W912DW25Q8011 0001.pdf

PDF 486 KB Posted

Attached to
Amendment 0001 - Union Slough Emergency Levee Rehab Equipment
Solicitation number
W912DW25Q8011
Issued by

About this file

This document is an Amendment of Solicitation (Standard Form 30) for the Union Slough Emergency Levee Repair project, modifying a federal contract opportunity issued by the US Army Corps of Engineers, Seattle District. The amendment extends the solicitation period to 28 July 10am PST and changes the period of performance to 14 August to 30 September 2025. The project requires specific equipment including a track-mounted hydraulic excavator, wheel loader, compact excavator, hydroseeding equipment, and silt fencing, with both base and optional hour allocations for regular and overtime work.

The scope of work involves installing silt fencing, repairing/replacing armor rock along levee slopes, placing base course and topsoil, and hydroseeding disturbed areas near Everett, WA. Equipment specifications are detailed, including minimum requirements for horsepower, weight, and bucket sizes. The project will be conducted in coordination with the Emergency Management Representative, with safety requirements following EM 385-1-1 standards. The contractor must pre-screen candidates using the E-verify program and provide personnel with appropriate PPE. Payment will be based on actual hours worked, with a lump sum for mobilization and demobilization.

View the file

Other files

File Type Posted
W912DW25Q8011.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to extend the soliciation period to 28 July 10am PST and change the period of performance to 14 August to 30 September. No other changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 22-Jul-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW25Q8011

X 9B. DATED (SEE ITEM 11)

27-Jun-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-Jul-2025

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DW25Q8011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been modified:

SOW

SCOPE OF WORK

Union Slough Emergency Levee Repair

Equipment

1) EQUIPMENT REQUIRED:

Furnish all necessary supplies, materials, earthmoving, and support equipment, complete with operator.

a) CE-1, Cat 312 or Similar, Track Mounted Hydraulic Excavator w/ Hydraulic Thumb, Minimum HP 70, Minimum Weight 25,000 LBS, Minimum Reach 26 feet at Ground Level with digging and clean-out buckets.

(1) 1 each - Mobilization/Demobilization

(2) Base – 80 Regular Hours, 40 Overtime Hours

(3) Option – 40 Regular Hours, 20 Overtime Hours

b) CE-2, Cat 908 Wheel Loader or Similar, Rubber Tire, Minimum HP 70, Minimum Weight 14,000 LBS, Minimum Bucket Size 1.5 CY.

(1) 1 each - Mobilization/Demobilization

c) CE-3, Cat 304 CR Compact Radius or Similar, Track Mounted Hydraulic Excavator w/ Hydraulic Thumb, Minimum HP 45, Minimum Weight 9,500 LBS, Minimum Reach 18 feet at Ground Level with digging and clean-out buckets.

(1) 1 each - Mobilization/Demobilization

d) CE-4, Hydroseed.

2000lbs of mulch per acre 400lbs of fertilizer (10-20-20) per acre 40-80lbs of tackifier per acre 200lbs of seed per acre Seed Mix:

75-80% Tall or meadow fescue (Festuca arundinacea or Festuca elatior).

10-15% Seaside/Creeping bentgrass (Agrostis palustris).

5-10% Redtop bentgrass (Agrostis alba or Agrostis gigantea).

Site constraints require hydroseed application by hose (200ft).

(1) Base – 0.5 Acres

(2) Option – 0.25 Acres

e) CE-5, Supply and deliver - Silt Fence with wood or metal posts, with the following minimum standards.

Material: Woven polypropylene.

Width: Minimum 36 inches.

Tensile Strength: Minimum 100 lb force, conforming to ASTM D4632.

Reinforcement: An integral reinforcement layer (polypropylene or equivalent net) is required.

Permittivity: Between 0.1 sec-1 and 0.15 sec-1, conforming to ASTM D4491.

Base – 1000 Lineal Feet

2) LOCATION:

Equipment and operator furnished under this Purchase Order shall be delivered according to the attached map, near Everett, WA and in coordination with the on-site representative. See attached map for location.

3) WORK TO BE DONE:

The project consists of installation of silt fencing, repairing and/or replacing armor rock along the slopes of the levee, placement of base course and topsoil, and hydroseeding all disturbed areas.

4) COMMENCEMENT, PROSECUTION AND COMPLETION:

Work will begin as coordinated by the designated Emergency Management Representative. The anticipated period of performance (POP) is that work will start on or about 31 July 2025 and be completed by 30 August 2025. 14 August to 30 Septemeber 2025.

5) INSPECTION AND SUPERVISION:

All work will be conducted in coordination with the onsite government representative of the Emergency Management Branch, Seattle District, Corps of Engineers.

https://www.google.com/search?sca_esv=031453346484e3fe&cs=1&q=ASTM+D4632&sa=X&ved=2ahUKEwjbu5iknI-OAxWfIEQIHVYwH0sQxccNegQIFhAB&mstk=AUtExfATtQXFdXGkY69az7o51iT9mk8AW9oxBSDmzoEjWot7seN3MxyWWdmYsdyDZivn62p9TE97tm4ejoiuL7EPqw6aH2z1Im0uQTWXFwUUIHLwQk0wEHrTtnkcAWukwVUdweY&csui=3

6) SAFETY REQUIREMENTS:

Operation of equipment shall be conducted in accordance with the requirements of EM 385-1-1, “Safety and Health Requirements Manual”. All personnel are required to have PPE in accordance with EM 385 1-1.

7) SECURITY:

The Contractor must pre-screen Candidates using the E-verify Program.

(http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

8) PAYMENT AND MEASUREMENT:

a) Payment

i) Mobilization and Demobilization: Payment will be made at the purchase order lump sum price for (items including) Mobilization and Demobilization, payment of which shall constitute full compensation for assembling equipment at site preparatory to starting work, and for removing it there from at completion of the work under direction of the Contracting Officer.

b) Measurement

ii) Payment will be based on the actual hours worked as reflected by the US Army Corps of Engineers, Seattle District, rental equipment record. Invoices will show actual hours worked, partial payments authorized.

(End of Summary of Changes)

1) EQUIPMENT REQUIRED:
Furnish all necessary supplies, materials, earthmoving, and support equipment, complete with operator.
4) COMMENCEMENT, PROSECUTION AND COMPLETION:
5) INSPECTION AND SUPERVISION:
6) SAFETY REQUIREMENTS:
8) PAYMENT AND MEASUREMENT:
a) Payment