W912DW19Q0037R0005_Q&A.pdf

PDF 558 KB Posted

Attached to
Barge Drydock Maintenance Services Federal contract opportunity
Solicitation number
W912DW19Q0037
Issued by
Department of the Army Corps of Engineers Engineering District Seattle

About this file

W912DW19Q0037R0005 Q&A

View the file

Other files for this federal contract opportunity

Other files attached to Barge Drydock Maintenance Services, newest first.
File Type Posted
W912DW19Q0037R0003_Barge.pdf PDF
W912DW19Q0037R0002.pdf PDF
Corps_Safety_Manual_EM_385-1-1.pdf PDF
W912DW19Q0037R0001_Q&A.pdf PDF
Attachment-Reference_Drawing_&_Pics.pdf PDF
W912DW19Q0037_Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W68MD983092639

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Please see continuation sheet:

1. CONTRACT ID CODE PAGE OF PAGES

J 1 18

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-May-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW19Q0037

X 9B. DATED (SEE ITEM 11)

28-Mar-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-May-2019

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DW19Q0037

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS 2

The solicitation closes 14 May 2019 at 2:00 PM PST. The purpose of this amendment is to accomplish the following:

- Update the Period of Performance (POP) to reflect the change in scope. The POP is 22 May 2019- 17 July 2019.

- Answer the following vendor questions:

1. How many tanks/voids are in this barge?

Answer: There are 3 main bulkheads inside so estimated at 4 voids.

2. Is the delivery date of July 17th still the requirement?

Answer: Yes.

3. Is it the government’s intent to have the timber fenders removed for sandblasting and then reinstalled after application of coatings, or can the fender timbers be left in place?

Answer: Timbers may be left in place.

4. The specifications specify sandblasting and painting of the deck but do not include high pressure water washing to remove dirt and salts before blasting, could USACE add the requirement to pressure wash the specifications?

Answer: Proper preparation is required prior to painting.

5. In Part 2, the work week is defined as Monday through Thursday. Please clarify? Is this just the days that the ACE are available?

Answer: USACE crew is available those days. Contractor work on Fridays is acceptable.

6. Pricing item 0001 - states to provide cost for all items in the PWS, items 1-8. I would just like to clarify that item 7 (Zincs) will not be included in the 0001 pricing and will now be standalone pricing in item 0002.

Answer: Yes replacement of the zincs are to be priced separately in item 0002 because there is not an accurate count of the zincs and they are all condition unknown.

7. The amended specifications do not include replacement of damaged hull side ladder rungs, is ladder rung replacement to be omitted from the requirements?

Answer: Ladder rungs to be omitted.

8. Is it the intent of the specifications to re-float and reposition the barge on drydock blocking to allow surface preparation and coating of surfaces otherwise obscured by drydock blocks?

Answer: Yes.

9. Does the paint contain lead?

Answer: The paint has not been tested. All work must be done in accordance with USACE Safety Manual EM 385- 1-1.

10. Does the customer want the 2 coat system from amendment 3 over the entire deck, or was it missed to separate the work deck area from the perimeter?

Answer: We are no longer putting on a wear deck, so need to revert to painting the entire deck in 2 part epoxy with non-skid coating.

11. The requirement for a SAMS marine surveyor is proving to be a difficult requirement. I was referred to NAMS, National Association of Marine Surveyors as a more appropriate surveyor for this type of work. Is using NAMS acceptable in lieu of the SAMS?

Answer: NAMS, SAMS or equivalent marine surveyor would be acceptable.

See the following changes in red.

SECTION SF 1449 - CONTINUATION SHEET

SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

Period of Performance: 22 April 2019 – 17 July 2019Provide all labor, materials, and equipment necessary to provide Dry-dock Maintenance Services for NWS Barge 1-12-2 for Seattle District, U.S. Army Corps of Engineers (USACE) Navigation projects in accordance with the attached Performance Work Statement (PWS).Applicable Service Wage Determination will be incorporated into contract after place of performance is determined.

To:

Period of Performance: 22 May 2019 – 17 July 2019Provide all labor, materials, and equipment necessary to provide Dry-dock Maintenance Services for NWS Barge 1-12-2 for Seattle District, U.S. Army Corps of Engineers (USACE) Navigation projects in accordance with the attached Performance Work Statement (PWS).Applicable Service Wage Determination will be incorporated into contract after place of performance is determined.

DELIVERIES AND PERFORMANCE

The following Delivery Schedule item for CLIN 0001 has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

POP 22-APR-2019 TO

17-JUL-2019

N/A US ARMY CORPS OF ENGINEERS

SEATTLE DISTRICT

PO BOX 3755

SEATTLE WA 98124-3755

FOB: Destination

960506

To:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

POP 22-MAY-2019 TO

17-JUL-2019

N/A US ARMY CORPS OF ENGINEERS

SEATTLE DISTRICT

PO BOX 3755

SEATTLE WA 98124-3755

The following Delivery Schedule for CLIN 0002 has been added:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

POP 22-MAY-2019 TO

17-JUL-2019

N/A US ARMY CORPS OF ENGINEERS

MAIL ROOM

SEATTLE DISTRICT

PO BOX 3755

SEATTLE WA 98124-3755

206-764-3799

The following have been modified:

PERFORMANCE WORK STATEMENT

PERFORMANCE WORK STATEMENT (PWS)

Barge NWS 1-12-2 Dry-Dock Maintenance Services Table of Contents

1 General ...................................................................................................................................................................... x

1.1 Description of Services/Introduction ................................................................................................................... x

1.2 Scope ................................................................................................................................................................... x

1.3 Period of Performance ......................................................................................................................................... x

1.4 General Information............................................................................................................................................. x

1.4.1 Quality Control ....................................................................................................................................... x

1.4.2 Quality Assurance .................................................................................................................................. x

1.4.3 Recognized Holidays .............................................................................................................................. x

1.4.4 Hours of Operation ................................................................................................................................. x

1.4.5 Place of Performance .............................................................................................................................. x

1.4.6 Type of Contract ..................................................................................................................................... x

1.4.7 Security Requirements ........................................................................................................................... x 1..4.8 Physical Security ................................................................................................................................... x

1.4.9 Key Control ............................................................................................................................................ x

1.4.10 Post Award Conference/Periodic Progress Meeting ............................................................................. x

1.4.11 Contracting Officer Representative (COR) .......................................................................................... x

1.4.12 Key Personnel ...................................................................................................................................... x

1.4.13 Identification of Contractor Employee ................................................................................................. x

1.4.14 Contract Travel ..................................................................................................................................... x

1.6.15 Other Direct Costs ................................................................................................................................ x

1.6.16 Data Rights ........................................................................................................................................... x

1.6.17 Organizational Conflict of Interest ....................................................................................................... x

1.6.18 Phase in/ Phase out Period .................................................................................................................... x

2 Definitions and Acronyms ......................................................................................................................................... x

2.1 Definitions ........................................................................................................................................................... x

2.2 Acronyms............................................................................................................................................................. x

3 Government Furnished Items and Services ................................................................................................................ x

3.1 Services ................................................................................................................................................................ x

3.2 Facilities .............................................................................................................................................................. x

3.3 Utilities ................................................................................................................................................................ x

3.4 Equipment ............................................................................................................................................................ x

3.5 Materials .............................................................................................................................................................. x

4 Contractor Furnished Items and Responsibilities ....................................................................................................... x

4.1 General ................................................................................................................................................................ x

4.2 Secret Facility Clearance ..................................................................................................................................... x

4.3 Materials .............................................................................................................................................................. x

4.4 Equipment ............................................................................................................................................................ x

5 Specific Tasks ............................................................................................................................................................. x

5.1 Basic Services ...................................................................................................................................................... x

5.2 Contractor Management Reporting ..................................................................................................................... x

6 Applicable Publications .............................................................................................................................................. x

6.1 List ....................................................................................................................................................................... x

7 Attachment/Technical Exhibit List ............................................................................................................................. x

7.1 Attachment 1/Technical Exhibit 1- Performance Requirements Summary ......................................................... x

PERFORMANCE WORK STATEMENT (PWS)

Barge NWS 1-12-2 Dry-Dock Maintenance Services

Part 1

General Information

1. GENERAL: This is a non-personnel services contract to provide USACE, Seattle District, Navigation Section, with Barge Dry-dock Maintenance Services, at a facility within the Puget Sound area. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services/Introduction: The contractor shall provide all management, personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and applicable licenses and permits necessary for Barge NWS 1-12-2 (110’ x 30’ x 9’ collected flat debris barge) Dry-dock Maintenance Services, as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract. Performance will be at a Contractor provided facility in the Puget Sound area.

A site visit will be conducted on 4 APR 2019 at 0800 AM Pacific Standard Time. The site visit will be conducted at:

Ballard (Hiram M. Chittenden) Locks 3015 NW 54th St, Seattle, WA 98107 Contact Tom Gay (425)-870-5275

1.2 Scope and Services: The contractor shall provide all necessary services required to perform dry-dock maintenance on Barge NWS 1-12-2 including:

1. Verify and renew American Bureau of Shipping (ABS) Certifications. Conduct vessel survey using Society of Accredited Marine Surveyors (SAMS), National Association of Marine Surveyors (NAMS), or equivalent accredited marine surveyor to assess value and condition of barge to determine need for future maintenance or assist in predicting useful life.

2. Clean and perform full inspection of hull, all enclosed spaces, bottom, topside and deck. Verify that closure devices-doors, hatches, etc.-can be closed easily and completely. Check for warping, that gaskets are in good shape and that a complete seal is maintained.

3. Sandblast, inspect and paint hull and bottom. Paint shall be marine grade 2 part epoxy and a minimum of 2 coats must be applied. Retain current paint color scheme and lettering.

4. Install 4, 36” kevel chocks 15’ from bitts, one on each of the 4 corners of vessel. They should be in line and centered with the bitts and 15’ toward lateral amidships from the center of the bitts. See drawing.

5. Sandblast, Inspect and Paint topside and deck in marine grade 2 part epoxy with non-skid coating.

Retain current paint color scheme and lettering.

6. Install a 3/8” 1”plate wear deck 4’ inboard form the port and starboard side and 9’ inboard from the ends covering the entire middle of deck. The wear deck is not to be painted. Paint the area around the edge of the barge deck red with heavy non-skid. The deck shall be welded to existing deck all around.

Modifications or partial removal of current deck is acceptable if necessary to affix welds properly.

7. Replace all hull zincs. Please price separately in Line Item 0002.

8. Transport of barge from Ballard Locks to Contractor facility and from Contractor facility to mooring at

Ballard Locks upon work completion.

1.3 Period of Performance: The period of performance shall be 22 April 22 May 2019- 17 July 2019.

1.4 General Information

1.4.1 Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system.

1.4.2 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.4.3 Recognized Holidays: Contractor will not perform on the following holidays:

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day

1.4.4 Hours of Operation: The contractor is responsible for conducting business, between the hours of 0900 to 1530 Monday thru Friday except Federal holidays. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.4.5 Place of Performance: The work to be performed under this contract will be performed at a contractor facility within the Puget Sound area. Contractor shall be responsible for transport of barge.

1.4.6 Type of Contract: The government will award a firm fixed price services contract.

1.4.7 Security Requirements: The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify ) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

1.4.8 Physical Security: Not Applicable

1.4.9 Key Control: Not Applicable

1.4.10 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced.

Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.4.12 Key Personnel: The following personnel are considered key personnel by the government. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract.

1.4.13 Identification of Contractor Employees: Not Applicable

1.4.14 Contractor Travel: Not Applicable

1.4.15 Other Direct Costs: Not Applicable

1.4.16 Data Rights: Not Applicable

1.4.17 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.18 PHASE IN /PHASE OUT PERIOD: Not Applicable

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. DEFINITIONS:

2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.12. WORK WEEK. Monday through Thursday, unless specified otherwise.

2.2. ACRONYMS:

ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer LWSC Lake Washington Ship Canal OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1. Services: Not Applicable.

3.2 Facilities: Not Applicable.

3.3 Utilities: Not Applicable

3.4 Equipment: Barge NWS 1-12-2.

3.5 Materials: None.

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1 General: The Contractor shall furnish all supplies, equipment, facilities, transportation, and services required to perform work under this contract that are not listed under Section 3 of this PWS.

4.2 Secret Facility Clearance: Not Applicable

4.3. Materials: The Contractor shall provide a written one year warranty on all work completed. Contractor shall provide SAMS, NAMS, or equivalent accredited marine survey report. updated ABS certification.

4.4. Equipment: The Contractor shall provide needed equipment to meet the requirements under this PWS.

PART 5

SPECIFIC TASKS

5. Specific Tasks:

5.1. Basic Services. The contractor shall provide all management, personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and applicable licenses and permits necessary to perform Barge Dry-dock Maintenance Services.

5.1.1 Verify ABS Certifications

Verify ABS Certification and issue renewal. Conduct Accredited Marine Survey- Conduct SAMS, NAMS, or equivalent accredited marine survey and provide full report to government.

5.1.2 Full Cleaning and Inspection of Entire Barge

Pressure wash the underwater hull to deck cap rail and fittings with fresh water at a minimum of 3,000 PSIG nozzle pressure to remove dirt, slime, marine growth, fouling and other foreign substances. Power tool clean inaccessible areas where washing equipment cannot reach and areas showing excessive corrosion. Accomplish a visual inspection of the entire barge. Verify that closure devices-doors, hatches, ECT. can be closed easily and completely.

Check for warping, gasket integrity, and that a complete seal is maintained. Document all discrepancies and deliver report to Government Representative prior to hull repainting.

5.1.3 Sandblast, Inspect and Paint Hull and Bottom, Replace Zincs Sandblast, inspect and paint entire hull and bottom. Retain current paint color scheme and lettering. Replace all hull zincs. Document all discrepancies and deliver report to Government Representative prior to hull repainting. Paint shall be marine grade 2 part epoxy and a minimum of 2 coats must be applied.

5.1.4 Installation of Cleats

Install four (4) 36” kevel chocks 15 feet from bitts, one on each of the 4 corners of vessel. They should be in line and centered with the bitts and 15 feet toward amidships laterally from the center of the bitts. See drawing.

Document all discrepancies and deliver report to Government Representative prior to installation.

5.1.5 Sandblast, Inspect and Paint Topside and Deck

Sandblast, inspect and paint topside and deck. Retain current paint color scheme and lettering. Document all discrepancies and deliver report to Government Representative prior to repainting. Paint shall be marine grade 2 part epoxy with non skid and a minimum of 2 coats must be applied.

5.1.6 Install Wear Deck

Install a 3/8” plate wear deck 4 feet inboard form the port and starboard side and 9 feet inboard from the ends Covering the entire middle of deck. The wear deck is not to be painted. Paint the area around the edge of the barge deck red with heavy non-skid. Paint shall be marine grade 2 part epoxy and a minimum of 2 coats must be applied.

5.1.7 Transportation of Barge

Transport barge from Ballard Locks to contractor’s facility and from contractor’s facility to mooring at Ballard Locks upon work completion.

PART 6

APPLICABLE PUBLICATIONS

6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS):

6.1. The Contractor must abide by the requirements set forth in the Corps Safety Manual EM 385-1-1, with changes.

Manual can be found at the following link:

https://www.nws.usace.army.mil/Portals/27/docs/construction/Preconstruction%20packet/App% 20A%20EM%20385-1-1%2015SEP08.pdf

PART 7

ATTACHMENT/TECHNICAL EXHIBIT LISTING

7. Attachment/Technical Exhibit List:

7.1. Attachment 1/Technical Exhibit 1 – Performance Requirements Summary

7.2. Attachment 2/Technical Exhibit 2 – Deliverables Schedule

TECHNICAL EXHIBIT 1

Performance Requirements Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective (The Service required—usually a shall statement)

Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)

Method of Surveillance

PRS # 1.

The contractor shall provide all personnel, equipment, supplies, transportation, tools, fuels, materials, supervision, licenses and permits necessary to provide dry-dock maintenance services under this PWS.

Safely perform assigned missions IAW EM 385-1-1, with changes

Zero deviation from standard.

Random inspection by Government representative and debris vessel M/V

PUGET

Master.

TECHNICAL EXHIBIT 2

Deliverables Schedule

Deliverable Frequency # of Copies Medium/Format Submit to ABS certification 1 2 Official Paper

Certification Bradford Schulz

Bradford.L.Schultz@usace.army.mil SAMS, NAMS, or equivalent accredited Marine Survey Inspection

Report

1 2 1 Paper 1 Electronic

(End of Summary of Changes)