Amendment W012DW21Q0003_0002 for PWS Updates and Pre_bid Q_A.pdf

PDF 761 KB Posted

Attached to
Lake Washington Ship Canal (LWSC) Dive Inspection
Solicitation number
W912DW21Q0003
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

a. The purpose of this amendment is for the follow ing:

1. Replace the Performance Work Statement w ith the enclosed version, dated 14 December 2020, for updates as show n in the track changes.

2. Provide for responses to pre-bid questions as enclosed.

b. The response time and date remains the same at 11:00AM, Pacific Time, 20 January 2021.

c. All other terms and conditions of the solicitation remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Dec-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW21Q0003

X 9B. DATED (SEE ITEM 11)

02-Dec-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Dec-2020

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

Pre-Bid Questions and Answers (Q&A)

1. Does inspection and cleaning of the Adult Salmon Exclusion structure include removal/opening of the intake screen and penetration into the vault?

Response: No, it does not.

2. In the past the locks have been shut to allow inspection of this structure. What is the allowable work window for inspection and cleaning?

Response: Eight hours for large lock seals. Eight hours for small lock seals and salmon exclusion structure area. Two hours for fish ladder area inspection. Two hours for pump plant discharge area.

3. The Performance Work Statement (Section 5.7-D) calls for an on-site decompression chamber. This is not required by EM385-1-1, given the depth (approx. 10 meters).

Response: The requirement is clarified in the relevant Section 5.7-D. Contractor needs to plan for risk mitigation methods and emergency actions. For example, factor for downtown traffic when the decompression facility is off site.

4. What will be the deepest dive needed to be done? It looks like nothing past 60ft will be done? Can you confirm dives will not be beyond 60 ft?

Response: If the question is referring to the depth, then yes we expect the depth to be less than

60 feet. However, the actual depth is tide and lake level dependent.

5. Will awarded companies be eligible to bid on construction/repair contracts identified by the inspection services outlined in this solicitation? Some state agencies do not allow firms who provided design services for a project to bid on the construction component when released for bid, as an example.

Response: There would be no issues with the contractor bidding on the dive inspection. We are not planning on underwater construction.

PERFORMANCE WORK STATEMENT (PWS)

Dive Inspection for

U.S. Army Corps of Engineers (USACE), Seattle District, Operations Division

December 14, 2020

Part 1

General Information

1.0. General: This is a non-personal professional service to provide dive inspection services for the Lake Washington Ship

Canal at Seattle, WA. The Government shall not exercise any direct supervision over the contract service providers performing the services herein.

1.1 Description of Services/Introduction: Contractor will perform underwater dive inspection and cleaning of the Adult

Salmon Exclusion Device, Large Lock inspection and minor maintenance, Large Lock salt water discharge system inspection, Fish Ladder inspection, miter gate inspection and other area inspections as needs arise. This service may include in water work activities, like underwater pressure washing, in water ice blasting, in water welding, and underwater rigging.

1.2 Background: The LWSC lies entirely within the City of Seattle and extends from deep water in Puget Sound through

Shilshole Bay, the locks, Salmon Bay, Lake Union, Portage Bay and Union Bay to deep water in Lake Washington. The

Hiram M. Chittenden Locks are located at the southern end of the Ballard neighborhood of Seattle, approximately 1 mile southeast of Shilshole Bay.

The 235-foot-long concrete gravity spillway dam is located between the small lock and the fish ladder on the south shore.

The spillway consists of six 32-foot-wide bays, each controlled by a 12.5-foot-radius tainter gate equipped with an individual electric motor-driven, cable drum-type gate hoist. The tainter gates and trunnions were replaced in 2014 due to corrosion of the original gates. The crest shape approximates that of a standard shaped ogee, having a design head of 7.4 feet, a crest elevation of 10.50 feet (13.75 ft. COE), and a weir height-to-design head ratio of approximately 1.0. Guide slots are located in the piers for installation of bulkheads for maintenance closure of the spillway bays. The spillway is capable of discharging up to 18,200 cubic feet

The salt water return system consists of the old salt water drain and fish attraction diffusion pipe. The fish attraction diffusion pipe was added to the saltwater drain in the mid-1970’s. The saltwater drain segment that is downstream of the diffusion pipe became known as the old saltwater drain. The inlet for the salt water return system is a 30 square foot grated opening at the bottom of the ship canal at the east end of the large lock south wall. A trashrack was originally placed at the entrance of the drain to minimize debris and prevent fish from entering the drain and fish ladder system, but since has been removed because of continual clogging problems. In 2008, a temporary screen was re-installed to prevent fish from entering the system. The temporary screen is known as the Adult Salmon Exclusion Structure (ASES) and can be opened from September to May to prevent clogging during winter storms. After entering the inlet, salt water return flow is conveyed westward back toward

Puget Sound through a five foot by six foot closed conduit to a point just east of the dam structure. Here a "Y" joint splits the conduit with one fork proceeding west through the old salt water drain and exiting via a gated spillway between the south wall of the small lock and spillway gate number 1. The total length of the drain between the inlet and the gated spillway is 660 feet. The other fork can carry salt water return flow southward through the fish attraction diffuser pipe (a 400 foot long, six foot diameter conduit) along the bottom of the Ship Canal to the diffusion well at the foot of the fish ladder facility.

Here the water is distributed among the lower ladder steps and empties out to Shilshole Bay. The saltwater drain and fish attraction diffusion culvert may be operated either concurrently or separately. The design operating capacity of the saltwater return system is about 330 cfs (this assumes discharge through both forks downstream of the “Y” joint). The diffusion pipe has a slide gate which is used to stop flow through the pipe for annual maintenance of the fish ladder facility or if required for other purposes such as water conservation. The original design of the diffusion pipe contained a butterfly valve which would work in concert with tide and lake elevation sensors to provide a constant fish attraction flow of approximately

160 cfs.

1.3 Objective:

1.3.1 BASE YEAR

CLIN 0001 (Base Item): Perform inspection and cleaning of the adult salmon exclusion structure.

CLIN 0002 (Option Item:) Additional dive services around the Lake Washington Ship Canal. Locations include Montlake

Cut and Fremont Cut. The contractor shall provide a price quote for each dive operation. Performance shall not exceed the contract amount and will be reimbursed based on the actual hours performed and the contract hourly rate for this CLIN.

1.3.2 OPTION YEAR 1

CLIN 1001 (Base Item) Perform inspection and cleaning of the adult salmon exclusion device for another year, include opening and closing the doors. (annual fishing season).

CLIN 1002 (Option Item) Additional dive services around the Lake Washington Ship Canal during option year 1. Locations include Montlake Cut and Fremont Cut. The contractor shall provide a price quote for each dive operation. Performance shall not exceed the contract amount and will be reimbursed based on the actual hours performed and the contract hourly rate for this CLIN.

1.3.3 OPTION YEAR 2

CLIN 2001 (Base Item) Perform inspection and cleaning of the adult salmon exclusion device for another fishing year.

CLIN 2002 (Option Item)

Additional dive services around the Lake Washington Ship Canal during option year 2. Locations include Montlake Cut and

Fremont Cut. The contractor shall provide a price quote for each dive operation. Performance shall not exceed the contract amount and will be reimbursed based on the actual hours performed and the contract hourly rate for this CLIN.

1.4 Scope: Provide equipment, vessel, and personnel to perform dive inspection and minor maintenance service. Dive inspection service can contain minor manipulation of underwater structures, making videos, making measurements, and writing reports. Minor maintenance will include clean, mechanical repairs, removing and retrieving items and underwater rigging. More details are provided in part 5 of this PWS.

Contractor shall have SCUBA, rebreather, or similar equipment for prolonged underwater activity.

1.5. Period of Performance: (To be updated at award)

Base Year 1 March 2020 through 28 February 2021

Option Year 1 1 March 2021 through 28 February 2022

Option Year 2 1 March 2022 through 28 February 2023

NOTE: For option items, the Government may exercise option items by issuing written notification within 10 working days prior to performance. If exercised, the period of performance for option item will not be extended.

1.6 General Information

1.6.1 Quality Assurance: The Government may evaluate the Contractor’s performance under this contract in accordance with

Technical Exhibit 1, the Quality Assurance and Performance Requirement Summary. This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.6.2 Recognized Holidays: The Contractor is not required to perform duty on the following recognized holidays:

New Year’s Day Labor Day

Martin Luther King Jr.’s Birthday Columbus Day

President’s Day Veteran’s Day

Memorial Day Thanksgiving Day

Independence Day Christmas Day

1.6.3 Hours of Operation: The Contractor is responsible for setting their own hours of business. However, the Contractor must provide adequate support to achieve required performance objectives of section 5 for the duration of the performance period. The government has regular business hours: Monday through Friday, 0700-1500 (Pacific Time).

1.6.4 Place of Performance: The work described in this PWS is to occur at the contractor’s facility and shall be within 5 miles of the following locations: Lake Washington Ship Canal, 3015 NW 54th ST., Seattle, WA 98107.

1.6.5 Type of Contract: Firm Fixed Priced contract.

1.6.6 Security Requirements: Contractor personnel performing work under this contract are not required to have a security clearance to perform the services contained in this contract.

1.6.7 Personally Identifiable Information (PII): Contractors shall perform the work as outlined in this scope of work in compliance with HIPPA (Health Insurance Portability and Accountability Act).

1.6.8 Special Qualifications: All divers and supporting personnel shall be qualified (or licensed, or certified) by applicable federal, state, and local government regulations.

1.6.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation

Subpart 42.5, Post Award Orientation. The Contracting Officer (KO), USACE Operating Project Administrative Officer

(AO), and other Government personnel, as appropriate, may meet periodically at a mutually determined location with the

Contractor to review the contractor's performance. At these meetings the KO will apprise the Contractor of how the

Government views the contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.6.10 Key Personnel: The follow positions are considered key personnel by the government, contact information will be provided with after contract award:

Quality Assurance Representative - The QAR is an employee of the U.S. Government designated by the Contracting Officer to assist in administering a contract. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

Government Dive Coordinator and Safety Office. This person is a government employee with dive operation experience.

This individual may stop the dive operation if any safety concerns has been identified. This person may also review and comment on the dive operation package submitted by the contractor prior to actual diving operation.

1.6.11 Contractor Point of Contact: The Contractor shall provide a point of contact who shall be responsible for replying to any inquiries that may arise as result of the work performed by this contract. The name of this person and an alternate who shall act for the contractor when the point of contact is absent shall be designated in writing to the contracting officer. The contractor shall immediately notify the contracting officer and USACE Operating Project Manager if the contractors point of contact or alternate change.

1.6.12 Contractor Travel: None.

1.6.13 Reserved:

1.6.14 Other Direct Costs: There are no other direct costs associated with this contract that are reimbursable by the

Government. Any and all other direct costs incurred by the Contractor are not reimbursable by the Government (e.g., photocopying, shipping expenses, and travel).

1.6.15 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to, or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.), or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI.

1.6.16 Phase In/Phase Out: Not Applicable.

1.6.17 Antiterrorism (AT) and Operations Security (OPSEC): Not Applicable.

1.6.17.1 Access and General Protection/Security Policy and Procedures:

All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative).

The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.

Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal

Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

16.17.2 Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database

(TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

16.17.3 Pre-screen candidates using E-Verify Program:

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of

Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment

Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting

Officer (or COR) and shall become part of the official contract file.

17.1 Invoice Submission: Invoices should reflect the CLIN numbers associated with the work performed and be submitted to the following address:

Lake Washington Ship Canal

U.S. Army Corps of Engineers

ATTN: Rose Hublitz

3015 NW 54TH ST

Seattle WA 98107

Phone: 206-297-9738

Rose.E.Hublitz@usace.army.mil

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. DEFINITIONS:

2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the Government.

The term used in this contract refers to the prime contractor.

2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the

Government.

2.1.3. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the

Performance Work Statement.

2.1.4. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.5. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.6. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.7. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.8. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.9. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.10. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.11. WORK WEEK. Monday through Friday, 0700-1500 (Pacific Time), unless specified otherwise.

2.2. ACRONYMS:

ACOR Alternate Contracting Officer's Representative

AFARS Army Federal Acquisition Regulation Supplement

AR Army Regulation

CCE Contracting Center of Excellence

CFR Code of Federal Regulations

CMR Contract Manpower Reporting

CONUS Continental United States (excludes Alaska and Hawaii)

COTS Commercial-Off-the-Shelf

DA Department of the Army

DD250 Department of Defense Form 250 (Receiving Report)

DD254 Department of Defense Contract Security Requirement List

DFARS Defense Federal Acquisition Regulation Supplement

DMDC Defense Manpower Data Center

DOD Department of Defense

FAR Federal Acquisition Regulation

HIPAA Health Insurance Portability and Accountability Act of 1996

KO Contracting Officer

NCR National Capital Region

OCI Organizational Conflict of Interest

OCONUS Outside Continental United States (includes Alaska and Hawaii)

ODC Other Direct Costs

OHN Occupational Health Nurse

OHP Occupational Health Physician

OHPM USACE Occupational Health Program Manager

PIPO Phase In/Phase Out

PLS Pure Live Seed

POC Point of Contact

PRS Performance Requirements Summary

PWS Performance Work Statement

QA Quality Assurance

QAP Quality Assurance Program

QASP Quality Assurance Surveillance Plan

QC Quality Control

QCP Quality Control Program

TE Technical Exhibit

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES: The Government will furnish the following information and equipment to the Contractor for use in the performance of this contract:

3.1. Services: None.

3.2 Facilities: None.

3.3 Utilities: Potable water and shore power is available on request. Pressure washer machine and ice blaster machine are available for use at the government site.

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1. General: Except as described in Part 3 of these specifications, the contractor shall furnish all labor, facilities, vehicles, equipment, materials, supplies, and services to accomplish all work in this contract. The contractor shall repair or replace at own expense any Government property which has been damaged or destroyed as a consequence of contractor (and subcontractors) performance of work under this contract.

PART 5

SPECIFIC TASKS

5. SPECIFIC TASKS:

5.1 CLIN 0001 (Base Item): Inspection, Cleaning, and Operate Adult Salmon Exclusion Structure

Check the underwater metal structure for damages. Open and close the gate as needed for fishing season. Remove debris blocking the structure as needed. Take photographs and videos for documentation. Submit a dive inspection report.

5.2 CLIN 0002 Option Item: Additional dive services around the Lake Washington Ship Canal.

The government may need additional inspection of the salt water drain system, pump plant discharge valve at the end of large lock, fish ladder structure, miter gates, work gates and spillway gate seals. Take photographs and videos for documentation.

Submit a dive inspection report. Minor in water maintenance and repair construction activities such as clean, mechanical repairs, removing and retrieving items and underwater rigging. Ice blaster and pressure washer machines are used to remove barnacles in water.

5.3 Stand Alone Documentation Package before each dive.

For each dive operation, contractor shall submit a document package containing the following three sections for government approval. Dive operation can commence after government approval and coordination.

1. Dive Operations Plan:

This document verifies that the contractor has a clear understanding of the dive mission to be undertaken and the method / procedures and equipment necessary to execute taskings safely, efficiently, and according to appropriate regulations. Plan shall include names, brief experience or biography of each person on the dive team, equipment list, task sequence, and time schedule.

2. Activity Hazard Analysis (AHA):

This document represents the contractor best effort to anticipate and mitigate or prevent injury to personnel, damage to equipment, structures and / or facilities.

3. Emergency Management Plan (EMP) or Site Specific Safety Plan (SSSP):

This plan details site-specific procedures and contact numbers in the event of an emergency or accident including the transport and treatment of a victim(s). SSSP can be the same for each dive operation if it’s in the same area.

The dive shall conform to the requirements of the U.S. Army Corps of Engineers Safety Manual EM-385-1-1, ER 385-1-86, the US Navy Dive Manual, as well as any applicable MOA’s and other state or federal regulations that may apply. Copies of all operational dive logs shall be furnished to the Dive Safety Inspector upon completion of the mission.

5.4 After Dive Inspection Report:

Each dive inspection report will include details of the actual dive. The end inspection report will include photographs with sufficient resolution. Annotate photographs as needed. Videos should be digital files with at least 1080p resolution, 24 frames to 30 frames per second. Include map or sketch of the area inspected. Weather and water temperature of the dive.

Include a written narrative of the dive and note extraordinary findings in detail. The report should be in industry standard

PDF file format. Photographs and video files can be submitted through agreed upon network or physical media.

Initial findings shall be reported to the government on site POC before the divers leave the site. Submit report within 40 calendar days after the dive has completed. Contractor shall retain the files for at least one year after the report was submitted to the government.

5.5 DIVE TEAM

The Dive Team shall consist of a minimum four-person crew. The work crew shall comprise of a dive supervisor / communications operator, diver, stand-by diver and dive tender. All dive team members shall have on file with the USACE

Seattle district current work documentation (dive logs, etc) and certifications showing that they are qualified to perform their dive team responsibilities and / or underwater work. For dives that require a recompression chamber, a certified chamber operator and inside chamber tender shall be specifically identified. Neither the operator of the chamber nor inside chamber tender shall be one of the in-water divers or stand-by divers.

In-water diver(s) and stand-by diver(s) shall not have been exposed to hyperbaric conditions within 12 hours of the first and all subsequent planned dives. Each dive team member shall have documented training and experience consistent with the performance requirements of this scope of work. As a minimum, each team member shall have at least 1 year of military and

/ or commercial experience in the applicable position; divers shall have completed at least four (4) working dives with similar decompression techniques as in the mission, using the particular diving techniques and equipment to be used under the mission. Divers shall demonstrate that at least one (1) of the four (4) qualification dives was performed in the last 12 months prior to mission.

5.6 Diving and Decompression Schedule and Method

All dives will be in accordance with the US Navy Diving Manual Air Decompression Table, latest revision.

Prior to their initial dive, each diver and standby diver will have a sufficient surface interval that will not be considered a

“repetitive dive”. After the initial dive repetitive dives may be performed if needed.

It is anticipated that only one diver will be deployed in the water at a time. If more than one diver is required, that diver may serve as a working in-water stand-by and / or working tender with both divers being tended according to regulations.

No diver will be exposed to more than four (4) hours in-water dive time per day. Any dives requiring decompression will be conducted in accordance with the U.S. Navy Standard Air Decompression Tables, latest revision. No dives will exceed the

‘O’ repetitive group designation. Although all operational depths are tide-dependent, no dive is expected to exceed a maximum working depth of 60 feet.

Planned Rotation of Divers and Dive-Team Members:

The diver rotation will be at the discretion of the Dive Supervisor according to individual wellness of divers and their ability to dive. No diving will be performed 24 hours prior to flying. Whenever divers are not acting as a diver or standby diver, they will be working on deck as a tender or alternate dive supervisor. The Dive Supervisor rotation will be at the discretion of the

Dive Team Lead. Dive team duties and rotation will be assigned each day during pre-dive safety / work meeting.

Site Safety and Health Officer: As per EM 385-1-1, the dive team shall employ a competent person at each project to function as the Site Safety and Health Officer (SSHO). The SSHO will manage the dive team’s Accident Prevention Plan

(APP). This may be a collateral duty responsibility unless specified differently in the contract. The person(s), as a minimum, must have completed the 30-hour OSHA Construction safety class or an equivalent course applicable to the work to be performed and given by qualified instructors. Such training shall have been within the last three (3) years. An SSHO shall be on-duty at all times when work is being performed and shall be responsible for enforcing and implementing the Contractor’s

Safety and Health Program in accordance with the accepted APP. A training certificate shall be on file in the Dive Safety

Office.

5.7 DIVE TEAM UNIT FURNISHED EQUIPMENT

The Dive Team shall supply:

A) Standard Surface-Supplied Air (SSA) or SCUBA with 2-way voice communication, approved air compressors and / or air cylinders shall be used for primary and backup SSA systems, at least two complete sets of 150 ft. umbilical’s shall be required to support the diver (s) and one standby diver.

NOTE: Use of tethered SCUBA IS APPROVED for the dive mission if needed.

B) USACE required diving equipment per EM 385-1-1, Section 30 and ER 385-1-93.

C) Unless waived in advance of the scheduled starting dive date(s) by the government, divers working in water less than 46-degree-F temperature for bottom times exceeding 45 minutes of accumulated bottom time or less than 36 degrees-F for bottom times exceeding 20 minutes of accumulated bottom time shall utilize hot water diving systems. Unless waived in advance of the scheduled starting dive date(s) by the government, variable-volume dry suits with appropriate thermal protection shall be utilized by divers working in waters 60 degrees or less.

D) An approved and certified dual-lock, multi-place recompression chamber (EM 385-1-1, Section 30.C) shall be available or readily accessible (available) if off site. This chamber must be certified and all pertinent documentation available on site. In accordance to industry practices the chamber will be pressurized to approximately 120 fsw and be fully ready to accept and treat an injured diver. The chamber shall be located such that the diver can be put to treatment depth within 5 minutes of surfacing. The designated Chamber operator must possess current certifications and / or training documentation. The operator of the chamber shall not be one of the divers or standby divers.

5.8 Communications

For Dive Operations: A hard-wired system will provide communication between the diver and the dive control station. In addition, divers will utilize line-pull signals should the primary voice communications fail. If primary communications fail, the diver will be directed via line pull signals to the surface or to the depth of any decompression obligation.

For Emergencies: The Dive Supervisor will have US-based cellular phones and / or VHF radios available for communication.

The Dive Team will be in constant available communications with LWSC personnel for calls to local 911/Emergency

Management Services (EMS) personnel. Local cellular phone network service will be the secondary means of communication for 911.

5.9 PRE / POST-DIVE PROCEEDURES: A pre / post-dive conference shall be conducted before and after all diving daily operations in the vicinity of the dive site at which all personnel are required to attend.

Pre-Dive Procedures: A daily pre-dive safety / work meeting will be conducted immediately prior commencing dive operations for the day. All personnel directly involved with the diving operation is required to attend. Topics will include team assignments, tasks to be performed, tools required, diving and topside safety, decompression and emergency procedures.

Post-Dive Procedures: Diver(s) shall remain stationary under observation of the dive supervisor for 10 minutes upon conclusion of dive. On being cleared, diver(s) will dress out and report to Dive Supervisor to sign dive logs and for further observation. All divers shall report any abnormal physical conditions to the dive supervisor or other dive team members as well as remain within reasonable travel distance to a recompression chamber for at least two hours after completing a dive. In addition, any other personnel who may notice another diver who may be displaying signs and symptoms of decompression sickness shall report their observations to the Dive Supervisor immediately.

5.10 Boat Restriction Zone (BRZ): Yes. All boat traffic within 50 yards of all dive sites will be suspended during dive operations. Setup and coordinate boat restriction zone(s) as required per regulations.

PART 6

APPLICABLE PUBLICATIONS

6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS).

6.1. EM 385-1-1 (2014), USACE Safety and Health Requirements Manual

6.2. 29 CFR 1910, Occupational Safety and Health Administration.

6.3. US Navy Dive Manual

PART 7

TECHNICAL EXHIBIT LISTING

7. Technical Exhibit List:

7.1 Technical Exhibit 1 – Quality Assurance and Performance Requirement Summary

7.2 Technical Exhibit 2 – Lake Washington Ship Canal design characteristics

7.3 Reference Images

TECHNICAL EXHIBIT 1

Quality Assurance and Performance Requirement Summary

1.1 General: The Government intends to monitor the contractor’s performance using quality assurance procedures established for the contract, and described in the Quality Assurance Surveillance Plan (QASP). The Government reserves the right to utilize inspection methods it deems necessary to assure contractor compliance with all terms and conditions of the contract.

1.2 Quality Standards: The contractor shall meet industry quality assurance standards, and comply with all established regulations. The contractor shall also perform all duties independently, with guidance provided and consultation conducted with the COR on major problems.

Performance Requirements Summary

2.1 General: The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

(The Service required— usually a shall statement) Standard

Performance Threshold

(This is the maximum error rate. It could possibly be “Zero deviation from standard”)

Method of

Surveillance

Task 1, Dive Operation without injury or damage to government property

a. Perform to dive plan without injury or additional damage to government property

a. 0%

a. Direct

Observation

Task 2, Dive Inspection

Report submitted within 40 calendar days of the dive

a. Contractor may submit the report up to 40 calendars after the dive has concluded

a. 0%

a. Direct

Observation

Task 3. Verbally report dive operation status at the end of each day’s dive activity.

a. Before leaving dive site, verbally communicate findings to the on site government POC. Especially near miss or injuries.

a. 0% a. Direct observation or phone conversation.

7.2 Technical Exhibit 2 – Lake Washington Ship Canal design characteristics

TAILWATER

Highest Tide (27 January 1983).............................................................................12.14 feet

Mean Higher High Water.........................................................................................9.02 feet

Mean High Water.....................................................................................................8.15 feet

Mean Low Water .....................................................................................................0.49 feet

Mean Lower Low Water........................................................................................ -2.34 feet

Lowest Tide (4 January 1916) ............................................................................... -7.38 feet

SPILLWAY DAM

Type ........................................................................ Concrete, ogee crest, with tainter gates

Crest Elevation.............................................................................. 10.5 feet (13.75 ft. COE)

Top of Gate Elevation (Closed) .................................................. 19.04 feet (22.29 ft. COE)

Number of Gates

Width of Each Gate.....................................................................................................32 fee t

Height of Each Gate.................................................................................................8.54 feet

Spillway Bridge Elevation ............................................................... 22.75 feet (26 ft. COE)

Spillway Hoist Deck Elevation........................................................ 30.75 feet (34 ft. COE)

LARGE LOCK

Type ........................................................................................................................Concrete

Length of Chamber - Overall....................................................................................825 feet

Length of East Chamber - Overall ............................................................................450 feet

Length of West Chamber - Overall...........................................................................375 feet

Width........................................................................................................................ ...80 feet

Elevation of Operating Deck ........................................................... 22.75 feet (26 ft. COE)

Elevation of Upper Miter Sill ........................................................-19.25 feet (-16 ft. COE)

Elevation of Lower Miter Sill........................................................-32.25 feet (-29 ft. COE)

Top of Saltwater Barrier - Lowered....................................................................... -13.5 feet

Top of Saltwater Barrier - Raised .................................................................................4 feet

Number of Gates ...........................................................................................................5 sets

Type of Gates................................................................................... Double sheathed, miter

Upper Guard Gate (Gate No. 1)................................................................42.54 x 46.33 feet

Upper Operating Gate (Gate No. 2)..........................................................42.54 x 46.33 feet

Intermediate Operating Gate (Gate No.3).................................................55.54 x 46.33 feet

Lower Operating Gate (Gate No. 4) .........................................................55.54 x 46.33 feet

Lower Guard Gate (Gate No. 5) ...............................................................45.54 x 46.33 feet

Elevation of Top of Gates............................................................. 19.95 feet (23.2 ft. COE)

Culverts......................................................................................................2 @ 14 x 8.5 feet

Laterals...............................................................................44 @ 2 x 4 feet, 8 @ 6 x 2 feet

Number of Valves

Type of Valves....................................................................................................Stoney gate

Size of Opening..................................................................................................14 x 8.5 fee t

SMALL LOCK

Type ........................................................................................................................Concrete

Length of Chamber-Overall......................................................................................150 feet

Width...........................................................................................................................30 feet

Elevation of Upper Miter Sill ...................................................................... 0.75 ft (4 COE)

Elevation of Lower Miter Sill................................................................-19.25 ft (-16 COE)

Number of Gates ...........................................................................................................4 sets

Type of Gates.....................................................................................Single sheathed, miter

Top of Gates.............................................................................................................23.2 feet

Upper Guard Gate .....................................................................................22.78 x 18.17 feet

Upper Operating Gate ...............................................................................22.78 x 18.17 feet

Lower Operating Gate...............................................................................42.78 x 18.17 feet

Lower Guard Gate.....................................................................................32.78 x 18.17 feet

Culverts......................................................................................................2 @ 6 x 4.25 feet

Laterals..................................................................................12 @ 2 x 3 feet, 2 @ 5 x 2 feet

Number of Valves

Type of Valves.....................................................................................................Cylindrical

Sizing of Opening, Diameter .................................................................................... 5.6 feet

FISH LADDER

Width.............................................................................................................................8 feet

General Slope.................................................................................1 vertical to 8 horizontal

Weir Height...................................................................................................................8 feet

Distance Between Weirs ...............................................................................................8 feet

Number of Fixed Weirs

Number of Adjustable Weirs

Ladder Flow.....................................................................................................18.6 to 23 cfs

Fishway Entrance Downstream Opening ...................................................................Gate controlled

Width................................................................................ 3.8 feet maximum to 0.94 feet minimum

Height....................................................................................................................... ...22 feet

Side Opening.................................................................................................... Uncontrolled

Width........................................................................................................................ ..1.0 feet

Height..........................................................................................................................22 feet

Fishway Exit ......................................................................................................5.5 x 10 feet

Attraction Water...................................................................Discharge from saltwater drain

Size of Conduit ................................................................ 6 feet in diameter x 210 feet long

Flow Control ........................................................................ 6-foot diameter butterfly valve

Number of Diffusers

Design Diffuser Flow.................................................................................................160 cfs

Minimum Diffuser Flow..............................................................................................85 cfs

SALTWATER DRAIN

Length .......................................................................................................700 feet (approx.)

Size (Dimensions vary)...................................................30 square feet cross sectional area

Intake................Concrete trashrack structure at bottom elevation -33.25 feet (-30 ft. COE)

Flow Control ......................................................5x7 sluice gate downstream end at bottom elevation of 6.75 feet (10 ft. COE)

Maximum Discharge..................................................................................................225 cfs

7.3 Reference Images

Image 1.

Image 2.

Image 3.

SF30_Amend 0002
RFQ Q&A_Amendment 0002
A.02.11 - FY21 LWSC Dive Contract Dec 14_2020_Amend 0002

File details come from the government source that posted it. Updated .