Text version

Question Date Received Government Response Government

Response Date Notes

Neither the Performance Work Statement, Request for Quote, or Price Schedule include updating the current CIP or preparing the community interview report, which are the 2 required documents from the Performance work statement, where in the CLIN pricing schedule is that level of effort to be captured?

25-Jan-22

The PWS describes the CIP update and interviews and indicates them as the two deliverables for Task 2.

CLINs will be added to the RFQ and price schedule include Task 2 Deliverables. 1-Feb-22 Please see Amendment 0001

The Performance work statement indicates that there will be at least 2 additional public meetings to address the Upland OU and the River OU, but neither of these is captured on the request for Quote or pricing schedule. 25-Jan-22

These two meetings will be added to the CLINs and price schedule for Task 3.2. 1-Feb-22 Please see Amendment 0001

Can you clarify/ expand upon what is meant by maintain the administrative record repository? And where is that level of effort to be captured as part of the CLINs?

25-Jan-22

The PWS describes the CIP update and interviews and indicates them as the two deliverables for Task 2.

CLINs will be added to the RFQ and price schedule include Task 2 Deliverables. 1-Feb-22 Please see Amendment 0001

W912DW22Q4000 - Q&A as of 01 February 2022