Questions for Industry:
1. Are you interested in providing One on One Input?
2. What past experience do you have with fish passages? Design and/or Construction?
3. Do you have any successes, challenges and lessons learned from other fish passages or similar projects that USACE should consider?
4. Any suggestions on constructability?
5. What would stop you from bidding on this project?
6. Are there concerns on special requirements, constraints or timing of work?
7. Any concerns on staging of materials and material transport due to the limited work area?
8. Are there concerns with materials or supplies anticipated for this project? Should USACE consider economic price adjustment being used?
9. Are there any issues with the features in the current concept, for example the fish ladder for bull trout?
10. What works well to help facilitate a successful design? What design submittals after award would you recommend?
11. What design build processes would you recommend to make this project successful, for example partnering, fast tracking, etc.
12. Any other comments?