This solicitation is for hydraulic maintenance dredging of the Snohomish River Federal Navigation Channel in Everett, Washington. The work includes removal of approximately 175,000 cubic yards of material from two areas of the channel between October 2023 and February 2024. Dredged material will be disposed of in designated placement areas.
The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Seattle. Bids are due by June 14, 2023 and the contract is to be awarded based on total price for base items plus any optional items exercised. The contractor will be required to provide dredging plant, equipment, operators, and means for transporting and placing dredged materials. The contractor must also develop safety plans and obtain necessary permits prior to starting work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ABSTRACT - 23B0006 Snohomish-Everett Dredging.pdf | ||
| 23B0006_0002 (Update WD).pdf | ||
| 2-PLANS.pdf | ||
| W912DW23B0006 Snohomish-Everett Hydraulic Dredging.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY23 Snohomish/Everett Hydraulic Maintenance Dredging.
The pupose of this amendment (0001) is to replace the spec section in it's entirety. The new section is 1 SPEC R0001.
Summary of Changes: Revised 01 11 00 SUMMARY OF WORK FOR HYDRAULIC DREDGING – Revised clarifying language in Section 1.2 regarding “The w ork includes approximately 175,000 Cubic Yards (CY).”
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-Sep-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW23B0006
X 9B. DATED (SEE ITEM 11)
17-Aug-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-Sep-2023
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CENWS-CT
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DW23B0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
(End of Summary of Changes)
FY23 Snohomish River Hydraulic Dredging 23001 Everett, WA
W912DW23B0006 01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK FOR HYDRAULIC DREDGING
08/15, CHG 1: 05/21
PART 1 GENERAL
1.1 REFERENCES
a) The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
CODE OF FEDERAL REGULATIONS (CFR)
29CFR 1910 Occupational Safety and Health Standards
29CFR 1926 Safety and Health Regulations for Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 U.S. Army Corps of Engineers Safety and Health Requirements Manual
EM 1110-2-1003 U.S. Army Corps of Engineers Hydrographic Survey Manual
1.2 WORK COVERED BY CONTRACT DOCUMENTS
a) The work is located in Everett, WA on the Snohomish River Federal Channel. The work includes approximately 140,000 175,000 Cubic yards (CY) of material from the Snohomish River Federal Navigation Channel from Station 337+07 to Station 354+47, and Sta. 65+00 to Sta. 78+00. It is anticipated the work would be performed in the Fall 2023– Winter 2024. All in-water work must be completed by 14 February 2024. The material will be dredged by Hydraulic pipeline dredge and placed in Parcel “O” and Jetty Island. Dredging will occur within the in-water construction work window of 16 OCT 2023 through 14 FEB 2024.
1.3 SUBMITTALS
a) Government approval is required for submittals with a "G" designation, submittals not having a "G" designation are for information only (FIO). Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
1) SD-01 Preconstruction Submittals
i. Construction Schedule; G
ii. Accident Prevention Plan (APP); G
iii. Activity Hazard Analysis (AHA); G
iv. Crane / Derrick Stability Analysis; G
v. Notice to Mariners; FIO
1.4 SCHEDULE
a) The Contractor shall submit an initial Schedule within five (5) calendar days after the date of receipt of the Notice to Proceed (NTP).
W912DW23B0006 01 11 00 - 2
b) Instruction and Information herein supplements requirements of FAR 52.236-15 Paragraph SCHEDULE FOR CONSTRUCTION of the CONTRACT CLAUSES and Section 01 45 00.15 10, RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM).
c) The Schedule shall show the total bid amount distributed among the features of work and show the percentage of completion at the close of each weekly period. This percentage shall be based on the percentage of physical completion of work.
d) The schedule shall be updated, at minimum, monthly and submitted with the Contractor’s pay request.
1.5 DREDGING SAFETY MANAGEMENT PROGRAM
a) The Contractor shall comply with the provisions of the EM 385 1-1, located on the following website:
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf.
1.6 SITE SAFETY AND HEALTH OFFICER (SSHO) REQUIREMENTS FOR DREDGING:
a) Site Safety and Health Officer (SSHO) Staffing for USACE Dredging Contracts. This contract requires a minimum of one full time SSHO assigned per project site for each shift. For individual dredging project sites with a workforce of less than eight (8) employees, the SSHO may be a collateral duty, with the same responsibilities as a full time SSHO.
b) The SSHO is considered part of the Contractor’s Quality Control staff. The SSHO shall receive direction and authority from the QC Manager and therefore the SSHO cannot also be the Contractor’s Quality Control Manager.
c) The SSHO must meet the following requirements:
1) A minimum of five (5) years of continuous construction industry safety experience in supervising/managing general construction (managing safety programs or processes or conducting hazard analyses and developing controls) on similar projects.
2) Thirty-hour OSHA Construction safety class or equivalent within the last four years.
3) SSHOs must maintain competency through having taken eight hours of documented formal, online, or self-study safety and health related coursework every year.
4) Competent person training as needed. Refer to EM 385-1-1 for Competent Person training requirements.
d) For projects with multiple shifts or when SSHO is temporarily off-site, a qualified Alternate SSHO (Alt SSHO) shall be assigned to always ensure SSHO coverage for the project work activities is conducted. The Alternate SSHO must meet the same requirements and assume the responsibilities of the project SSHO. The Alt SSHO position may be a collateral duty.
e) In addition to requirements stated elsewhere in these specifications, the SSHO/Alternate SSHO shall be present at the project site, located so they have full mobility and reasonable access to all major work operations, for each shift when work is being done. The SSHO or Alternate SSHO shall be available during all shifts for immediate verbal consultation and notification, by either phone or radio and be able to be on-site within 30 minutes. The SSHO/alternate SSHO shall be a full-time, dedicated position, except as noted above. The SSHO/alt SSHO shall report to a senior project (or corporate) official.
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
W912DW23B0006 01 11 00 - 3
f) The SSHO/alternate SSHO shall inspect all work areas and operations during initial set-up and at least monthly observe and provide personal oversight on each shift during dredging operations for projects with many work sites, more often for those with less work sites.
g) If the SSHO is off-site for a period longer than 24 hours, the contractor shall propose a qualified replacement SSHO who shall fulfill the same roles and responsibilities as the primary/initial SSHO. Proof of proposed SSHO qualifications and certifications shall be submitted to the Contracting Officer Representative (COR) for approval prior to the transition.
1.7 ACCIDENT PREVENTION PLAN (APP)
a) The Contractor shall submit within fourteen (14) calendar days of NTP, an Accident Prevention Plan (APP), written in accordance with EM 385-1-1, APPENDIX A.
b) If the Contractor is a currently accepted participant in the Dredging Contractors of America (DCA)/United States Army Corps of Engineers (USACE) Dredging Safety Management Program (DSMP), as determined by the DCA/USACE Joint Committee, and holds a current valid Certificate of Compliance for both the Contractor Program and the Dredge(s) to be used to perform the work required under this contract, the Contractor may, in lieu of the submission of an APP:
1) Submit the current valid Company Certificate of Compliance for its SMS.
2) Submit site-specific addenda to the SMS as specified in the solicitation.
c) Submit the current dredge(s) Certificate of Compliance based on third party audit, and a floating service Naval Architectural Analysis for all vessels utilizing floating cranes/derricks (Crane/Derrick Stability Analysis) per the Consolidated EM 385-1-1 manual.
d) Contractor shall report all Reportable Injury, Accident, Load Handling Equipment (LHE) Accident/Mishap, or Incident. Document an Injury, Accident, LHE mishap, property damage, or any other reportable incident using:
1) FORM ENG 3394
2) OSHA FORM 300
3) Send/email Form ENG 3394 to the COR.
4) Contractor staff shall immediately report all Recordable events to the SSHO and the Contractor Superintendent.
5) Contractor shall, within 24 hours of notice of the affected employee, notify the Government Safety Office and the Project COR and PM.
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
a) The Contractor shall submit within fourteen (14) calendar days of NTP, an initial Activity Hazard Analysis (AHA). The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM 385-1-1.
b) Before beginning each activity, task, or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA. AHAs must be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime Contractor review and approval before submitting to the COR. AHAs must be signed by the SSHO, Superintendent, QC Manager and the
W912DW23B0006 01 11 00 - 4
subcontractor Foreman performing the work. Format the AHA in accordance with EM 385-1-1, Section 1 or as directed by the COR.
c) AHAs must identify competent persons required for phases involving high risk activities, including confined entry, crane and rigging, excavations, trenching, electrical work, fall protection, and scaffolding.
d) Submit the AHA for review at least two (2) working days prior to the start of each phase. Format subsequent AHAs as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.
e) The AHA list will be reviewed periodically (at least monthly) at the Contractor supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.
f) Develop the activity hazard analyses using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA. The AHAs will be developed by the contractor, supplier, or subcontractor and provided to the prime contractor for submittal to the COR.
1.9 WORK HOURS
a) A proposed schedule of work hours, shifts, and days of the week shall be submitted for approval by the COR in the WORK PLAN. Notification of any proposed changes of the schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site shall be submitted to the COR for approval. Initial coordination of such proposed changes shall occur with the Government during the weekly meeting.
1.10 WEEKLY COORDINATION MEETINGS
a) Contractor-lead weekly (or more frequently if necessary, for continued project progress) coordination meetings (in person or via phone) shall be held between the Contractor and the Government. These meetings will be used to discuss the Contractor's proposed schedule, actual progress in the last week, and work planned in the upcoming two weeks. Planned work shall be shown in a scheduled format. The Contractor shall make note of any work requiring Government support. The Contractor shall keep meeting minutes and shall document all action items and decisions made. Meeting minutes shall be attached with the daily Quality Control report. A time and place shall be mutually agreed upon for the same time each week for the coordination meeting.
1.11 CORRESPONDENCE
a) All correspondence shall be addressed, at minimum, to the Government Project Manager and project COR. All copies provided shall be legible. Enclosures attached or transmitted with the correspondence shall also be furnished with the original and each copy. Each correspondence shall refer to the contract name, contract number and shall have only one subject.
b) For submission of Contractor payment requests, See Section 01 20 00, PRICE AND PAYMENT PROCEDURES and 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS
CM).
c) An informal process (without the use of serial letters) may be proposed and adopted with approval from both the Contractor and the Government.
W912DW23B0006 01 11 00 - 5
1.12 EXISTING CONDITION SURVEYS AND CROSS-SECTIONS
a) Government provided drawings are believed to accurately present conditions existing at the time the bathymetric survey was taken. There may be unknown conditions not identified. It is the Contractor’s responsibility to verify conditions.
b) Government provided drawings showing existing condition surveys and cross section sheets are furnished for information only.
c) Drawings shall be provided by the Government electronically via email or other electronic methods such as the Government’s file transfer site after the Notice to Proceed (NTP).
1.13 PROJECT SPECIFIC PHYSICAL DATA:
a) Data and information furnished or referred to below is for the Contractor's information. The Government will not be responsible for any interpretation or conclusion is drawn from the data or information by the Contractor. Please see FAR clause 52.236-4 PHYSICAL DATA for additional information.
1) Right-of-Way: The right-of-way for the work covered by these specifications will be furnished by the Government. The Contractor may use such portions of the land within the right-of-way not otherwise occupied as may be designated by the COR. The Contractor shall, without expense to the Government, and at any time during the progress of the work when space is needed within the right-of-way for any other purposes, promptly vacate and clean up any part of the grounds that have been allotted to, or have been in use by, him when directed to do so by the COR. The Contractor shall keep the buildings and grounds in use by him at the site of the work in an orderly and sanitary condition. If the Contractor requires additional working space or lands for material yards, job offices, or other purposes, he shall obtain such additional lands or easements at his expense.
2) Condition of Area: The condition of the area when last bathymetric surveyed is shown on the drawings. Topography is in feet and represents elevation with reference to mean lower low water (MLLW). Elevations above MLLW. are denoted by a (+) sign.
3) Temporary Removal of Aids to Navigation: The temporary removal or changes in locations of channel markers may be required to facilitate dredging operations. The Contractor shall notify the COR at least fourteen (14) calendar days prior to the date that the removal or change in location of channel markers will be required so the U.S. Coast Guard can perform the work and so navigation interests may be informed sufficiently in advance of the proposed removal or change in location.
4) Obstruction of Channel: The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Sections 15, 19, and 20 of the Rivers and Harbors Act approved 3 March 1899 (33 USC 410 et sec.). The Contractor shall be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon the completion of the work, the Contractor shall promptly remove his plant, including ranges, buoys, piles, and other marks placed by him under the Contract in navigable waters or on shore. No additional payment shall be made for delays due to waterway activities.
W912DW23B0006 01 11 00 - 6
5) Datum and Benchmarks: The vertical plane of reference is NOS mean lower low water (MLLW) (U.S, Survey feet, epoch 1983-2001). Horizontal control is based on Lambert Grid Projection for Washington North Zone 4601, NAD 83/2011. The Benchmarks for this area are designated as the following (Attachment 01 11 00-A):
i. 944 7659 TIDAL 5, PID SY0006. The benchmark is a metal disk stamped “5 1934”. The disk is set in the lowest step at the NW end of the NE abutment of the railroad bridge over Wall Street, 450 ft SW of the SW end of the passenger station, 18.5-ft NE of the centerline of Wall Street, 17.0-ft NW of the NW rail, 15.0-ft below the track, 3.0-ft SE of the SE end of the concrete retaining wall, and 2.5-ft above the sidewalk level.
ii. 944 7659 TIDAL 4, PID SY0004. The benchmark is a metal disk stamped “4 1934”. The disk is set into the concrete abutment on the SE end of the NE concrete abutment of the steel railroad bridge over Hewitt Avenue, 330-ft north of the railroad station, 13 rails NE of the NE end of the passenger station, 8.5-ft SE of the SE rail, 7.0-ft above the sidewalk, and 4.0-ft below the level of the overhead tracks.
iii. J7, PID SY0003. The benchmark is a metal disk stamped “J 7 ELEV 23.025 FT”. The disk is set into the concrete abutment at the Hewitt Avenue overhead bridge No. 406, in the top of the NW corner of the west stone abutment supporting steel column on the south curb line of Hewitt Avenue, 300-ft NE of the NE end of the railroad station, 17.0-ft south of the centerline of the south lane of Hewitt Avenue, and 16.0-ft north of the retaining wall face at the SW end of the underpass.
b) Overhead, Underground, and Underwater Facilities: Clearances of overhead, underground, and underwater facilities are shown when known. Each bidder shall satisfy himself as to the accuracy of locations and clearances by consultation with the owners of the facilities. See the applicable National Oceanic and Atmospheric Administration (NOAA) Chart for the location of known overhead power and telephone cables and bridges.
c) Channel Traffic: Marine Traffic consists of shallow-draft vessels, small boats, fishing boats with nets deployed, commercial, and recreational and USCG vessels. Some interference with dredging operations is to be expected.
d) Local Conditions: Utility locations and elevations are approximate, and it shall be Contractor's responsibility to obtain exact locations and elevations from owners.
1.14 LOCAL NOTICE TO MARINERS (NTM OR LNM)
a) Contractor shall request a Local Notice to Mariners (otherwise known as NTM or LNM) from the U.S. Coast Guard at least fourteen (14) calendar days prior to the start of any dredging, in writing via email:
D13-SMB-D13-LNM@uscg.mil Commander, 13th Coast Guard District (DPW) 915 Second Avenue, 35th Floor, Room 3510 Seattle, Washington 98174
b) A copy shall be submitted to the COR at least fourteen (14) calendar days prior to the start of any dredging.
c) The NTM shall be updated and submitted to the USCG any time there is a change in timing and/or work area, and at minimum, every two weeks within each work window, with a copy submitted to the COR.
mailto:D13-SMB-D13-LNM@uscg.mil
W912DW23B0006 01 11 00 - 7
1.15 PUBLIC CONVENIENCE AND SAFETY
a) Contractor shall always take necessary care in operations and use of its equipment to protect the public and to facilitate traffic.
1.16 FLOATING VESSEL
a) All self-propelled floating vessels, and operators thereof, shall be certified and conform to the requirements as specified in EM 385 1-1 (Nov 2014). Copies of the Coast Guard certification (if applicable) and crane test certificates (if applicable) shall be submitted with the APP.
1.17 SIGNAL LIGHTS
a) The Contractor shall display signal lights and conduct its operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed;
vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65-feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules:
International Inland (COMDTINST M16672.2), of 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.
1.18 PERMITS AND RESPONSIBILITIES
a) The Government has obtained the following permits/licenses related to the construction of this project:
1) Water Quality Certification(s) and WQMP details are provided in 01 57 19 TEMPORARY
ENVIRONMENTAL CONTROLS.
b) It is the responsibility of the Contractor to obtain all other permits/licenses required for this project as required under the Contract Clauses “PERMITS AND RESPONSIBILITIES.” It is the responsibility of the Contractor to comply with the provisions and conditions of these obtained permits, authorizations, and/or licenses.
c) The Contractor shall be responsible for all corrective action associated with violation of the WQC and WQMP, including both physical corrective action and financial costs associated with the corrective action, including any fines levied against the project.
1.19 TRIBAL COORDINATION
a) The project is located within the boundaries of the Tulalip Tribes’ usual and accustomed fishing area. Depending on the fish run, Tribal fishing will be occurring in the navigational channel and boat basin, in various locations and at various times during the construction operation. Dredging / Construction shall not interfere with Tribal fishermen. Prior to commencing dredging/construction activities, the Contractor shall coordinate its activities with Tulalip Tribes.
The Tribal Point of Contact is Kurt Nelson, telephone at 360-651-4485 or e-mail:
knelson@tulaliptribes-nsn.gov. The Contractor shall also provide a copy of its final dredging and disposal work schedule to Mr. Nelson prior to performing dredging operations.
b) Pursuant to the PERMITS AND RESPONSIBILITIES Clause FAR 52.236-7, Government contractors are required to comply with all laws, codes, and regulations applicable to the performance of the work. Pursuant to the FEDERAL, STATE, AND LOCAL TAXES Clause, the contract price is to mailto:knelson@tulaliptribes-nsn.gov
W912DW23B0006 01 11 00 - 8
include all applicable taxes and duties. The Government will not reimburse contractors for additional costs resulting from any tribal fees or ordinances amounting to direct taxation on the Government. Such costs, if applicable, shall be reflected in the contract price.
1.20 REQUIRED INSURANCE
a) Workers’ compensation and employer's liability: Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when Contract operations are so commingled with a Contractor's commercial operation that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in states with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.
1) General Liability:
i. The Contracting Officer shall require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $5,000,000 per person, per occurrence.
ii. Property damage liability insurance shall be required only in special circumstances as determined by the agency.
2) Automobile Liability: The Contracting Officer shall require automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the Contract. Policies covering automobiles operated in the United States shall provide coverage of at least $1,000,000 per person and $1,000,000 per occurrence for bodily injury and $1,000,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
3) Aircraft public and passenger liability: When aircraft are used in connection with performing the Contract, the Contracting Officer shall require aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability, and $200,000 per occurrence for property damage. Coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
4) Vessel liability: When Contract performance involves use of vessels, the Contracting Officer shall require, as determined by the agency, vessel collision liability and protection and indemnity liability insurance.
5) When Contract performance includes the transport, treatment, storage, or disposal of hazardous material waste the following coverage is required. The Contractor shall ensure the transporter and disposal facility have liability insurance in effect for claims arising out of the death or bodily injury and property damage from hazardous material/waste transport, treatment, storage, and disposal, including vehicle liability and legal defense costs in the amount of $1,000,000.00 as evidenced by a certificate of insurance for General, Automobile, and Environmental Liability Coverage.
6) Proof of insurance shall be provided to the Contracting Officer.
W912DW23B0006 01 11 00 - 9
1.21 PROPOSED PROJECT MODIFICATIONS
a) Price proposals for proposed modifications shall be submitted in accordance with the requirements of the Contract Clause DFARS 252.236-7000 MODIFICATION PROPOSALS - PRICE BREAKDOWNS. If change order work impacts or delays other unchanged contract work, the costs of such impacts or delays shall be included in the proposals and separately identified.
b) In conjunction with the Contract Clause DFARS 252.236-7000 MODIFICATION PROPOSALS - PRICE BREAKDOWNS, additional instructions for submitting price proposals can be found in NPSP-415-1-1 INSTRUCTION AND INFORMATION FOR CONTRACTORS. When information regarding when actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the EP 1110-1-8, Vol 8.
1.22 SURVEY
a) Quantity Surveys
1) The Government shall conduct the bathymetric surveys of the dredged work area for any periods for which progress payments are requested and shall make the computations based on these bathymetric surveys. Bathymetric surveys will be conducted at a frequency no greater than once every two weeks (fourteen (14) calendar days) but may occur more frequently at the discretion of the COR. Failure by the Government to adhere to these bathymetric survey schedules shall not be the basis for a claim by the Contractor or subcontractors for extra compensation for any reason. Additional bathymetric surveys can be requested by the COR if/when unusual circumstances arise or as required by the COR.
2) COVID-19 Contingency – If there are state, federal, and/or USACE-specific restrictions due to COVID-19 that prevent the normally performed surveys, surveys will be conducted as soon as possible, within the allowable restrictions and requirements.
3) Hydrographic surveys will be conducted by the Government to meet USACE Performance Standards as defined in the Hydrographic Surveying Manual EM 1110-2-1003. Surveys will be conducted utilizing depth sounding and horizontal positioning equipment. Sounding depths will generally be derived utilizing multi-beam or single-beam acoustic methods.
However, the Government reserves the right to take soundings by any method, including a lead line or trigonometric leveling (total station)/differential leveling. The same method will be used for the before dredge (BD), progress, and after dredge (AD) surveys of a given pay area.
4) Cubic yard volumes will be computed by comparing the Government's bathymetric soundings against the channel design template. The Government intends to use Hypack v2016 or later, or Bentley InRoads Software Package versions v8i or Bentley OpenRoads Software Package version (current version) or later to compute pay volumes. Computed pay volumes will be the difference between the computations of the BD and AD surveys.
Volumes may be computed by comparing the Government's bathymetric progress soundings against other progress surveys, or an after-dredge survey, but only at the COR’s discretion.
5) All Contractor owned equipment including all attendant plant, pipes and anchor lines in the survey area must be removed from the acceptance area prior to the initiation of all BD and AD dredge surveys. Any failure by the Contractor to remove attendant plant, pipes and anchor lines in the survey area may result in the postponement of the government survey.
W912DW23B0006 01 11 00 - 10
6) All surveys conducted by the Contractor shall be in accordance with the USACE Hydrographic Surveying Manual EM-1110-2-1003. Accuracy(ies) will be in accordance with stated quality control values in USACE Hydrographic Surveying Manual EM-1110-2-1003.
7) The Contractor is responsible for requesting Government BD and AD surveys of all work areas. The request shall be submitted in writing to the Government representative(s) identified at the pre-construction conference. The Government Survey periods stated above are contingent on availability of government equipment, weather, and sea conditions.
8) In the event it becomes necessary to reschedule a request for a survey, the Contractor shall notify the Government at least two (2) working days prior to the first day of the scheduled survey period.
9) All depths obtained from multibeam surveys will be utilized for volume computation purposes. Multibeam surveys will use a 2-foot-by-2-foot matrix using the median depth of all depths recorded in a cell will be generated from the edited multibeam data to perform the TIN volume computations, following the procedures outlined in EM 1110-2-1003. Any corresponding plotted plan view sounding sheets depicting representative depths over a dredging project will be generated using a cell size that is plot-scale dependent, utilizing a randomly selected sounding that is closest to cell center (shot depth) shifted to the center of the cell from the edited multi-beam data, as described in EM 1110-2-1003. All edited/processed bathymetric survey data (xyz) used for volume computations shall be made available to the Contractor upon request.
10) No separate payment will be made for impacts associated with these surveys.
b) Positioning Equipment
1) Dredging and material placement plant shall be positioned using a differential GPS with an accuracy of +/- 3 feet. The system shall be used to ensure that dredging is performed within the designated pay area(s) and that material will be evenly distributed within the dredged material placement areas, as shown. Any delay or suspension for noncompliance of this requirement will be at no cost to the Government nor shall it be considered grounds for a time extension.
c) Gauge Equipment - Tide Data
1) All vertical control shall be referenced to the Government staff gauge provided by the Government at the pre-dredge meeting. The datum used for each project is specified on the layout charts. The Contractor shall check the operation of the automatic tide gauge, or temporary tide board at least twice daily by comparing readings to the specified gage board.
The QC reports shall reflect the time and results of these inspections.
d) Dispute of Surveys Performed by the Government
1) If the Contractor disputes the accuracy of any survey performed by the Government, the Contractor shall immediately notify the COR in writing, concerning the nature of the dispute.
If the dispute cannot be resolved immediately, the Contractor shall immediately resurvey the shoal using multibeam, or all remaining areas that have not been dredged or unaffected portions of the shoal with a Government representative onboard the Contractor’s survey boat. At the conclusion of the survey, the Contractor shall provide copies of all raw and edited data files for that shoal. The files shall be in Hypack format. The Contractor shall submit the following information (as a minimum) in support of the survey data:
W912DW23B0006 01 11 00 - 11
i. Edited survey data in xyz format (2x2 and 5x5 matrix); coordinates shall be WA State Plane Coordinates, NAD 1983.
ii. Method of horizontal and vertical positioning used (RTK or Tide Gauge).
iii. Date, time, and stage of tide.
iv. Water surface conditions.
v. Plan drawing in pdf format showing the edited depth soundings.
vi. Plotted cross sections of the latest Contractor survey compared with the Government survey. The individual cross sections shall be performed at 25 feet increments.
vii. Plan drawing in pdf format of channel showing areas that were worked by the dredge.
viii. Speed of sound through the water column in the area of survey and method used to determine the speed of sound.
ix. Draft of survey boat and method used to determine the draft.
x. A table listing the status of all calibrations to include patch performance test area designated by the COR and required by EM 1110-2-1003, HYDROGRAPHIC SURVEYING MANUAL, and the date equipment was set up and last checked.
2) The Government will evaluate the data provided by the Contractor and use this information to evaluate and make a determination of the dispute.
1.23 CONTRACTOR FIELD OFFICE
a) The Government is not responsible for providing Contractor work areas. If used, the Contractor shall locate all field office elements at one site, regardless of the numbers and types of equipment used. The Contractor shall be responsible for identifying a location and making all and any arrangements with the property owner. If a Field Office location is used, it shall be identified in the Contractor Quality Control and Work Plan.
1.24 CONTRACTOR PLANT AND EQUIPMENT
a) Unless otherwise specifically cited elsewhere in these specifications, the Contractor shall provide vessels, barges/scows, cranes, rigging, lifts, operators, and other necessary means to unload, load, and move equipment or materials as required to perform the work.
b) Complete Plant and Equipment List to be used onsite shall be provided to the COR. The Contractor shall update and submit this list monthly with each progress payment request. The list shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The list shall indicate dates equipment is assigned to or removed from the project, dates scheduled for repairs and returned for use, and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
c) The Contractor’s equipment shall be conspicuously marked for identification. Contractor vehicles shall be marked on the outside with the company name.
d) Any barge used as a base for any equipment or materials shall not be allowed to ground. Any positioning shall be accomplished using anchors or spuds.
W912DW23B0006 01 11 00 - 12
1.25 CONTRACTOR PROPERTY SECURITY
a) The Government is not responsible for providing security for Contractor work areas and Contractor-owned/controlled equipment, supplies, or materials. The Contractor shall provide those necessary security measures.
1.26 INSPECTION
a) The presence of the Government inspector shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with the specifications. The Contractor shall:
1) Furnish, on the request of the COR or any inspector, the use of such boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the dredging plant as may be reasonably necessary for inspecting and supervising the work.
However, the Contractor will not be required to furnish such facilities for the surveys, as prescribed in the clause entitled "Final Examination and Acceptance."
2) Furnish, on request of the COR or any inspector, suitable transportation for Government inspectors from all points on shore designated by the COR to and from the various pieces of plant and to and from placement/disposal areas. If the Contractor refuses, neglects, or delays compliance with these requirements, the specific facilities may be furnished and maintained by the Government, and the cost thereof will be deducted from any amounts due, or to become due, the Contractor.
3) On the request of the COR or any inspector, allow the Government to temporarily install a construction camera, provided by the Government, on the dredge vessel. In general, the location provided shall provide for a 360-degree viewpoint permitting the observation of the crane deck and dredge barge. The mounting point shall consist of a wooden or metal stanchion, a minimum of 3 inches in diameter, but not greater than 6 inches in diameter. In addition, the contractor shall provide a source of electrical power consisting of 110v, 20 Amp. Power for the camera must be provided at all times the vessel is dredging and when scow filling activities are occurring. Mounting location shall be agreed upon after contract award. Contractor shall be given access to the camera’s web-based video feed.
4) At the Government’s discretion, if the Government designated QA representative is unable to be physically present at the Contractor’s plant to verify the CQC procedures, the Contractor must provide real time video capability for the Government to perform inspections, witness tests, participate in meetings, and other tasks of a similar nature.
Anticipating these efforts may take up to 3 hours each week.
5) At the Government’s discretion, QA equipment inspections may be completed from a distance using electronic methods such as a video chat or live-time video call (compatible with Government cell phones or computers). The Contractor must provide real time video, if requested by the Government, for the Government to perform the inspection remotely, and anticipate the inspection may take up to 3 hours each week.
6) No separate payment will be made for impacts associated with Government QA inspections.
1.27 SHOALING
a) If, before the Contract is completed, shoaling occurs in any section previously accepted, including shoaling in the finished channel, because of the natural lowering of the side slopes, re-dredging at the contract price, within the limit of available funds and time, may be done if agreeable to both the Contractor and the COR in writing before work commences.
W912DW23B0006 01 11 00 - 13
1.28 PROTECTION AND RESTORATION OF PROPERTY
a) The work shall include the preservation of all public and private property, monuments, power and telephone lines, other utilities, etc., along, and adjacent to the disposal areas insofar as they may be endangered. All utility lines shall be repaired immediately at the Contractor’s expense.
Contractor shall coordinate with the public utility companies, agencies, and property owners.
Contractor shall provide temporary utility services if necessary. When or where any direct or indirect damages or injury are done to public or private property by, on account of, any act, omission, neglect, or misconduct in the execution of the work, or in consequence of the non-execution thereof, such property shall be restored to a condition similar and equal to existing before such damage or injury was done. The restoration shall be completed before the final acceptance of the project.
1.29 FINAL EXAMINATION AND ACCEPTANCE
a) As soon as practicable after the completion of the entire work or any section or subsection thereof (if the work is divided into sections and/or subsections) as in the opinion of the COR will not be subject to damage by further operations under the Contract, such work will be thoroughly examined at the cost and expense of the Government by sounding or by sweeping, or both, as determined by the COR. Acceptance will be based on the removal of all dredge material above the “Required Dredging Depth.” The Government will verify full removal by visual examination of a bathymetric drawing showing multi-beam survey data, that is plot-scale dependent, utilizing a randomly selected sounding. If there are sections of concern, an additional analysis using cross-sections at 25-foot intervals from a 2x2 or 5x5 matrix surface will be used to confirm whether the material was removed to the specified depth required in the channel prism, including channel side-slopes. If any shoals, lumps, or other lack of Contract depth be disclosed by this examination, the Contractor shall be required to remove these areas by dredging at the Contract rate for dredging. If the bottom is soft and the shoaled areas are small and form no material obstruction to navigation, the removal of such shoal may be waived by the discretion of the COR. The Contractor or his authorized representative will be notified when soundings and/or sweepings are to be made and will be permitted to accompany the survey party. When the area is found to comply with contract specifications, it will be accepted.
b) Final acceptance of the whole or a part of the work and the deductions or corrections of deductions made thereon will not be reopened after having once been made, except on the evidence of collusion, fraud, or obvious error, and the acceptance of a completed section shall not change the time of payment of the retained percentages of the whole or part of the work.
1.30 CONTRACTOR PERFORMANCE EVALUATIONS
a) In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), the Contractor’s performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $700,000.00, the USACE will evaluate contractor’s performance and prepare a performance report using the Contractor Performance Appraisal Reporting System (CPARS). After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of sixty (60) calendar days. Access is granted by a network of government Focal Points. Typically, there are many Focal Points assigned to the agency. If you require assistance with identifying your Focal Point, please email the CPARS helpdesk
W912DW23B0006 01 11 00 - 14
(webptsmh@navy.mil) with the contract/order number you are trying to access, and they will provide the Contractor with the Focal Point name and contact information.
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
NOT USED
--END OF SECTION--
IFB No. W912DW23B0006
Date: 14 JUNE 2023
FY23 Snohomish River Hydraulic Dredging Everett, Washington
Invitation For Bid
DB SP JOB# 23001
23001 FY23 Snohomish River Hydraulic Dredging
W912DW23B0006 00 11 00 - 1
00 11 00
BID SCHEDULE
ITEM
NO. DESCRIPTION OF ITEM
ESTIMATED
QUANTITY
(Note 1) UNIT
UNIT
PRICE AMOUNT
BASE ITEMS
1000 Mobilization and Demobilization 1 JOB N/A $
2000 Dredging and Disposal (Sta.
337+07 to Sta. 354+47) 85,000 CY $ $
3000 Dredging and Disposal (Sta.
65+00 to Sta.78+00) 28,000 $ $
TOTAL ESTIMATED AMOUNT BASE ITEMS: $
OPTIONAL ITEMS
(Note 2) Additional Dredging and Disposal (Sta. 337+07 to Sta. 354+47)
4101 Additional Dredging and Disposal 5,000 CY $ $
4102 Additional Dredging and Disposal 50,000 CY $ $
(Note 3) Additional Dredging and Disposal (Sta. 65+00 to Sta. 78+00)
5101 Additional Dredging and Disposal 2,000 CY $ $
5102 Additional Dredging and Disposal 5,000 CY $ $
TOTAL ESTIMATED AMOUNT OPTION ITEMS: $
TOTAL ESTIMATED AMOUNT BASE & OPTION ITEMS: $
NOTES FOR CONTRACT LINE ITEM (CLIN) SCHEDULE
Note 1: Quantities are ESTIMATED except where shown as “JOB”.
Note 2: Option Item No. 4101 is the first subline item and Option Item No 4102 is the second subline item under Item No. 4100.
Note 3: Option Item No. 5101 is the first subline item and Option Item No 5102 is the second subline item under Item No. 5100.
Note 4: Bids shall not be submitted for quantities less than those specified for each line item.
Note 5: Offerors must insert a price on all numbered items of the Bid Schedule. Prices are on a unit basis. Failure to include pricing for all quantities of all line items will result in the rejection of the bid as non-responsive.
23001
W912DW23B0006 00 11 00 - 2
FY23 Snohomish River Hydraulic Dredging Everett, WA
Note 6: The contract price will be evaluated based on the total price of all options exercised the maximum number of times, added to the total price of the base items.
DEFINITIONS FOR CONTRACT LINE ITEM (CLIN) SCHEDULE
CY = Cubic Yards
W912DW23B0006 01 00 00 TOC - 1
SECTION 01 00 00
TABLE OF CONTENTS
TECHNICAL SPECIFICATIONS
Section No. Section Title
00 11 00 Bid Schedule
01 00 00 Table of Contents
01 11 00 Summary of Work
01 11 00-A Project Benchmarks
01 20 00 Price and Payment Procedures
01 33 00 Submittal Procedures
01 33 00-A Example Submittal Transmittal Form 4025
01 33 00-B Draft Submittal Register Form 4288
01 45 00.10 20 Quality Control
01 45 00.15 10 Resident Management System Contractor Mode (RMS CM)
01 57 19 Temporary Environmental Controls
01 57 19-A Washington Department of Ecology Water Quality Certification (WQC)
01 57 19-B Water Quality Monitoring Plan (WQMP – Hydraulic Dredging)
35 20 23 Dredging
35 20 23-A U.S. Geologic Survey (USGS) Wentworth Grade Scale
35 20 23-B Dredging Best Management Practices (BMPs)
W912DW23B0006 01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK FOR HYDRAULIC DREDGING
08/15, CHG 1: 05/21
PART 1 GENERAL
1.1 REFERENCES
a) The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
CODE OF FEDERAL REGULATIONS (CFR)
29CFR 1910 Occupational Safety and Health Standards
29CFR 1926 Safety and Health Regulations for Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 U.S. Army Corps of Engineers Safety and Health Requirements Manual
EM 1110-2-1003 U.S. Army Corps of Engineers Hydrographic Survey Manual
1.2 WORK COVERED BY CONTRACT DOCUMENTS
a) The work is located in Everett, WA on the Snohomish River Federal Channel. The work includes approximately 140,000 175,000 Cubic yards (CY) of material from the Snohomish River Federal Navigation Channel from Station 337+07 to Station 354+47, and Sta. 65+00 to Sta. 78+00. It is anticipated the work would be performed in the Fall 2023– Winter 2024. All in-water work must be completed by 14 February 2024. The material will be dredged by Hydraulic pipeline dredge and placed in Parcel “O” and Jetty Island. Dredging will occur within the in-water construction work window of 16 OCT 2023 through 14 FEB 2024.
1.3 SUBMITTALS
a) Government approval is required for submittals with a "G" designation, submittals not having a "G" designation are for information only (FIO). Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
1) SD-01 Preconstruction Submittals
i.…