FRP Base PWS.pdf
PDF 4 MB Posted
- Attached to
- Demolition - Facility Reduction Program, Middle and Eastern Region Federal contract opportunity
- Solicitation number
- W912DY09R0007
About this file
This is a draft copy of the base PWS. Solicitation will contain the final copy.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MidEastDraftPWS.pdf | ||
| MidWestConferenceForm.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
FACILITIES REDUCTION PROGRAM
MIDEAST U.S. MULTIPLE AWARD TASK ORDER CONTRACT
24 November 2008
U. S. Army Engineering and Support Center Huntsville, Alabama
1.0 GENERAL INFORMATION
1.1 Background
1.2 Objective
1.3 Scope
1.4 Dismantling and Demolition of Property
1.5 Contractor Management and Personnel Requirements
1.6 Access and Security Requirements
1.7 Pre-Proposal Conference and Site Investigation
1.8 Conditions Affecting the Work
1.9 Contractor Quality Control
1.10 Government Quality Assurance
1.11 Safety and Health
1.12 Construction and Demolition Waste Management and Diversion
1.13 Licensing, Bonding, and Insurance
1.14 Required Submittals
1.15 Acceptance of Plans
1.16 Unforeseen Developments
1.17 Environmental Protection
1.18 Cleanup
1.19 Performance Schedule
1.20 Performance Objectives and Criteria
2.0 DEFINITIONS
2.1 General Definitions
2.2 Technical Definitions
3.0 GOVERNMENT- FURNISHED PROPERTY/ITEMS AND SERVICES
3.1 Government-Furnished Facilities
3.2 Government-Furnished Records and Documents
3.3 Government-Furnished Landfill / Borrow Pit
3.4 Government-Furnished Utilities
4.0 CONTRACTOR-FURNISHED ITEMS AND SERVICES
5.0 SPECIFIC TASKS
5.1 Summary of Work
5.2 Emergency Response <DELETED>
5.3 Site-Specific Demolition Work Plan
5.4 Waste Management and Diversion Plan
5.5 Safety and Occupational Health
5.6 Contractor’s Quality Control Plan
6.0 APPLICABLE DOCUMENTS
6.1 References
TECHNICAL EXHIBITS
Technical Exhibit 1 – Quality Assurance Surveilance Plan Technical Exhibit 2 – Project Sites Technical Exhibit 3 – Required Reports Technical Exhibit 4 – MFRP002 Safety and Health Program Technical Exhibit 5 – MFRP007 Accident Exposure Data Report Technical Exhibit 6 – Specification Guide 02220 – Demolition Technical Exhibit 7 – Specification Guide 02221 – Excavation, Backfilling, and Site Restoration Technical Exhibit 8 – Hazardous Material and UST/AST Removal and Disposal
Technical Exhibit 9 – Requirements for Sustainable Management of Waste in Military Construction, Renovation, and Demolition Activities, dated July 2006
1.0 GENERAL INFORMATION
1.1 Background
In 2004, the Installation Management Command (IMCOM) assigned management of the OMA (Operations and Management, Army) and AFH (Army Family Housing) facility demolition programs to the U.S. Army Corps of Engineers, Huntsville Center (CEHNC). The Huntsville Center centrally manages these programs with execution accomplished through installations, Corps Districts, and Huntsville Center integrated product delivery teams. In 2005, the Installation Management Agency (IMA), now IMCOM, requested that CEHNC create an additional national contracting capability to handle the demolition/remediation requirements.
The Army installation master plans for mission transformation at Army installations include the demolition and deconstruction of buildings and structures. This is accomplished by contracting for the best overall value, while considering cost, project completion times, compliance with environmental and safety requirements, and the ability to meet and exceed industry standards for quality demolition and abatement. The Army’s Facilities Reduction Program (FRP) consists of removal, demolition and/or deconstruction of small to very large buildings and structures to include the removal of trees and vegetation, parking lots, drives, sidewalks, roadways, utility and electrical disconnections, removal and rerouting utility connections, removal of outbuildings, site-assessments, environmental assessments, abatement of facilities contaminants (i.e. lead, asbestos, chemicals, PCBs, petroleum byproducts), removal of above or underground storage tanks, recycling of building materials, redirection of debris waste streams, value engineering, site restoration, data collection, data analysis and reporting, both hazardous and non-hazardous debris transportation, environmental sampling, and other activities pertaining to demolition, destruction, reduction and restoration. Projects may also include emergency response to disasters causing either man-made or natural destruction, such as hurricanes, floods, tornadoes, terrorist activities, etc.
This performance work statement (PWS) supports the Mideast United States Facilities Reduction Program (FRP) Multiple Award Task Order Contract (MATOC) which is performance-based.
1.2 Objective
The purpose of this acquisition is to reduce the Federal Government’s inventory of excess (no longer needed) facilities, thereby saving energy and maintenance cost; eliminate safety hazards, nuisances and unsightly structures and free up valuable Army real estate for future development. In addition, Contractors must be capable of mobilizing equipment and personnel with very short notice within specified time constraints in response to man-made or natural disasters.
1.3 Scope
This contract is for commercial demolition related services. General work activities performed under this contract shall be for the planning, coordination, and execution of building and facility removal/demolition. Major aspects of the field work include, but are not limited to, facility abatement and hazardous material removal, demolition, debris management and disposition, and site restoration and cleanup. The Contractor shall provide a full range of professional services in a proficient, productive, and knowledgeable manner to efficiently and effectively accomplish all contract work. Each task order awarded under this contract is for firm fixed price (FFP). Work shall be conducted pursuant to Federal, state, county, and local laws and regulations. Required facility demolition/removal services include, but are not limited to:
� Securing the site and buildings/structures;
� Development and submission of site-specific Demolition Work Plan (DWP) to include an Environmental Protection Plan, Asbestos Containing Material (ACM) Abatement and Hazardous Materials Removal Plan;
Access/Egress and Security Plan, and Waste Management and Diversion Plan � Development and submission of an Accident Prevention Plan (APP) and a Contractor Quality Control Plan;
� Obtaining all permits and making all required notifications;
� Disconnecting, capping and/or rerouting all utilities;
� Hazardous material abatement/removal including, but not limited to ACM, mercury switches, light ballast, as well as transportation, and disposal of same;
� Removal and disposal of underground/above ground (UST/AST) storage tanks;
� Demolition of facilities � Transportation and disposal of construction and demolition (C&D) building debris materials;
� Diversion of demolition waste materials for reuse, recycling or salvage per U.S Army Policy;
� Site-restoration (backfilling, grading, reseeding, etc.); and � Tracking and submission of required submittals and reports.
Under this PWS, the contractor shall not perform Munitions and Explosives of Concern (MEC) work.
1.4 Dismantling and Demolition of Property
Except where specified or reserved by the Government in other sections, all materials and equipment dismantled, demolished, or removed, and not reused, shall become the property of the Contractor and shall be removed from Government property.
1.5 Contractor Management and Personnel Requirements
1.5.1 Contractor Management
The contractor shall provide all personnel necessary to manage and perform the services specified. The contractor shall furnish the general management, safety management, quality management, training, administration, travel, supervision, quality control (QC), supplies, materials and equipment (not otherwise furnished as Government Furnished Materials) necessary to deliver services within schedule and in accordance with contract terms and conditions, reference documents, contract and task order requirements, and contract clauses. At all times during performance of this contract, and until the work is completed and accepted, the Contractor shall directly superintend the work and have a Program/Project Manager (designated in writing), as well as an on-worksite qualified Job-Site Superintendent (designated in writing.). The Project/Program Manager must have full authority to act on behalf of the Contractor. The Job-Site Superintendent must be on the worksite during all work activities, and when absent from the job site, a fully qualified alternate shall be appointed. The Project/Program Manager and Job-Site Superintendent (and/or designated alternate) must be satisfactory to the Contracting Officer and have authority to act for the Contractor.
1.5.2 Personnel Duties, Qualifications, and Training
The Contractor is responsible for and shall ensure that all Contractor and subcontractor personnel working under this contract are fully qualified and have current and valid certifications and training for their assigned duties per all applicable Federal, state, and local regulations. Key personnel identified in the original proposal may not be substituted without written approval by the Contracting Officer. The duties, qualifications, and training requirements for the Key Personnel positions include, but are not limited to, the following:
1.5.2.1. Program Manager (Key Personnel). This is the individual who has the direct responsibility for the Contractor’s entire facility reduction program contract. This individual shall serve as the single point of contact and liaison between the Contracting Officer and the Contractor. The Program Manager should have a Bachelor’s degree from an accredited college or university in the relevant field, 6-8 years of relevant experience and/or training, or an equivalent combination of education and experience, in addition to a minimum of four years in a supervisory position.
If a Program Manager has no college degree, they shall have a minimum of 12 years relevant experience. The Program Manager should be familiar and conversant with the various environmental and safety laws and regulations applicable to facility reduction project tasks covered in the Performance Work Statement.
1.5.2.2. Job-Site Superintendent (Key Personnel). The Superintendent is the on-site person who plans, assigns, directs safe work activities for all Contractor and subcontractor personnel, and is qualified to perform as “Competent Person.” They are responsible and accountable for all work-site activities and outcomes and act as primary Contractor liaison with the Contracting Officer Representative (COR). They also conduct daily safety meetings and safety/health inspections, mishap investigations, maintain OSHA logs, and implements the APP and AHAs per USACE EM 385-1-
1. The Superintendent shall have sufficient relevant education and/or demolition and supervisory experience to effectively and properly oversee the project. Sufficient education and experience is generally, a Bachelor’s degree; 4- 10 years experience and/or training; or an equivalent combination of education and experience. The Superintendent may fulfill the Site Safety and Health Officer (SSHO) duties and responsibilities provided they are properly trained and meet minimum requirements to include, but not limited to, completion of 30-hour OSHA construction safety class and demolition safety training, as well as CPR and First Aid certification.
1.5.2.3. Site Safety and Health Officer (SSHO). When required by the nature and complexity of the project and/or specified by a task order, a dedicated Site Safety and Health Officer (SSHO) shall be provided at the work site to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor, per EM 385-1-1 and Federal, state, and local regulations. The SSHO shall have sufficient documented education, training, and experience in safety work with at least 4 years of experience on similar projects. Training shall include a 30-hour OSHA construction safety class, demolition safety training, CPR and First Aid certification.
This individual reports to the Job-Site Superintendent.
1.5.2.4. Certified Industrial Hygienist (CIH). When required by the nature and complexity of the project and/or specified by task order instructions, a dedicated Certified Industrial Hygienist (CIH) shall be provided at the work site to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor, per EM 385-1-1. The CIH shall have sufficient documented education, training, and experience, be currently certified by a State authority, and have a minimum of 3 years of field experience. The CIH shall be the safety and occupational health "Competent Person" as defined by USACE EM 385-1-1.
1.5.2.5. Crane Operators (Non-Key Personnel). Crane operators shall meet the requirements in USACE EM 385-1-1, Section 16 and Appendix G. In addition, for mobile cranes with Original Equipment Manufacturer (OEM) rated capacities of 50,000 pounds or greater, crane operators shall be designated as qualified by a source that qualifies crane operators (i.e., union, a government agency, or and organization that tests and qualifies crane operators). Proof of current qualification shall be provided. This individual reports to the Job-Site Superintendent.
1.5.3 Competent Person(s)
29 CFR 1926.32(f) defines “Competent Person” as one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them. Per EM 385-1-1, the Contractor shall, as a minimum, designate and submit qualifications for competent persons for each of the following major areas:
excavation; scaffolding; fall protection; hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents; personal protective equipment and clothing to include selection, use and maintenance.
1.5.4 Contractor Personnel
The contractor must not employ persons for work on this contract if such employee is considered by the Contracting Officer to be a potential threat to the health, safety, security, general well-being, or operational mission of the installation or its population.
1.6 Access and Security Requirements
The Contractor shall submit to and comply with each individual installation’s access control and security procedure requirements. Contractor instructions for gaining site access shall be provide in each task order. All Contractor and Subcontractor personnel may be subject to intense in-processing and vehicle searches prior to being granted access to an installation and this process may be time consuming and access may be delayed or denied. At a minimum, the Contractor should expect 100% ID check and commercial vehicle searches when entering any installation. The need for and level of installation access control measures may change during contract performance. Any changes shall be communicated to the Contractor at the time of change. Requirements for installation passes and site-specific security requirements shall be included with task order instructions.
1.7 Pre-Proposal Conference and Site Investigation
Contractors are advised to attend a pre-proposal conference/site visit and preview the project site prior to the submission of any task order proposals. During the pre-proposal conference, the Contractor shall be provided information such as local transportation routes, availability of on-site landfills and stockpile areas, hours of operation, special conditions, limitation/restrictions, and additional specifications, as required. In addition the Contractor shall have an opportunity to personally view and assess the project area(s). Future task orders may require attendance of a pre-proposal/site visit in order to respond to the RFP.
1.8 Conditions Affecting the Work
The Contractor shall be aware of, conform to, and verify all general and specific technical project terms, conditions, and circumstances before proposing on this contract or any subsequent task order resulting from this contract. During the site visit the Contractor shall take reasonable steps to ascertain the nature and location of the work, and ensure it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (l) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) the conformation and conditions of the ground; and (4) the type of equipment and facilities needed prior to and during work performance. The Contractor must satisfy itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph shall not relieve the Contractor from responsibility for properly estimating the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government. The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inherent to the type of work provided for in the contract.
1.9 Contractor Quality Control
At a minimum, quality control, as discussed in this PWS, shall apply to all task orders awarded under this contract.
The Contractor shall submit a Contractor Quality Control (CQC) Plan for review and acceptance for all task order awards. The Job-Site Superintendent shall be held responsible for the quality of work on the job. The Superintendent in this context shall be the highest level manager responsible for the overall construction activities at the site, including quality and production. The Superintendent shall maintain a physical presence at the site at all times, except as otherwise acceptable to the COR, and shall be responsible for all demolition/removal and related activities at the site. The contractor is solely responsible for the quality of all contract deliverables and should develop their products by referring to their CQC to assure service quality.
1.10 Government Quality Assurance
In accordance with FAR 52.246-4 (a) the Government shall evaluate the contractor’s performance under this contract.
For the desired outcomes listed on the Performance Requirement Summary/Quality Assuarance Surveilance Plan (PRS/QASP) (Technical Exhibit 1), the contracting officer’s representative (COR) or evaluators shall perform quality checks to assure conformance with contractual requirements during all phases of the work as outlined in Section 5 – Specific Tasks. The government may also provide the contractor with information for reasonable in-scope quality improvement that the contractor shall then implement. The specific task order awarded may provide more specific details of this process. It should be emphasized that the responsibility for effective Quality Control rests with the contractor.
1.11 Safety and Health
While performing contract services, the Contractor shall comply with safety and occupational health requirements in USACE EM 385-1-1 < http://www.ace.army.mil/publications/eng-manuals/em385-1-1/entire.pdf>, 29 CFR 1910, 29 CFR 1915, and 29 CFR 1926, as well as all other applicable Federal, state, local, and host installation laws, ordinances, regulations, and policies. In addition, all work shall conform to the current issue of the National Electrical Code (NEC), National Fire Codes (NFC), and the National Fire Protection Agency (NFPA), NFPA 101, Code for Safety to Life for Structures and Buildings, Occupational Safety and Health Administration (OSHA), Army Installation Fire Prevention Standards, and other applicable Federal, state and local regulations.
In addition to complying with the above stated references, the Contractor shall prepare and submit a site-specific Accident Prevention Plan (APP) and detailed Activity Hazard Analysis (AHA) in accordance with USACE EM 385- 1-1, Safety and Health Requirements. (See Appendix A, USACE EM 385-1-1 for minimum basic outline for APP.)
http://www.hq.usace.army.mil/soh/hqusace_soh.htm. If a Contractor is only visiting an Army installation (pre-proposal conference excepted), where they are not already performing demolition activities under an APP, they shall complete and submit a “fill-in-the-blank” Abbreviated Accident Prevention Plan (AAPP) a minimum of 5 work days prior to the visit using the template in Technical Exhibit 4 – MFRP002 Safety and Health Program, Enclosure 1. The AAAP must be reviewed and accepted by the Government before the visit can take place.
Display of Safety Information, site safety reference materials, emergency response, contingency procedures, medical treatment, accident reports, hot work requirements, hazardous materials exposure, fall hazard protection and prevention, material handling, rescue procedures, utility hazards and location verification, scaffolding, heavy equipment, and conduct of electrical work, among other safety requirements are addressed in USACE EM 385-1-1 and apply to this contract. Accidents involving personal injury/illness or property damage shall be reported to the Contracting Officer, or authorized representative, immediately.
1.12 Construction and Demolition Waste Management and Diversion Government policy is to apply sound environmental principles in the design, construction, use and removal of facilities. As part of the implementation of that policy the Contractor shall: (1) practice efficient waste management when removing, collecting, sizing, cutting, separating demolition/ deconstruction debris and (2) use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling or reuse. Waste diversion projects performed under this contract shall comply with U.S. Army Policy, Requirements for Sustainable Management of Waste in Military Construction, Renovation, and Demolition Activities, dated 5 July 2006, which means a goal of 50% (by weight) or better diversion of C&D debris from a landfill. The necessary containers, bins and storage areas to facilitate effective waste management shall be provided by the Contractor, unless otherwise specified by task order.
Unless otherwise specified in this contract, the contractor shall be responsible for the transportation and disposal of all hazardous materials from the performance of this work. The contractor shall not dispose of any hazardous materials / waste in any dumpster, sanitary sewer, storm sewer or dispose of hazardous materials / waste by any other means on government property without authorization from the Government. The contractor shall provide copies of all manifests or bills of lading for the transportation and disposal of all asbestos or asbestos containing materials to the Contracting Officer. The contractor shall immediately contain, cleanup and report all spills or release of hazardous materials, including all motor vehicle fuels, motor oil, anti-freeze, and hydraulic fluid to the host installation Fire Department and the Environmental Branch Office.
1.12.1 Management
The Contractor shall take a proactive, responsible role in the management of construction and demolition waste and require all subcontractors, vendors, and suppliers to participate in the effort. Construction and demolition waste includes all products of demolition or removal, excess or unusable construction materials and other associated items identified for removal as part of the project. In the management of waste, consideration shall be given to the availability of viable markets, the condition of the material, the ability to provide the material in suitable condition and in a quantity acceptable to available markets, and time constraints imposed by internal project completion mandates.
The Contractor shall be responsible for implementation of any special programs involving rebates or similar incentives related to recycling of waste. Revenues or other savings obtained for salvage or recycling shall accrue to the Contractor and are expected to be listed and accounted for in the final bid price. Firms and facilities used for recycling, reuse, and disposal shall be appropriately permitted for the intended use to the extent required by Federal, state, and local regulations.
1.12.2 Waste Disposition Records
Records shall be maintained to document the type and quantity of waste generated for each structure to be demolished as part of this contract. These records shall be made available to the COR during demolition, and a copy of the records shall be delivered to the COR upon completion of the project. The Project C&D Materials and Quantity Report shall contain segregated data for metals/steel salvage, concrete materials, all other recyclable and/or reusable materials, and all other debris. Other debris material that is diverted from landfills shall be so identified.
1.13 Licensing, Bonding, and Insurance
The Contractor, or their designated subcontractor, shall be licensed to perform ACM abatement and all other hazardous material removal activities in the State/Locality where the work is performed. Similarly, the Contractor shall be licensed to perform demolition work in the State/Locality where the work is performed. Work shall not proceed until all permits and licenses are approved by the COR. All insurance and bonding requirements are as stated in the MATOC contract and/or respective task order. Unless otherwise stated, the contractor is required to obtain and provide a Bid Bond amounting to 10% of the first task order. A 100% Payment/Performance Bond will be required prior to issuance of notice to proceed for each.
1.14 Required Submittals
Contractor shall provide a minimum list of submittals and/or samples to the Contracting Officer in strict accordance with the contract/task order specifications. A list of required submittals shall be included in each Task Order award issued under this MATOC. This list does not relieve the Contractor of the responsibility of insuring the accuracy or the completeness of the list or responsibility of providing all submittals required by contract documents.
1.15 Acceptance of Plans
The contractor must ensure Government acceptance of all work plan documents required and submitted under this contract prior to the mobilization and start of any on-site work activities under this contract, or any subsequent task order award. Acceptance is conditional and shall be predicated on satisfactory performance during the work activity.
The Government reserves the right to require the Contractor to make changes in his Work Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
1.16 Unforeseen Developments
The Contractor shall promptly advise the Contracting Officer or the Contracting Officer’s Representative (COR) of significant, unforeseen developments affecting the contract within 1 business day of the event. The Contractor shall take appropriate measures to obtain clarification of any direction or contract requirement which is not fully understood and incorporate such information into the work being performed.
1.17 Environmental Protection
In order to prevent, and to provide for abatement and control of any environmental pollution arising from the demolition activities in the performance of this contract, the Contractor and all subcontractors shall comply with all applicable Federal, state, and local laws and regulations and shall obtain all necessary permits required by the same.
Prior to commencement of the work, the Contractor shall submit for approval, an Environmental Protection Plan that addresses regulatory requirements. The COR shall notify the Contractor in writing of any non-compliance with the aforementioned Federal, state, or local laws or regulations. Such notice, when delivered to the authorized representative of the Contractor at the site of the work, shall be deemed sufficient for this purpose. The Contractor shall, after receipt of such notice, immediately inform the COR in writing, of the proposed corrective action and take such action, once approval has been obtained in writing from the COR. If the Contractor fails or refuses to comply promptly, the COR may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time lost, due to any such stop orders, shall be made subject of a claim for extension of time or for excess costs of damages by the Contractor.
1.17.1 Protection of Land Resources
The land resources within the project boundaries and outside the limits of permanent work performed under this contract shall be preserved as set forth in these Specifications and on the drawings. Except in areas indicated on the plans that are specified to be cleared, the Contractor shall not deface, injure, or destroy trees or shrubs, nor remove or cut them without the approval of the Contracting Officer. Ropes, cables, or guys shall not be fastened to or attached to any existing nearby trees for anchorages unless specifically authorized. Where such special emergency use is permitted, it shall be performed in such a manner as to avoid damage to the trees. The Contractor shall in any event be responsible for any damage resulting from such use and shall be required to repair or place the damage trees at no additional cost to the Government. Where the possibility exists that trees may be defaced, bruised, injured, or otherwise damaged by the Contractor's equipment or operations, the Contractor shall adequately protect such trees.
Stone, earth or other material that is displaced into undisturbed areas shall be removed. Monuments and markers shall be protected before construction operations commence. Any landscape features damaged during the performance of this contract shall be restored to original condition or to a condition approved be the COR.
1.17.2 Protection of Water Resources
The Contractor shall not pollute any streams, rivers or waterways with fuels, oils, bitumen, calcium chloride, acids, insecticides, herbicides or other harmful materials. The Contractor shall investigate and comply with all applicable Federal, state, county, and municipal laws concerning pollution of rivers and streams. The Contractor shall submit for approval a Storm Water Pollution Prevention Plan (SWPPP) in accordance with Federal, state and local requirements.
The Contractor shall conduct operations in conformance with the SWPPP. The Contractor shall also be responsible for submitting Notices of Intent (NOI) and Notices of Termination (NOT) and procuring any necessary permits required by Federal, state, county or municipal laws. A copy of the NOI, NOT and any such permits shall be furnished to the COR. Surface drainage from cuts and fills within the limits of the work shall be held in suitable sedimentation ponds or shall be graded to control erosion within acceptable limits. Temporary erosion and sediment control measures, in conformance with the SWPPP, shall be provided and maintained until the permanent work and permanent erosion and sediment control measures are completed and operative and the SWPPP is successfully closed out by the issuing authority.
1.17.3 Recording and Preserving Historical and Archaeological Finds
Any and all items having any apparent historical or archaeological interest that are discovered in the course of any construction activities shall be carefully preserved. The Contractor shall leave the archaeological find undisturbed and shall immediately report the find to the COR so that proper authorities may be notified. If an archaeological find is discovered and a job stop page is required, the delay shall not be reason for the Contractor to submit a claim against the Government.
1.18 Cleanup
The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials except as required to maintain the proper pace and flow of the demolition process. Before completing the work, the Contractor shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer. All material and debris shall be hauled to an appropriate disposal site.
1.19 Performance Schedule
The performance schedule and required delivery date for each project under this contract are reflected in the respective task order. Optional services may also be exercised in accordance with the schedule established for each project under the respective task order.
1.20 Performance Objectives and Criteria
The Contractor shall furnish all required services in a manner that best meets the following performance objectives and standards:
Timeliness, accuracy, and completeness of project deliverables;
Waste stream management (diversion);
Quality and effectiveness of practices, means, and methods;
Safety program and history;
Compliance with Federal, state, and local requirements and regulations;
Budget, cost, and productivity;
Conformance and ability to relate and respond to project requirements;
Schedule and resource management.
1.20.1 Performance Standards and Criteria
The Contractor’s performance shall be evaluated by assessing the key project deliverables described in the Performance Requirements Summary (Technical Exhibit 1) according to the five performance standards depicted below. For each of the five standards, the Contracting Officer shall assign one of four ratings for each of the Contractor’s services/deliverables.
Performance Standard
Superior Performance
Acceptable Performance
Marginal Performance
Unacceptable Performance
Quality Contractor exceeds the requirements in the PWS for the milestone/deliverable.
Deliverables are accepted after one round of comments from USACE and Regulators and no further revisions are required.
Contractor meets the requirements in the PWS for the milestone/ deliverable.
Deliverables are accepted with 2 rounds of comments from USACE /regulators and no further revisions are required.
Contractor does not meet the requirements in the PWS for the milestone/ deliverable.
Deliverables/mil estones require more than two rounds of USACE and Regulators comments before being approved.
Contractor does not meet the requirements in the PWS for the milestone/deliverable.
Milestone/deliverable is never accepted.
Timeliness Contractor exceeds the Contractor meets the Contractor fails Contractor fails to meet
Accuracy Completeness requirements in the PWS to maximize outcomes resulting in overall project completion 10% ahead of schedule with virtually no errors or omissions.
requirements in the PWS and commits only a few minor errors or omissions.
to meet all PWS requirements, is behind project schedule milestone / deliverables and/or commits numerous minor errors or a significant error or omission.
key PWS requirements, is behind schedule milestone/ deliverables resulting in significant delays impacting follow-on construction, or commits multiple significant errors and omissions
Safety No reportable or lost time accidents.
No reportable or lost time accidents above industry standards.
Reportable lost time accidents above industry standard; no regulatory citations.
Contractor has lost time accidents above industry standard and received regulatory citation for noncompliance.
Conformance and Compliance
Meets the standard for superior performance with the exception of minor differences or omissions that do not negatively impact the project or violate mandatory regulations.
All work complies with generally accepted industry best practices, as well as all local, state, and Federal statutory and regulatory guidelines.
All work conforms to contract requirements.
Commits significant exception to best practices or major omission that requires additional work/cost to resolve or minor delays to the project milestones/ schedule.
Commits multiple exceptions to best practices and/or major omissions that result in regulatory intervention, threat of fine or stop work, with major disruption in project milestones/ schedule.
Management Effectiveness
Subcontractor, labor, and equipment management is optimally effective and ensures complete compliance with requirements of the
PWS.
Planning and control of subcontractors, labor, and equipment is mostly effective and ensures sound compliance with requirements of the
PWS.
Significant lapse in planning and/or control of subcontractors, labor, and equipment which requires some rework or minor delays to the project. Fails to comply with
PWS
requirements.
Multiple lapses in planning and/or control of subcontractors, labor, and equipment.
Requires CO/COR intervention to resolve and has a significant impact on project milestones / schedule.
2.0 DEFINITIONS
2.1 General Definitions
2.1.1 Defective Service. A service output that does not meet the standard of performance requirement specified in the contract for that service.
2.1.2 Performance Requirement. The point that divides acceptable and unacceptable performance of the task according to the Performance Requirement Summary/Quality Assuarance Surveilance Plan (PRS/QASP) and the inspection of services clause. It is the number of defects or maximum percentage of defects that is acceptable.
2.1.3 Performance Requirements Summary. A listing of the services under the contract that are to be evaluated by the COR on a regular basis, the surveillance methods to be used for these outputs, and the performance requirements of the listed outputs.
2.1.4 Quality Assurance. A planned and systematic pattern of all Government actions necessary to provide confidence that adequate technical requirements are established; services conform to established technical requirements; and satisfactory performance is achieved. Quality assurance refers to actions by the Government assurance functions for a contracted service.
2.1.5 Quality Control. Those actions taken by the Contractor to control the production of outputs to ensure that they conform to the contract requirements.
2.1.6 Specialized Demolition. Demolition of a structure that is contaminated by explosives and or any other extraordinary substance. Asbestos, mercury switches, and other such ordinary hazardous wastes are not considered extraordinary substances.
2.2 Technical Definitions
ACM asbestos-containing materials AHA Activity Hazard Analysis APP Accident Prevention Plan AST above-ground storage tank C&D construction and demolition Calendar Day The time from midnight to midnight.
CIH Certified Industrial Hygienist Competent Person One who meets the requirements in 29 CFR 1926.32 (f), and is capable of identifying existing asbestos hazards in the workplace, able to select the appropriate control strategy, and has the authority to take prompt corrective measures to mitigate them.
COR Contracting Officer’s Representative is the individual appointed in writing by the contracting officer and delegated specific authority to monitor contractor performance.
CQC Contractor Quality Control DSPOYR Disposition year of removal/demolition DWP Demolition Work Plan EPA Environmental Protection Agency Facility A separate building, structure, or other real property improvements including, but not limited to, fences and utility systems.
FACNO Facility number. Real property is identified by a distinct facility number FFP Firm fixed price FRP Facilities Reduction Program ID/IQ Indefinite Delivery / Indefinite Quantity MATOC Multiple award task order contract MEC Munitions and explosives of concern OEM Original Equipment Manufacturer OSHA Occupational Safety and Health Administration NEC National Electrical Code NFPA National Fire Protection Association NOI Notice of Intent – An application for coverage under a general NPDES permit required by EPA notifying them of any construction project of .5 acres or more and the effect of such construction project on the nation’s waterways.
NOT Notice of Termination- A notice informing EPA of the closeout of a project covered under an NOI.
NPDES National Pollutant Discharge Elimination System- A program intended to eliminate discharges of sediments and other pollution into the nation’s waterways.
Performance Performance measures provide a series of indicators, expressed in Measures qualitative, quantitative or other tangible terms that indicate whether current performance is reasonable and cost effective. Performance measures can include workload and output-to-cost ratios, transaction ratios, error rates, consumption rates, inventory fill rates, timeliness measures, completion and back order rates, etc. Quality service measures may include responsiveness rates, user satisfaction rates, etc.
PRS/QASP PERFORMANCE REQUIREMENTS SUMMARY/QUALITY ASSURANCE
SURVEILANCE PLAN -The PRS/QASP lists those tasks that are key performance indicators of the function. The result is a list of key required services, standards of performance, method of surveillance, and the incentives/disincentives with respect to outcomes.
Performance A performance standard reflects the minimum, sector-specific, Federal Standard requirement for the performance of a commercial service or activity. It incorporates both quality measures and cost measures.
PWS PERFORMANCE WORK STATEMENT - A performance work statement is a statement of the technical, functional and performance characteristics of the work to be performed. Identifies essential functions to be performed and determines performance factors, including the location of the work, the units of work, the quantity of work units, and the quality and timeliness of the work units.
QA QUALITY ASSURANCE -This is a structured program used by the Army to monitor the actions of the contractor to ensure the Army gets the work done that is required by the PWS.
Quality Assurance Surveillance
Quality Assurance Surveillance is the method by which Federal employees shall monitor contract performance to ensure that the standards of the PWS are met within the agreed costs.
RFP Request for Proposal SSHO Site Safety and Health Officer SWPPP Storm Water Pollution Prevention Plan - A plan conforming to Federal, state, and local codes which addresses measures to reduce and/or eliminate discharge of sediments and pollutants to the watershed from construction sites.
TCLP Toxic Characteristic Leaching Procedure is one of the tests for the determinations of whether a solid waste is classified as a hazardous substance via EPA Method 1311.
T.O. Task Order UM Unit(s) of measure (square feet, cubic yards, etc.)
USACE United States Army Corps of Engineers UST underground storage tank Wage The wage determination sets the minimum wages and fringe benefits that Determination contractors and/or their subcontractors must pay their employees subject to the
Service Contract Act.
Work Day (WD) Normal schedule day of work not including weekends and holidays.
3.0 GOVERNMENT- FURNISHED PROPERTY/ITEMS and SERVICES
The Government shall furnish the following items and services as described below. In addition, the Government shall provide a list of host installation contacts.
3.1 Government-Furnished Facilities
The Government shall furnish a list of all facilities, buildings, structures, and appurtenances to be completely removed, or partially removed/altered as part of the demolition process. The Contractor shall receive title to all property to be dismantled or demolished that is not specifically designated otherwise by the Government/owner in this contract and/or any subsequent task order. The title shall vest in the Contractor immediately upon issuing the notice to proceed (NTP) with the work.
3.2 Government-Furnished Records and Documents
The Government shall furnish site-specific information which may include environmental surveys, hazardous material surveys, drawings, and installation policies and procedures affecting the work. The documents may include items such as local procedures for disposal of C&D materials, site limitations for working hours, travel routes, a list of Government retained property and Service Contract Act determinations. All such items, when and where available shall be provided with the respective task order RFP.
3.3 Government-Furnished Landfill / Borrow Pit
The Contract may be granted access to and use of the on-site installation landfill for disposal of various demolition and abatement debris. Availability for selected debris categories shall be provided in the respective task order. The Contractor may also be granted use of an on-site installation borrow pit for deposit of, or access to, suitable backfill materials, as the project dictates. Use of a borrow pit shall be provided with the respective task order RFP.
3.4 Government-Furnished Utilities
The Installation shall provide to the Contractor use of such utilities as are available at the site. However, determination of the existence and location of such utilities is the responsibility of the Contractor and the Installation is under no obligation to provide utilities if none is available on site. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract.
Unless otherwise provided in the contract specifications, when utilities are available they shall be furnished without charge. The Contractor, at its expense and in a workmanlike manner satisfactory to the Government, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used. Prior to final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
4.0 CONTRACTOR-FURNISHED ITEMS and SERVICES
The contractor is required to furnish all services, materials, and equipment needed to perform the requirements of this contract, except for those items specifically enumerated in Section 3. The burden of determining exactly what items and services are required to perform this contract according to all its terms is the responsibility of the contractor.
The Contractor shall provide a full range of commercial demolition services to include, but not limited to, the specific work tasks stated in Section 5, that follows. Additional detailed demolition-related services may be required, per individual task order. The objective of this contract is to remove excess existing U.S. Army and other Federal facilities using proven commercial means, methods, techniques, and best practices. Specific project details and special conditions shall be delineated in individual task orders awarded under this contract. Contractors can generally anticipate task order projects to consist of some form of ACM abatement and hazardous material removal, demolition, and site restoration.
The Contractor shall perform all services in the contract per Federal, state, and locals laws and regulations. This includes all required certifications, licenses, permits, and notifications.
The use of explosives or burning is not permitted for this work, unless explicitly requested in a project task order.
5.0 SPECIFIC TASKS
The Government intends to award a series of individual, competitive task orders under this contract, each with a distinct project / site-specific performance work statement. The specific tasks listed in this Section describe the nature and type of tasks that shall commonly be required under this contract, but may not be all inclusive. For each of these tasks/services, the Contractor must, at a minimum, meet acceptable performance levels in specialized expertise, technical approach (means and methods), safety and health, regulatory compliance, budget and productivity, schedule management, and an ability to relate and respond to project requirements. Tasks may be further defined in each individual task order.
All Contractor work shall be in accordance with applicable Federal, state, and local regulations. Additionally, the Contractor shall conform to the contract specifications stated herein, as well as the subsequent task orders. Additional applicable Technical Exhibits are provided that either mandate specific Contractor actions, provide guidance for accomplishing mandatory activities, or simply provide related information.
5.1 Summary of Work
5.1.1 Preparation and submittal of all pre-project documents. The Contractor is responsible for proper preparation and timely submission of all required contract submittals, documents, forms, permit requests, notifications, work plans, accident prevention plans, quality control plans, and related documents, as required by this contract; Federal, state, and local regulations; and each respective task order.
5.1.2 Mobilization/demobilization and work site setup. Contractor shall provide/transport all labor, equipment and materials to the work site; accomplish all site in-processing and orientation; establish work areas and set up mobile office; and install storm water protection system and temporary safety fencing as required by the respective task order.
Each demolition project shall require the posting of a project sign in accordance with USACE standards described in EP 310-1-6a and 6b.
5.1.3 Disconnect, capping, removal, re-routing of all utilities. Disconnect, cap, remove, and/or reroute utilities serving the facilities to be removed per each respective task order.