS work and all other work included in this project.
The criteria for full or partial ACP projects are driven by the Army Standard for Access Control Points. The Army Standard for Access Control Points (ACP) was approved by the Deputy Chief of Staff, G-9 (DCS, G-9). At time of award, use latest publication in combination with the most recent version of the Army ACP Standard Design available and the most recent version of the ACP Standard Design Drawings available as the overriding criteria for any AVBCS work.
The Army Center of Standardization (COS) for Access Control Points shall approve all changes, deviations, or waivers to the Army Standard for ACP or the Army ACP Standard Design or Design Drawings. The exception and waiver process is identified in AR 420-1. Waivers to the Army ACP standards require a COS position statement and approval by HQ USACE.
In the event of conflict between References and/or Applicable Military Criteria, apply the most stringent requirement, unless otherwise specified in the contract or task order.
SECTION 01 11 00.10 Page 11
Use UFGS 34 75 13.13 CRASH RATED ACTIVE VEHICLE BARRIERS AND CONTROLS.
BARRIERS AND CONTROLS as criteria and requirements for AVBCS projects. The Designer of Record must complete this Section and incorporate it into the Design packages for each submission. Any changes to unbracketed text are considered as variations to the contract requirements. (that is, any non-bracketed text in UFGS 34 75 13.13 is a contract requirement unless determined not applicable, relevant or appropriate by DOR and accepted by the Government).
Section 34 75 13.13 will be completed to align with the prepared design and warranty management plans.
UFGS 34 75 13.13 includes notes throughout the specification, ensure you use the notes when it is tailored for the project. This is an Army project.
All updates to Section 34 75 13.13 shall be clearly annotated by highlighted and strike through font with the first Design submission.
Update annotations can be removed once intermediate design submittal package is approved.
1.9 CERTIFICATION OF WORK
Unless otherwise indicated in the SOW, active registered professional engineers, architects, and industrial hygienists shall certify Work Plan and Design documentation with their stamp and signature and ensure proper usage of codes and standards. Certify each drawing sheet. Certify the cover sheet of the technical specifications. Design documentation shall be certified by the appropriate design discipline. The contractor shall provide certification in accordance with the state and local requirements when required.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
PART 4 ADDENDUMS/ENGINEERING CHANGE PROPOSALS (ECP)
Not Used
-- End of Section --
SECTION 01 11 00.10 Page 12
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 5: 05/25
PART 1 GENERAL
1.1 SUBMITTALS
1.2 LICENSES AND PERMITS
1.3 SPECIAL SCHEDULING REQUIREMENTS
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Installation Regulations
1.4.1.1 Prohibitions for Alcohol Use, Drugs and Use of Tobacco
1.4.1.2 Anti-Terrorism and Operational Security (ATOPSEC)
1.4.1.3 ATOPSEC Training
1.4.1.4 Access and General Protection/Security Policy and Procedures
1.4.1.5 Suspicious Activity Reporting Training
1.4.1.6 Operational Security (OPSEC) Training
1.4.1.7 Pre-screen Candidates using E-verify Program
1.4.2 Contractor and Subcontractor Contacts List
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 5: 05/25
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with "G", "DA", "CR", "DA/CR" or "DA/GA" classifications. Submittals not having a classification are for information only (FIO). Submittal classifications are outlined in 01 33 00 SUBMITTAL PROCEDURES paragraph 1.9.6.1. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor and Subcontractor Contacts List;
1.2 LICENSES AND PERMITS
Obtain licenses and permits required for the construction of the project and in accordance with FAR 52.236-7 Permits and Responsiblities. Notify the Government of all general use permitted equipment the Contractor plans to use on site. This paragraph supplements the Contractor's responsiblity under FAR 52.236-7 Permits and Responsibilities.
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the construction work. The intent is to have material submittals approved prior to mobilization for construction and to have the equipment and materials delivered to and ready for use or installation prior to when they are scheduled for incorporation into the work. Material submittals cannot be submitted prior to submission of the first design package. Specific items of work to which this requirement applies to those items included in the paragraph entitled "MOBILIZATION" in Section 01 30 00 ADMINISTRATIVE
REQUIREMENTS.:
b. ACP operations will follow the guidance provided in Section 01 11 00.10 1.5.
c. Permission to interrupt any Installation roads, railroads, or utility service must be requested in writing a minimum of 30 calendar days prior to the desired date of interruption. Traffic Control Plan must already be approved prior to submitting permission to interrupt.
d. Holiday Periods for Government Review or Actions: Do not schedule meetings, Government review or responses during the last two weeks of December or other designated Government Holidays (including Friday after Thanksgiving). Exclude such dates and periods from any durations specified herein for Government actions.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
Ensure that Contractor personnel employed on the Activity become familiar
SECTION 01 14 00 Page 2 with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, including delivery vehicles, are clearly identified with their company name.
1.4.1 Installation Regulations
Follow the published policies and regulations for the Installation. These regulations are contract requirements.
Regardless of whether site of the work is on a military reservation or on a civilian installation associated with the military, all rules and regulations issued by the Commanding Officer/Director covering general safety, security, sanitary requirements, pollution control, work hours, storage areas, utility availability and use, utility interruptions, site conditions, environmental compliance, clean up, conduct and dress, work in areas with others, excavation permits, access to work areas, traffic regulations, as well as any other pertinent information requested by the Contractor or provided by the authorized installation technical representative shall be observed by the Contractor. Information regarding these requirements may be obtained by contacting the authorized installation technical representative, who will provide such information or assist in obtaining same from appropriate authorities.
1.4.1.1 Prohibitions for Alcohol Use, Drugs and Use of Tobacco
a. Alcohol Use. Alcohol use is not allowed at the project site.
b. Drugs. Possession or use of any controlled substance without a valid prescription, or use of prescription drugs intended for another person, is against the law. This includes any use of Marijuana or CBP products at any time, regardless of local laws.
c. Use of Tobacco. Do not use tobacco products, smokeless tobacco, and electric cigarettes in the workplace (that is, prohibited anywhere except for a designated smoking area). The work site may have a single smoking area located at least 50 feet from any building, roadway, sidewalk, grassed path or other areas where personnel travel or congregate. No underage workers may use tobacco (for example, the tobacco use age in the most states is 21). Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation.
Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer identifies designated smoking areas only as the areas already established by the Installation and the single work site area.
1.4.1.2 Anti-Terrorism and Operational Security (ATOPSEC)
The Contractor shall adhere to the principles of Operational Security (OPSEC) as outlined in regulation and guidance to safeguard sensitive information. This includes identifying critical information, assessing potential threats and vulnerabilities, and implementing measures to protect against unauthorized disclosure. The Contractor must ensure that OPSEC measures are integrated into all aspects of the contract's performance.
SECTION 01 14 00 Page 3
The Contractor is further responsible for maintaining the confidentiality of any classified or sensitive information encountered during the course of the project and report all violations to the Government's Contracting Officer Representative/Project Manager.
1.4.1.3 ATOPSEC Training
All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:
http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.
1.4.1.4 Access and General Protection/Security Policy and Procedures
All contractor and all associated sub-contractor's employees shall comply with applicable installations, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations
1.4.1.5 Suspicious Activity Reporting Training
The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5
SECTION 01 14 00 Page 4 calendar days after the completion of the training.
1.4.1.6 Operational Security (OPSEC) Training
All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training.
OPSEC awareness training is available at the following websites:
https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.
1.4.1.7 Pre-screen Candidates using E-verify Program
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
1.4.2 Contractor and Subcontractor Contacts List
Provide a Contractor and Subcontractors Contacts List of the Contractor Key Personnel and at least one point of contact (such as, Foreman) for each Subcontractor. Include office addresses and local telephone (such as, cell phone) numbers for use in the event of an emergency or for other communications. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 14 00 Page 5
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 SUBMITTALS
1.2 CONTRACT COST BREAKDOWN
1.3 SINGLE JOB PAYMENT ITEMS
1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.4.1 PAYMENT REQUEST PROCEDURES
1.4.1.1 Contractor Payment Alerts
1.4.1.1.1 Electronic Funds Transfer (EFT)
1.4.1.2 Progress Payments
1.4.1.2.1 RMS
1.4.1.2.2 Progress Payment Package Contents
1.4.1.2.3 Progress Payment Process and Submittal
1.5 PAYMENTS TO THE CONTRACTOR
1.5.1 Obligation of Government Payments
1.5.2 Payment for Onsite and Offsite Materials
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 Activity Cost Loading
3.2 Withholdings / Payment Rejection
3.3 Payrolls and Basic Records
3.3.1 Payroll
SECTION 01 20 00 Page 1
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with "G", "DA", "CR", "DA/CR" or "DA/GA" classifications. Submittals not having a classification are for information only (FIO). Submittal classifications are outlined in 01 33 00 SUBMITTAL PROCEDURES paragraph 1.9.6.1. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
1.2 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
1.3 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments will be made are listed in the PROPOSAL SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.4.1 PAYMENT REQUEST PROCEDURES
Submit, no more than once per month, payment requests (a.k.a., invoices, billings) using RMS to invoice costs (or agreed-to amounts based on percentage of completion, etc.) following the applicable FAR clause 52.232 (such as, "Payments under Fixed-Price Construction Contracts," "Payments Under Time-and-Materials and Labor-Hours Contracts," and "Fixed-Price Architect-Engineer Contracts"). All documents submitted for payment must reference the accounting and appropriation data included in the individual task orders. Follow the additional requirements of this section and in Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) and Section 01 32 01.00 10 PROJECT SCHEDULE.
SECTION 01 20 00 Page 2
1.4.1.1 Contractor Payment Alerts
1.4.1.1.1 Electronic Funds Transfer (EFT)
The USACE Finance Center (UFC) is altering their process for obtaining electronic funds transfer (EFT) banking information utilized for vendor contract payment and will no longer accept UFC Form 23 to update EFT banking information for vendors. Banking information for all vendors will be retrieved from SAM.gov and entered into CEFMS II. There are no exceptions to this policy change. All contractors must notify the UFC via e-mail at: cefc-fc-eft@usace.army.mil when banking information has been updated in SAM.gov. Compliance with this requirement will help ensure timely payment to the correct bank account.
1.4.1.2 Progress Payments
Prepare and submit monthly progress payment requests electronically in RMS and as an attached package via email.
Submit, no more than once per month, a payment request using RMS in accordance with the applicable FAR clause 52.232 entitled "Fixed Price," "Payments under Fixed-Price Construction Contracts", "Payments Under Time-and-Materials and Labor-Hours Contracts", and "Fixed-Price Architect-Engineer Contracts". Provide payment requests following the requirements of this section, Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM), and Section 01 32 01.00 10 PROJECT
SCHEDULE.
1.4.1.2.1 RMS
Manage the progress payment request in RMS and via email.
a. Ensure the Government has the correct Payee Office address.
b. Input a complete list of all subcontractors and the subcontract amounts.
This information is input in the section on Administration, Subcontractors.
This is a requirement of FAR 52.323-5 Payments Under Fixed-Price Construction Contracts.
c. Have an approved activity schedule (i.e., updated progress schedule).
d. Update the activity schedule with current progress percentages and quantities (a.k.a., work in place (WIP).
e. Ensure that are no CLIN or contract variances. If there is a variance that is anything but $0.00, RMS will not allow a pay request to be created until the…
This is the start of the file's text. The full file is on GovTribe.