Text version
W68MD963150131
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Albeni Falls Pow erhouse Station Service Sw itchgear
Please see Continuation Page for details.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Mar-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW-17-R-0011
X 9B. DATED (SEE ITEM 11)
24-Feb-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Mar-2017
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CECT-NWS
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DW-17-R-0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The purpose of Amendment one (0001) is as follows:
Incorporate below items as indicated.
1. Specifications/Drawings – revised/new specifications and drawings are as follows:
01 11 10.00 26, Summary of Work 01 22 00.00 10, Price and Payment Procedures 00 73 00-A, Index of Drawings G-002, Index of Contract Drawings ED803, Conduit and Cable Schedule – Sheet 3 -- Removal ED804, Conduit and Cable Schedule – Sheet 4 -- Removal E-210, SC4 Panel Elevation View – Partial Layout -- Install E-802, Conduit and Cable Schedule – Sheet 2 -- Install
The attached revised sections are to be replaced in their entirety. Specifications changes are generally identified, for convenience, either by strikeout for deletions, and double underlining of text for additions or a single dark line in the margin. All portions of the revised sections shall apply whether or not changes have been indicated.
2. Site Visit – Attendance Roster Site visit attendance roster (8 March 2017) is provided for informational purposes only.
3. Proposal Submittal Proposal submittal date/time remains the same: 30 March 2017 at 12:30 p.m. LOCAL TIME.
NOTICE TO OFFERORS: Offerors must acknowledge receipt of this amendment by number and date on offer.
Encl:
01 11 10.00 26 (revised) 01 22 00.00 10 (revised) 00 73 00-A (revised) G-002 (revised) ED803 (new) ED804 (new) E-210 (revised) E-802 (revised) Site Visit Attendance Roster (new)
(End of Summary of Changes)
Albeni Falls Powerhouse 13.8 kV and 480 V Switchgear Replacement 15020 Oldtown, ID
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 10.00 26
SUMMARY OF WORK
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
1.2 CHANGES IN SPECIFICATIONS AND DRAWINGS
1.3 DEFINITIONS
PART 2 - PRODUCTS - NOT USED
PART 3 - PRODUCTS - NOT USED
-- End of Section Table of Contents --
SECTION 01 11 10.00 26 Page 1
W912DW-17-R-0011 R0001
SECTION 01 11 10.00 26
SUMMARY OF WORK
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
This section covers the technical specifications to perform all work required to upgrade the Albeni Falls Powerhouse 15 kV and 480 V Station Service Switchgear Replacement. This section is a general summary of the required work and is not all-inclusive. The work described within these specifications includes, but not necessarily limited to the following:
a. Remove and dispose of three (3) 15 kV rated switchgear lineups including related feeders and control systems located on EL 2060.
b. Remove and dispose of one (1) double-ended 480 V switchgear, SQ1,located on EL 2042 consisting of two (2) 750 kVA 13.8 kV-480 V dry type transformers and seven (7) vertical breaker sections, including the control systems, incoming 15kV feeders.
c. Remove and dispose of abandoned rotating excitation equipment consisting of three (3) Amplidyne Sets, three (3) Rheostat Cubicles, and three (3) Amplidyne Cubicles , and abandoned rotating excitation equipment cables . Cut and plug abandoned conduits.
d. Furnish, install, and test three (3) new 15 kV switchgear lineups SJ1, SJ2, and SJ3 on EL 2060 complete with vacuum circuit breakers; XJ1, XJ2, XJ3, XJO1, and XJO2, new surge protective equipment, 15 kV bus duct modifications, new conduits and feeders to TO1 and TO2, controls, annunciation, and protection circuits.
e. Furnish, install, and test one (1) 480 V double ended substation (SQ1) consisting of two (2) main bus breakers, two (2) tie breakers, and eleven (11) feeder breakers on each bus, complete with relays, meters, and wiring on EL 2042.
g. Furnish, install, and test two (2) three-phase, 1000 kVA, Delta/Wye 13,800/480 V dry-type transformers, two (2) high-resistance grounding systems, and associated surge arresters and surge capacitors on EL 2042.
h. Furnish, install, and test one (1) local-remote control panel SQ1C for control of supply breakers, tie/isolation breakers, and all feeder breakers.
i. Furnish, install, and test three (3) new high-resistance grounding (HRG) units in SJ1, SJ2, and SJ3.
j. Furnish, install, and test one (1) new high-resistance grounding (HRG) unit for the exisisting Diesel generator system.
k. Modify and test four (4) sections of main control switchboard (SC) panels 1 through 4 located in the control room on EL 2060 to include
SECTION 01 11 10.00 26 Page 2 the removal and installation of new associated controls and indication for 15 kV circuit breaker, 480 V station service switchgear, and mimic bus modifications.
l. Furnish, install, and test new feeder cables to fifth floor offices from SQ1 and new manual transfer switch.
m. Furnish services of manufacturer's erecting engineer and system commissioning.
n. Furnish spare parts and accessories, training of Government Personnel, O & M Manuals, and as-built drawings.
p. Furnish concrete cutting and sawcutting for equipment foundations.
p. Perform work required to comply with site operations, environmental protection, and safety and health provisions.
1.2 CHANGES IN SPECIFICATIONS AND DRAWINGS
The Government reserves the right to revise or amend the specifications and/or drawings prior to the due date set for receipt of proposals.
Copies of such amendments will be furnished to all prospective offerors.
If the revisions and amendments require material changes in quantities or prices, or both, the due date set for receipt of proposals may be extended to enable offerors the opportunity to revise their proposals. The amendment will include an announcement of the new due date for receipt of proposals.
1.3 DEFINITIONS
a. Wherever in the specifications, or upon the drawings, the words "directed", "required", "ordered", "designated", "prescribed", or words of like import are used, it shall be understood that the "direction", "requirement", "order", "designation", or "prescription" of the Contracting Officer is intended, and similarly the words "approved", "acceptable", "satisfactory", or words of like import shall mean "approved by" or "acceptable to" or "satisfactory to" the Contracting Officer unless otherwise expressly stated.
b. Where "as shown", "as indicated", "as detailed", or words of like import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word "provided" as used herein shall be understood to mean "provided complete in place", that is, "furnished and installed". (FAR 52.236.21(b) and (c)).
c. Wherever in these specifications or upon the drawings, the words "Contracting Officer" (CO) or "Contracting Officer's Representative" (COR) are used, it shall be understood to also mean "Government" unless otherwise expressly stated.
d. Wherever in these specifications the word "weekend(s)" is used, it shall be understood to mean "Saturday, Sunday, and Federal Holidays", unless otherwise expressly stated.
e. Whenever in these specifications the word "Project" is used, it shall be understood to mean Albeni Falls Powerhouse.
SECTION 01 11 10.00 26 Page 3
PART 2 - PRODUCTS - NOT USED
PART 3 - PRODUCTS - NOT USED
-- End of Section --
SECTION 01 11 10.00 26 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
1.1.1 CLIN 0001 Mobilization and Demobilization
1.1.2 CLIN 0003 Remove and Dispose of Double-ended 480 V Switchgear
SQ1
1.1.3 CLIN 0004 Remove and Dispose of Abandoned Rotating Excitation
Equipment
1.1.4 CLIN 0005 Furnish, Install, and Test New 15 kV Switchgear
Lineup SJ1
1.1.5 CLIN 0006 Furnish, Install, and Test New 15 kV Switchgear
Lineup SJ2
1.1.6 CLIN 0007 Furnish, Install, and Test New 15 kV Switchgear
Lineup SJ3
1.1.7 CLIN 0008 Furnish, Install, and Test New Double-ended 480 V
Switchgear SQ1
1.1.8 CLIN 0010 Furnish, Install, and Test Local-Remote control panel SQ1C
1.1.9 CLIN 0011 Furnish, Install, and Test New High-Resistance
Grounding (HRG) Units in SJ1, SJ2, and SJ3
1.1.10 CLIN 0012 Modify and Test Main Control Switchboard (SC)
Panels 1 Through 4
1.1.11 CLIN 0013 Furnish, Install, and Test New feeder cables to fifth floor offices
1.1.12 CLIN 0014 Furnish System Commissioning Services
1.1.13 CLIN 0015 Furnish O&M Manuals
1.1.14 CLIN 0016 Furnish As-Constructed Drawings
1.1.15 CLIN 0017 Furnish Training of Government Personnel
1.1.16 CLIN 0018 Miscellaneous Concrete work and Saw Cutting
1.1.17 CLIN 0019 Furnish Spare Parts and Accessories
1.1.18 CLIN 0020 Furnish, Install, and Test One (1) New
High-Resistance Grounding (HRG) Unit for the Existing Diesel Generator System
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 CLIN 0002 Remove and Dispose of Existing 15 kV Switchgear
1.2.2 CLIN 0009 Furnish, Install, and Test New 13.8 kV/480 V, Dry-type Transformers TO1 and TO2
1.3 PROGRESS PAYMENT INVOICE
1.4 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS
1.4.1 Contractor POC
1.4.2 Responsibilities
1.4.3 Certification
1.5 PROPOSED PROJECT MODIFICATIONS
PART 2 PRODUCTS
SECTION 01 22 00.00 10 Page 1
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 22 00.00 10 Page 2
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the PRICING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 CLIN 0001 Mobilization and Demobilization
Payment for Mobilization and Demobilization will be paid for under CLIN No. 0001. Price and payment shall constitute full compensation for:
a. Site mobilization of all materials, equipment, and labor required to accomplish the work. Mobilization will be considered complete when the Contractor is ready to commence work.
b. Site demobilization will be considered complete when the Contractor has removed all construction equipment, cleaned the area, and restored the work area to "as-found" pre-contract conditions, unless otherwise approved.
c. Payment for Mobilization and Demobilization will be paid as a JOB at a rate of 60 percent for mobilization and 40 percent for demobilization.
1.1.2 CLIN 0003 Remove and Dispose of Double-ended 480 V Switchgear SQ1
Payment for Remove and Dispose of Double-ended 480 V Switchgear SQ1 will be paid under CLIN 0003 as a JOB. Price and payment will constitute full compensation to Remove and Dispose of Double-ended 480 V Switchgear SQ1, including existing transformers,cables, equipment and accessories not to be reused, to the first existing points of termination and retaining all existing 480V feeder cables.
1.1.3 CLIN 0004 Remove and Dispose of Abandoned Rotating Excitation Equipment
Payment for Remove and Dispose of Abandoned Rotating Excitation Equipment will be paid under CLIN 0004 as a JOB. Price and payment will constitute full compensation to Remove and Dispose of Abandoned Rotating Excitation Equipment including existing equipment pedestals and cables and to cut and plug abandoned conduits .
SECTION 01 22 00.00 10 Page 3
1.1.4 CLIN 0005 Furnish, Install, and Test New 15 kV Switchgear Lineup SJ1
Payment for Furnish, Install, and Test New 15 kV Switchgear Lineup SJ1, Complete with Breakers, Wiring, Relays, Meters, Controls, 15 kV Bus Duct Modifications, and new Conduits and Feeders to TO1 will be paid under CLIN 0005 as a JOB. Price and payment will constitute full compensation for the furnishing of all material, labor and equipment to fabricate and install the new SJ1 switchgear and control boards with feeder protection relays including maintenance mode, a remote racking device, metering, local controls and indication, infrared viewing windows, all associated control wiring from SJ1 to the first existing points of termination, modifications to the existing 15 kV metal-enclosed bus below SJ1 to connect to new 15 kV metalclad switchgear, and feeders to the 480 V substation transformer TO1 to make a fully functioning system.
1.1.5 CLIN 0006 Furnish, Install, and Test New 15 kV Switchgear Lineup SJ2
Payment for Furnish, Install, and Test New 15 kV Switchgear Lineup SJ2, Complete with Breakers, Wiring, Relays, Meters, Controls, 15 kV Bus Duct Modifications, and new Conduits and Feeders to TO2 will be paid under CLIN 0006 as a JOB. Price and payment will constitute full compensation for the furnishing of all material, labor and equipment to fabricate and install the new SJ2 switchgear and control boards with feeder protection relays including maintenance mode, a remote racking device, metering, local controls and indication, infrared viewing windows, all associated control wiring from SJ2 to the first existing points of termination, modifications to the existing 15 kV metal-enclosed bus below SJ2 to connect to new 15 kV metalclad switchgear, and feeders to the 480 V substation transformer TO2 to make a fully functioning system.
1.1.6 CLIN 0007 Furnish, Install, and Test New 15 kV Switchgear Lineup SJ3
Payment for Furnish, Install, and Test New 15 kV Switchgear Lineup SJ3, Complete with Breakers, Wiring, Relays, Meters, Controls, 15 kV Bus Duct Modifications will be paid under CLIN 0007 as a JOB. Price and payment will constitute full compensation for the furnishing of all material, labor and equipment to fabricate and install the new SJ3 switchgear and control boards with feeder protection relays including maintenance mode, a remote racking device, metering, local controls and indication, infrared viewing windows, all associated control wiring from SJ to the first existing points of termination, and any modifications to the existing 15 kV metal-enclosed bus below SJ3 to make a fully functioning system.
1.1.7 CLIN 0008 Furnish, Install, and Test New Double-ended 480 V Switchgear SQ1
Payment for Furnish, Install, and Test New Double-ended 480 V Switchgear SQO1 will be paid under CLIN 0008 as a JOB. Price and payment will constitute full compensation to furnish, install, and test new double-ended 480 V Switchgear SQ1.
1.1.8 CLIN 0010 Furnish, Install, and Test Local-Remote control panel SQ1C
Payment for Furnish, Install, and Test NLocal-Remote control panel SQ1C will be paid under CLIN 0010 as a JOB. Price and payment will constitute full compensation to furnish, install, and test new Local-Remote Control Panel for SQ1 Supply Breakers, Tie/Isolation Breakers, and All Feeder Breakers.
SECTION 01 22 00.00 10 Page 4
1.1.9 CLIN 0011 Furnish, Install, and Test New High-Resistance Grounding (HRG) Units in SJ1, SJ2, and SJ3
Payment for Furnish, Install, and Test New High-Resistance Grounding (HRG) Units in SJ1, SJ2, and SJ3 will be paid under CLIN 0011 as a JOB measured per HRG. Price and payment will constitute full compensation to furnish, install, and test new High-Resistance Grounding (HRG) Units in SJ1, SJ2, and SJ3.
1.1.10 CLIN 0012 Modify and Test Main Control Switchboard (SC) Panels 1 Through 4
Payment for Modify and Test Main Control Switchboard (SC) Panels 1 Through 4 will be paid under CLIN 0012 as a JOB. Price and payment will constitute full compensation to furnish, install, and test new Main Control Switchboard (SC) Panels 1 Through 4.
1.1.11 CLIN 0013 Furnish, Install, and Test New feeder cables to fifth floor offices
Payment for Furnish, Install, and Test New feeder cables to fifth floor offices will be paid under CLIN 0013 as a JOB. Price and payment will constitute full compensation to furnish, install, and test new feeders to fifth floor offices from SQ1 and new manual transfer switch.
1.1.12 CLIN 0014 Furnish System Commissioning Services
Payment for Furnish System Commissioning Services will be paid under CLIN 0014 as a JOB. Price and payment will constitute full compensation to System Commissioning Services.
1.1.13 CLIN 0015 Furnish O&M Manuals
Payment for Furnish O&M Manuals will be paid under CLIN 0015 as a JOB.
Price and payment will constitute full compensation to furnish Operations and Maintenance Manuals. No partial of full payments will be authorized until final documents are approved by the Contracting Officer.
1.1.14 CLIN 0016 Furnish As-Constructed Drawings
Payment for Furnish As-Constructed Drawings will be paid under CLIN 0016 as a JOB. Price and payment will constitute full compensation to furnish As-Constructed Drawings. No partial of full payments will be authorized until final documents are approved by the Contracting Officer.
1.1.15 CLIN 0017 Furnish Training of Government Personnel
Payment for Furnish Training of Government Personnel will be paid under CLIN 0017 as a JOB. Price and payment will constitute full compensation to furnish training of Government Personnel.
1.1.16 CLIN 0018 Miscellaneous Concrete work and Saw Cutting
Payment for Miscellaneous Concrete work and Saw Cutting will be made under CLIN 0018 as a JOB. Payment shall include the furnishing of all equipment and labor for installing the new equipment and removing the existing equipment which price and payment will be full compensation for the directed work. This work will include, but is not limited to, the repair of the concrete surfaces beneath the rotating excitation equipment.
SECTION 01 22 00.00 10 Page 5
1.1.17 CLIN 0019 Furnish Spare Parts and Accessories
Payment for Furnishing spare parts and accessories will be paid under CLIN 0019 as a JOB Payment shall include the furnishing of all spare parts and accessories, which price and payment will be full compensation for the directed work.
1.1.18 CLIN 0020 Furnish, Install, and Test One (1) New High-Resistance Grounding (HRG) Unit for the Existing Diesel Generator System
Payment for Furnish, Install, and Test One (1) New High-Resistance Grounding (HRG) Unit for the Existing Diesel Generator System will be paid under CLIN 0020 as a JOB measured per HRG. Price and payment will constitute full compensation to furnish, install, and test new High-Resistance Grounding (HRG) Unit for the Existing Diesel Generator System.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the PRICING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.2.1 CLIN 0002 Remove and Dispose of Existing 15 kV Switchgear
Payment for Remove and Dispose of Existing 15 kV Switchgear will be paid under CLIN 0002 on a unit price basis. Abatement of any present asbestos is to be included under CLIN 0002. Price and payment will constitute full compensation to remove and dispose of the 15 kV Switchgear to be measured by per switchgear: generator switchgear 1, generator switchgear 2, and generator switchgear 3 to the first existing points of termination including all cables, equipment and accessories not to be reused and to protect and retained power and control cables.
1.2.2 CLIN 0009 Furnish, Install, and Test New 13.8 kV/480 V, Dry-type Transformers TO1 and TO2
Payment for Furnish, Install, and Test New 13.8 kV/480 V, Dry-type Transformers TO1 and TO2 will be paid under CLIN 0009 on a unit price basis measured per transformer. Price and payment will constitute full compensation to furnish, install, and test new 15 kV/480 V, Dry-type transformers TO1 and TO2.
1.3 PROGRESS PAYMENT INVOICE
Requests for payment shall be submitted in accordance with Federal Acquisition Regulations (FAR) Subpart 32.9, entitled "PROMPT PAYMENT", and Clauses 52.232-5 and 52.232-27, entitled "Payments Under Fixed-Price Construction Contracts", and "Prompt Payment for Construction Contracts", respectively. In addition each request shall be submitted in the number of copies and to the designated billing office as shown in the Contract.
When submitting payment requests, complete Blocks 1 through 12 of the "PROGRESS PAYMENT INVOICE" Form as directed by the Contracting Officer
SECTION 01 22 00.00 10 Page 6
(provided in QCS). The completed form shall then become the cover document to which all other support data shall be attached.
One additional copy of the entire request for payment, to include the "PROGRESS PAYMENT INVOICE" cover document , shall be forwarded to a separate address as designated by the Contracting Officer.
Submit with each pay request, a list of subcontractors that have worked during that pay period. The listing shall be broken down into weeks, identifying each subcontractor that has worked during a particular week, and indicate the total number of employees that have worked on site for each subcontractor for each week. Also indicate the total number of employees for on-site staff for each week.
1.4 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS
1.4.1 Contractor POC
Within 14 days after award of the contract, designate a point of contact (POC) who will be responsible for the Construction Wage Rates Requirements Program for the Contractor and all subcontractors under this contract as required by the Contract Clauses and FAR 52.222.
1.4.2 Responsibilities
The designated Contractor POC shall be responsible for Construction Wage Rates Requirements Program activities including, but not limited to:
a. Documentation and record keeping;
b. Submittal and accuracy of certified payrolls;
c. Submittal of required labor forms including requests for additional classifications and rates, Statements and Acknowledgement, etc.;
d. Posting of the wage determination, approved additional classifications and rates, labor and EEO posters;
e. Coordination with the Contracting Officer's Labor Program POC.
Prior to submittal to the Government, payrolls shall be reviewed for compliance to all applicable labor standards, to include, but not be limited to the following items: correct wage rates, correct overtime classification and pay, misclassification of workers for work actually performed, apprentice to journeyman ratios, and registration of apprentice. Corrective actions shall be taken as necessary to ensure Contractor compliance with applicable contract and FAR clauses.
1.4.3 Certification
The Contractor POC shall provide a signed certification stating the following: "I certify that the submitted items being forwarded have been reviewed in detail and are correct and in strict conformance with the Labor Standards of the contract except as otherwise stated."
1.5 PROPOSED PROJECT MODIFICATIONS
Price proposals for contract modifications shall be submitted in accordance with the requirements of the Contract Clause MODIFICATION
SECTION 01 22 00.00 10 Page 7
PROPOSALS - PRICE BREAKDOWNS. If change order work impacts or delays other unchanged contract work, the costs of such impacts or delays shall be included in the proposals and separately identified. The current threshold for requiring cost or pricing data is $750,000 but is subject to change. (See FAR 15.403-4(a)(1)iii.) Any modification proposal that exceeds the cost and pricing data threshold shall meet the requirements of FAR 15.403-4. (See instructions for Change Orders/Modification and Claims in Table 15-2 of FAR 15.408.)
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used -- End of Section --
SECTION 01 22 00.00 10 Page 8
00 73 00-A - 1
ATTACHMENT 00 73 00-A
INDEX OF DRAWINGS
DRAWING NO. AFP-1.96-6-0A-0, DATED 20 OCT 15
SHEET
NUMBER
PLATE
NUMBER
TITLE REVISION
NUMBER
DATE
1 G-001 TITLE SHEET AND PROJECT LOCATION &
VICINITY MAP
2 G-002 INDEXS OF DRAWINGS R0001 3/9/17
3 G-003 REFERNCE DRAWING INDEX
4 G-004 ELECTRICAL NOTES & LEGEND
5 ED101 POWERHOUSE PLAN VIEW -- ELEVATION
2060 -- REMOVAL
6 ED102 POWERHOUSE PLAN VIEW -- ELEVATION
2042 & 2047 -- REMOVAL
7 ED201 TRANSVERSE SECTION -- -- REMOVAL
8 ED202 CIRCUIT BREAKER GALLERY PLAN VIEW --
15 KV SWITCHGEAR UNIT 1 -- REMOVAL
9 ED203 CIRCUIT BREAKER GALLERY PLAN VIEW --
15 KV SWITCHGEAR UNIT 2 -- REMOVAL
10 ED204 CIRCUIT BREAKER GALLERY PLAN VIEW --
15 KV SWITCHGEAR UNIT 3 -- REMOVAL
11 ED205 SECTIONS AND DETAILS -- 15 KV
SWITCHGEAR SJ1 -- REMOVAL
12 ED206 SECTIONS AND DETAILS -- 15 KV
SWITCHGEAR SJ2 -- REMOVAL
13 ED207 SECTIONS AND DETAILS -- 15 KV
SWITCHGEAR SJ3 -- REMOVAL
14 ED208 480 VAC SWITCHGEAR -- ELEVATION VIEW --
REMOVAL
15 ED209 MAIN CONTROL & INSTRUMENT BOARD --
FRONT ELEVATION VIEW -- REMOVAL
00 73 00-A - 2
W912DW-17-R-0011 R0001
SHEET
NUMBER
PLATE
NUMBER
TITLE REVISION
NUMBER
DATE
16 ED601 MAIN SINGLE LINE -- -- REMOVAL
17 ED602 THREE LINE DIAGRAM -- GENERATOR
SWITCHGEAR NUMBER 1 -- REMOVAL
18 ED603 THREE LINE DIAGRAM -- GENERATOR
SWITCHGEAR NUMBER 2 -- REMOVAL
19 ED604 THREE LINE DIAGRAM -- GENERATOR
SWITCHGEAR NUMBER 3 -- REMOVAL
20 ED605 XJ MAIN UNIT BREAKER -- CONTROL
SCHEMATIC -- REMOVAL
21 ED606 125 VDC CONTROL CIRCUITS -- SCHEMATIC
DIAGRAM -- REMOVAL
22 ED607 MAIN UNIT -- GOVERNOR CONTROL
SCHEMATIC -- DIGITAL INPUTS - REMOVAL
23 ED608 UNIT 2 EXCITER -- CONTROL SCHEMATIC --
REMOVAL
24 ED609 480 VAC STATION SERVICE -- ONE LINE
SHEET 1 -- REMOVAL
25 ED610 480 VAC STATION SERVICE -- ONE LINE
SHEET 2 -- REMOVAL
26 ED612 STATION SERVICE MAIN BREAKERS -- XQ01
& XQ02 -- REMOVAL
27 ED613 STATION SERVICE TIE & -- STANDBY GEN.
BREAKER -- REMOVAL
28 ED661 MAIN CONTROL BOARD PANEL 1C -- WIRING
29 ED662 MAIN CONTROL BOARD PANEL 1R -- WIRING
30 ED663 MAIN CONTROL BOARD PANEL 2C -- WIRING
31 ED664 MAIN CONTROL BOARD PANEL 2R -- WIRING
00 73 00-A - 3
W912DW-17-R-0011 R0001
SHEET
NUMBER
PLATE
NUMBER
TITLE REVISION
NUMBER
DATE
32 ED665 MAIN CONTROL BOARD PANEL 3C -- WIRING
33 ED666 MAIN CONTROL BOARD PANEL 3R -- WIRING
34 ED667 MAIN CONTROL BOARD PANEL 4C -- WIRING
35 ED801 CONDUIT AND CABLE SCHEDULE -- SHEET 1
-- REMOVAL
36 ED802 CONDUIT AND CABLE SCHEDULE -- SHEET 2
37 ED803 CONDUIT AND CABLE SCHEDULE -- SHEET 3
R0001 3/9/17
38 ED804 CONDUIT AND CABLE SCHEDULE -- SHEET 4
-- REMOVAL
R0001 3/9/17
3739 E-101 POWERHOUSE PLAN VIEW -- ELEVATION
2060 -- INSTALL
3840 E-102 POWERHOUSE PLAN VIEW -- ELEVATION
2042 & 2047 -- INSTALL
3941 E-201 TRANSVERSE SECTION -- -- INSTALL
4042 E-202 CIRCUIT BREAKER GALLERY PLAN VIEW --
15 KV SWITCHGEAR SJ1 -- INSTALL
4143 E-203 CIRCUIT BREAKER GALLERY PLAN VIEW --
15 KV SWITCHGEAR SJ2 -- INSTALL
4244 E-204 CIRCUIT BREAKER GALLERY PLAN VIEW --
15 KV SWITCHGEAR SJ3 -- INSTALL
4345 E-205 SECTIONS AND DETAILS -- 15 KV
SWITCHGEAR SJ1 -- INSTALL
4446 E-206 SECTIONS AND DETAILS -- 15 KV
SWITCHGEAR SJ2 -- INSTALL
4547 E-208 480 VAC SWITCHGEAR SQ1 -- ONE LINE
ELEVATION VIEW -- INSTALL
00 73 00-A - 4
W912DW-17-R-0011 R0001
SHEET
NUMBER
PLATE
NUMBER
TITLE REVISION
NUMBER
DATE
4648 E-209 MAIN CONTROL & INSTRUMENT BOARD --
FRONT ELEVATION VIEW -- INSTALL
4749 E-210 SC4 PANEL ELEVATION VIEW -- PARTIAL
LAYOUT -- INSTALL
R0001 3/9/17
4850 E-211 LOCAL/REMOTE PANEL SQ1C -- LAYOUT --
INSTALL
4951 E-212 POWERHOUSE PARTIAL PLAN -- ELEVATION
2080 -- INSTALL
5052 E-601 MAIN SINGLE LINE -- -- INSTALL
5153 E-605 XJ1 BREAKER -- CONTROL SCHEMATIC --
5254 E-606 125 VDC CONTROL CIRCUITS -- SCHEMATIC
DIAGRAM -- INSTALL
5355 E-607 MAIN UNIT -- GOVERNOR CONTROL
SCHEMATIC -- DIGITAL INPUTS - INSTALL
5456 E-608 UNIT 2 EXCITER -- CONTROL SCHEMATIC --
5557 E-609 480 VAC STATION SERVICE -- ONE LINE
SHEET 1 -- INSTALL
5658 E-610 480 VAC STATION SERVICE -- ONE LINE
SHEET 2 -- INSTALL
5759 E-611 SQ1 STATION SERVICE SWITCHBOARD --
ONE LINE -- INSTALL
5860 E-612 SQ1 MAIN BREAKER -- XQ01 & XQ02
CONRTOL SCHEMATICS -- INSTALL
5961 E-613 SQ1 TIE & TIE ISOLATION -- BREAKER
CONTROL SCHEMATICS -- INSTALL
6062 E-614 STANDBY GENERATOR & FEEDER --
BREAKER CONRTOL SCHEMATICS --
6163 E-615 DC AND PREFERRED AC SYSTEMS -- ONE
LINE DIAGRAM -- INSTALL
00 73 00-A - 5
W912DW-17-R-0011 R0001
SHEET
NUMBER
PLATE
NUMBER
TITLE REVISION
NUMBER
DATE
6264 E-616 125 VDC PANELBOARD CE-1, CE-2, & CE-3 --
SCHEDULE AND DETAILS -- INSTALL
6365 E-617 125 VDC PANELBOARD CE-4 -- SCHEDULE
AND DETAILS -- INSTALL
6466 E-661 MAIN CONTROL BOARD PANEL 1C -- WIRING
6567 E-662 MAIN CONTROL BOARD PANEL 1R -- WIRING
6668 E-663 MAIN CONTROL BOARD PANEL 2C -- WIRING
6769 E-664 MAIN CONTROL BOARD PANEL 2R -- WIRING
6870 E-665 MAIN CONTROL BOARD PANEL 3C -- WIRING
6971 E-666 MAIN CONTROL BOARD PANEL 3R -- WIRING
7072 E-667 MAIN CONTROL BOARD PANEL 4C -- WIRING
7173 E-668 SQ1 TERMINALS -- WIRING DIAGRAM --
7274 E-669 SQ1C TERMINALS -- WIRING DIAGRAM --
7375 E-801 CONDUIT AND CABLE SCHEDULE -- SHEET 1
-- INSTALL
7476 E-802 CONDUIT AND CABLE SCHEDULE -- SHEET 2
-- INSTALL
R0001 3/9/17
REFERENCE DRAWINGS
Reference drawings provided show conditions at time of construction. These drawings are furnished for information only and the Government does not warrant that conditions will be exactly as shown. Minor deviations can be anticipated and shall not be the basis for a claim for extra compensation.
00 73 00-A - 6
W912DW-17-R-0011 R0001
The list of reference drawings set out in the index on the drawings, Sheet No. S-001 is hereby incorporated by reference into these specifications.
SHEET NUMBER PLATE
NUMBER
TITLE
1 FIO-001 Powerhouse Main Auxilliary Board
2 FIO-002 Annunciation System Schematic Diagram
3 FIO-003 480 V Switchgear Front View Single Line Diagram
4 FIO-004 480 V Switchgear Elementary Diagram
5 FIO-005 480V Switchgear Schematic Diagram Main Breakers
6 FIO-006 Main Unit Relay Panel
FIO-007 Wiring Diagram Station Service Main Control Instrument Board
Panel 4C
8 FIO-008 Connection Diagram Relay Board Panel 4R
9 FIO-009 SJ Switchgear Unit 1 Schematic Diagram
10 FIO-010 XJ1 Close & Trip Schematic Diagram
11 FIO-011 SJ Switchgear Unit 2 Schematic Diagram
12 FIO-012 XJ2 Close & Trip Schematic Diagram
13 FIO-013 Wiring Diagram Main Unit Relay Board Panel 2R
14 FIO-014 15kV Metal Clad Switchgear Outline and General Arrangement
15 FIO-015 Standby Generator Room One Line Diagram
16 FIO-016 Wiring Diagrams Main Single Line
17 FIO-017 Electrical Plans Generator Room Plan El 2080.50 and Demolition
18 FIO-018 Electrical Plans Generator Room Mechanical and Electrical Details
19 FIO-019 Wiring Diagrams Standby Generator and Control Room One Line
20 FIO-020 Conduit and Groundig Plan El 2023
21 FIO-021 Conduit and Groundig Plan El 2042 & 2047 Assembly Bay
22 FIO-022 Conduit and Groundig Plan El 2042 Assembly Bay
00 73 00-A - 7
W912DW-17-R-0011 R0001
23 FIO-023 Conduit and Groundig Plan El 2042 & 2047 Unit 1 Monolith
24 FIO-024 Conduit and Groundig Plan El 2042 & 2047 Unit 1 Monolith
25 FIO-025 Conduit and Groundig Plan El 2042 & 2047 Unit 2 Monolith
26 FIO-026 Conduit and Groundig Plan El 2042 & 2047 Unit 2 Monolith
27 FIO-027 Conduit and Groundig Plan El 2042 & 2047 Unit 3 Monolith
28 FIO-028 Conduit and Groundig Plan El 2042 & 2047 Unit 3 Monolith
29 FIO-029 Conduit and Groundig Plan El 2060 Assembly Bay
30 FIO-030 Conduit and Groundig Plan El 2060 Assembly Bay
31 FIO-031 Conduit and Groundig Plan El 2060 Assembly Bay
32 FIO-032 Conduit and Groundig Plan El 2060 & 2070 Unit 1 Monolith
33 FIO-033 Conduit and Groundig Plan El 2060 Unit 1 Monolith
34 FIO-034 Conduit and Groundig Plan El 2060 Unit 1 Monolith
35 FIO-035 Conduit and Groundig Plan El 2060 & 2070 Unit 2 Monolith
36 FIO-036 Conduit and Groundig Plan El 2060 Unit 2 Monolith
37 FIO-037 Conduit and Groundig Plan El 2060 Unit 2 Monolith
38 FIO-038 Conduit and Groundig Plan El 2060 & 2070 Unit 3 Monolith
39 FIO-039 Conduit and Groundig Plan El 2060 Unit 3 Monolith
40 FIO-040 Conduit and Groundig Plan El 2060 Unit 3 Monolith
41 FIO-041 Conduit & Grounding Sections & Details
42 FIO-042 Conduit & Grounding Sections & Details
43 FIO-043 Conduit & Grounding Sections & Details
44 FIO-044 Conduit & Grounding Sections & Details
45 FIO-045 Conduit & Grounding Main Grounding Schematic Diagram
FIO-046 AC Main Auxilliary Power Board Outline and General
Arrangement
FIO-047 AC Main Unit Aux Power Board and Lighting Board Outline
General Arrangement
00 73 00-A - 8
W912DW-17-R-0011 R0001
48 FIO-048 Purifier Board and Pump Board Outline and General Arrangement
FIO-049 Mechanical Equipment Board & Misc Cabinets Outline and General
Arrangement
50 FIO-050 15kV Metal Cald Switchgear Outline and General Arrangelent
51 FIO-051 Generator Leads General Arrangement
52 FIO-052 125VDC Control Circuits Diagram
53 FIO-053 Generator 1 & Transformer 1 Connection Diagram
54 FIO-054 Generator 2 & Transformer 2 Connection Diagram
55 FIO-055 Generator 3 & Transformer 3 Connection Diagram
56 FIO-056 CO2 Systems Connection Diagram
57 FIO-057 Main Auxilliary Board Connection Diagram
58 FIO-058 Plan Turbine Floor El 2042 & 2047
59 FIO-059 Demolition Plan and Floor Plan
60 FIO-060 DC and Preferred AC System One Line Diagram
61 FIO-061 125VDC Panelboards CE-1,CE-2,and CE-3 Schedule and Details
62 FIO-062 125VDC Panelboards CE-4 Schedule and Details
63 FIO-063 Powerplant Equipment Arrangement Transverse section
FIO-064 MAIN CONTROL & INSTRUMENT BOARD FRONT
ELEVATION
65 FIO-065 WIRING DIAGRAMS MAIN SINGLE LINE
66 FIO-066 SJ SWITCHGEAR UNIT 3 SCHEMATIC DIAGRAM
67 FIO-067 XJ3 CLOSE & TRIP SCEMATIC DIAGRAM
FIO-068 125 V DC CONTROL CIRCUITS TRANSFORMER RELAY
UNIT 1
69 FIO-069 UNIT CONTROLLER SCHEMATIC
70 FIO-070 UNIT 2 EXCITATION SYSTEM SCHEMATIC DIAGRAM
FIO-071 WIRING DIAGRAM MAIN CONTROL & INSTRUMENT
BOARD PANEL 1C
FIO-072 WIRING DIAGRAM MAIN CONTROL & INSTRUMENT
BOARD PANEL 2C
00 73 00-A - 9
W912DW-17-R-0011 R0001
FIO-073 WIRING DIAGRAM MAIN CONTROL & INSTRUMENT
BOARD PANEL 3C
FIO-074 WIRING DIAGRAM MAIN CONTROL & INSTRUMENT
BOARD PANEL 1R
FIO-075 WIRING DIAGRAM MAIN CONTROL & INSTRUMENT
BOARD PANEL 2R
FIO-076 WIRING DIAGRAM MAIN CONTROL & INSTRUMENT
BOARD PANEL 3R
77 FIO-077 ARRANGEMENT TRANSVERSE SECTIONS
78 FIO-078 ARRANGEMENT LONGITUDINAL SECTIONS
79 FIO-079 ARRANGEMENT GENERAL PLAN
FIO-080 ARRANGEMENT SUPERSTRUCTURE PLAN &
MISCELLANEOUS SECTIONS
81 FIO-081 ARRANGEMENT PLAN GENERATOR FLOOR
82 FIO-082 ARRANGEMENT PLAN TURBINE FLOOR
83 FIO-083 ARRANGEMENT PLAN GENERATOR FLOOR EL 2060
84 FIO-084 ARRANGEMENT PLAN GENERATOR FLOOR EL 2042 & 2047
End of Attachment 00 73 00-A
This page intentionally left blank.
G-004
G-003
G-002
G-001
AFP-1.96_G-004XXX.dgn
AFP-1.96_G-003XXX.dgn
AFP-1.96_G-002XXX.dgn
AFP-1.96_G-001XXX.dgn
ELECTRICAL NOTES & LEGEND
REFERENCE DRAWING INDEX
INDEX OF DRAWINGS
SITE LOCATION AND -- VICINITY MAP
E-802
E-801
E-669
E-668
E-667
E-666
E-665
E-664
E-663
E-662
E-661
E-617
E-616
E-615
E-614
E-613
E-612
E-611
E-610
E-609
E-608
E-607
E-606
E-605
E-604
E-603
E-602
E-601
E-212
E-211
E-210
E-209
E-208
E-207
E-206
E-205
E-204
E-203
E-202
E-201
E-102
E-101
AFP-1.96_E-802XXX.dgn
AFP-1.96_E-801XXX.dgn
AFP-1.96_E-669XXX.dgn
AFP-1.96_E-668XXX.dgn
AFP-1.96_E-667XXX.dgn
AFP-1.96_E-666XXX.dgn
AFP-1.96_E-665XXX.dgn
AFP-1.96_E-664XXX.dgn
AFP-1.96_E-663XXX.dgn
AFP-1.96_E-662XXX.dgn
AFP-1.96_E-661XXX.dgn
AFP-1.96_E-617XXX.dgn
AFP-1.96_E-616XXX.dgn
AFP-1.96_E-615XXX.dgn
AFP-1.96_E-614XXX.dgn
AFP-1.96_E-613XXX.dgn
AFP-1.96_E-612XXX.dgn
AFP-1.96_E-611XXX.dgn
AFP-1.96_E-610XXX.dgn
AFP-1.96_E-609XXX.dgn
AFP-1.96_E-608XXX.dgn
AFP-1.96_E-607XXX.dgn
AFP-1.96_E-606XXX.dgn
AFP-1.96_E-605XXX.dgn
RESERVED
RESERVED
RESERVED
AFP-1.96_E-601XXX.dgn
AFP-1.96_E-212XXX.dgn
AFP-1.96_E-211XXX.dgn
AFP-1.96_E-210XXX.dgn
AFP-1.96_E-209XXX.dgn
AFP-1.96_E-208XXX.dgn
RESERVED
AFP-1.96_E-206XXX.dgn
AFP-1.96_E-205XXX.dgn
AFP-1.96_E-204XXX.dgn
AFP-1.96_E-203XXX.dgn
AFP-1.96_E-202XXX.dgn
AFP-1.96_E-201XXX.dgn
AFP-1.96_E-102XXX.dgn
AFP-1.96_E-101XXX.dgn
CONDUIT AND CABLE SCHEDULE -- SHEET 2 -- INSTALL
CONDUIT AND CABLE SCHEDULE -- SHEET 1 -- INSTALL
SQ1C TERMINALS -- WIRING DIAGRAM -- INSTALL
SQ1 TERMINALS -- WIRING DIAGRAM -- INSTALL
MAIN CONTROL BOARD PANEL 4C -- WIRING DIAGRAM -- INSTALL
MAIN CONTROL BOARD PANEL 3R -- WIRING DIAGRAM -- INSTALL
MAIN CONTROL BOARD PANEL 3C -- WIRING DIAGRAM -- INSTALL
MAIN CONTROL BOARD PANEL 2R -- WIRING DIAGRAM -- INSTALL
MAIN CONTROL BOARD PANEL 2C -- WIRING DIAGRAM -- INSTALL
MAIN CONTROL BOARD PANEL 1R -- WIRING DIAGRAM -- INSTALL
MAIN CONTROL BOARD PANEL 1C -- WIRING DIAGRAM -- INSTALL
125 VDC PANELBOARD CE-4 -- SCHEDULE AND DETAILS -- INSTALL
125 VDC PANELBOARD CE-1, CE-2, & CE-3 -- SCHEDULE AND DETAILS -- INSTALL
DC AND PREFERRED AC SYSTEMS -- ONE LINE DIAGRAM -- INSTALL
STANDBY GENERATOR & FEEDER -- BREAKER CONRTOL SCHEMATICS -- INSTALL
SQ1 TIE & TIE ISOLATION -- BREAKER CONTROL SCHEMATICS -- INSTALL
SQ1 MAIN BREAKER -- XQ01 & XQ02 CONRTOL SCHEMATICS -- INSTALL
SQ1 STATION SERVICE SWITCHBOARD -- ONE LINE -- INSTALL
480 VAC STATION SERVICE -- ONE LINE SHEET 2 -- INSTALL
480 VAC STATION SERVICE -- ONE LINE SHEET 1 -- INSTALL
UNIT 2 EXCITER -- CONTROL SCHEMATIC -- INSTALL
MAIN UNIT -- GOVERNOR CONTROL SCHEMATIC -- DIGITAL INPUTS - INSTALL
125 VDC CONTROL CIRCUITS -- SCHEMATIC DIAGRAM -- INSTALL
XJ1 BREAKER -- CONTROL SCHEMATIC -- INSTALL
RESERVED
RESERVED
RESERVED
MAIN SINGLE LINE -- -- INSTALL
POWERHOUSE PARTIAL PLAN -- ELEVATION 2080 -- INSTALL
LOCAL/REMOTE PANEL SQ1C -- LAYOUT -- INSTALL
SC4 PANEL ELEVATION VIEW -- PARTIAL LAYOUT -- INSTALL
MAIN CONTROL & INSTRUMENT BOARD -- FRONT ELEVATION VIEW -- INSTALL
480 VAC SWITCHGEAR SQ1 -- ONE LINE ELEVATION VIEW -- INSTALL
RESERVED
SECTIONS AND DETAILS -- 15 KV SWITCHGEAR SJ2 -- INSTALL
SECTIONS AND DETAILS -- 15 KV SWITCHGEAR SJ1 -- INSTALL
CIRCUIT BREAKER GALLERY PLAN VIEW -- 15 KV SWITCHGEAR SJ3 -- INSTALL
CIRCUIT BREAKER GALLERY PLAN VIEW -- 15 KV SWITCHGEAR SJ2 -- INSTALL
CIRCUIT BREAKER GALLERY PLAN VIEW -- 15 KV SWITCHGEAR SJ1 -- INSTALL
TRANSVERSE SECTION -- -- INSTALL
POWERHOUSE PLAN VIEW -- ELEVATION 2042 & 2047 -- INSTALL
POWERHOUSE PLAN VIEW -- ELEVATION 2060 -- INSTALL
ED804
ED803
ED802
ED801
ED667
ED666
ED665
ED664
ED663
ED662
ED661
ED613
ED612
ED610
ED609
ED608
ED607
ED606
ED605
ED604
ED603
ED602
ED601
ED209
ED208
ED207
ED206
ED205
ED204
ED203
ED202
ED201
ED102
ED101
AFP-1.96_ED804XXX.dgn
AFP-1.96_ED803XXX.dgn
AFP-1.96_ED802XXX.dgn
AFP-1.96_ED801XXX.dgn
AFP-1.96_ED667XXX.dgn
AFP-1.96_ED666XXX.dgn
AFP-1.96_ED665XXX.dgn
AFP-1.96_ED664XXX.dgn
AFP-1.96_ED663XXX.dgn
AFP-1.96_ED662XXX.dgn
AFP-1.96_ED661XXX.dgn
AFP-1.96_ED613XXX.dgn
AFP-1.96_ED612XXX.dgn
AFP-1.96_ED610XXX.dgn
AFP-1.96_ED609XXX.dgn
AFP-1.96_ED608XXX.dgn
AFP-1.96_ED607XXX.dgn
AFP-1.96_ED606XXX.dgn
AFP-1.96_ED605XXX.dgn
AFP-1.96_ED604XXX.dgn
AFP-1.96_ED603XXX.dgn
AFP-1.96_ED602XXX.dgn
AFP-1.96_ED601XXX.dgn
AFP-1.96_ED209XXX.dgn
AFP-1.96_ED208XXX.dgn
AFP-1.96_ED207XXX.dgn
AFP-1.96_ED206XXX.dgn
AFP-1.96_ED205XXX.dgn
AFP-1.96_ED204XXX.dgn
AFP-1.96_ED203XXX.dgn
AFP-1.96_ED202XXX.dgn
AFP-1.96_ED201XXX.dgn
AFP-1.96_ED102XXX.dgn
AFP-1.96_ED101XXX.dgn
CONDUIT AND CABLE SCHEDULE -- SHEET 4 -- REMOVAL
CONDUIT AND CABLE SCHEDULE -- SHEET 3 -- REMOVAL
CONDUIT AND CABLE SCHEDULE -- SHEET 2 -- REMOVAL
CONDUIT AND CABLE SCHEDULE -- SHEET 1 -- REMOVAL
MAIN CONTROL BOARD PANEL 4C -- WIRING DIAGRAM -- REMOVAL
MAIN CONTROL BOARD PANEL 3R -- WIRING DIAGRAM -- REMOVAL
MAIN CONTROL BOARD PANEL 3C -- WIRING DIAGRAM -- REMOVAL
MAIN CONTROL BOARD PANEL 2R -- WIRING DIAGRAM -- REMOVAL
MAIN CONTROL BOARD PANEL 2C -- WIRING DIAGRAM -- REMOVAL
MAIN CONTROL BOARD PANEL 1R -- WIRING DIAGRAM -- REMOVAL
MAIN CONTROL BOARD PANEL 1C -- WIRING DIAGRAM -- REMOVAL
STATION SERVICE TIE & -- STANDBY GEN. BREAKER -- REMOVAL
STATION SERVICE MAIN BREAKERS -- XQ01 & XQ02 -- REMOVAL
480 VAC STATION SERVICE -- ONE LINE SHEET 2 -- REMOVAL
480 VAC STATION SERVICE -- ONE LINE SHEET 1 -- REMOVAL
UNIT 2 EXCITER -- CONTROL SCHEMATIC -- REMOVAL
MAIN UNIT -- GOVERNOR CONTROL SCHEMATIC -- DIGITAL INPUTS - REMOVAL
125 VDC CONTROL CIRCUITS -- SCHEMATIC DIAGRAM -- REMOVAL
XJ MAIN UNIT BREAKER -- CONTROL SCHEMATIC -- REMOVAL
THREE LINE DIAGRAM -- GENERATOR SWITCHGEAR NUMBER 3 -- REMOVAL
THREE LINE DIAGRAM -- GENERATOR SWITCHGEAR NUMBER 2 -- REMOVAL
THREE LINE DIAGRAM -- GENERATOR SWITCHGEAR NUMBER 1 -- REMOVAL
MAIN SINGLE LINE -- -- REMOVAL
MAIN CONTROL & INSTRUMENT BOARD -- FRONT ELEVATION VIEW -- REMOVAL
480 VAC SWITCHGEAR -- ELEVATION VIEW -- REMOVAL
SECTIONS AND DETAILS -- 15 KV SWITCHGEAR SJ3 -- REMOVAL
SECTIONS AND DETAILS -- 15 KV SWITCHGEAR SJ2 -- REMOVAL
SECTIONS AND DETAILS -- 15 KV SWITCHGEAR SJ1 -- REMOVAL
CIRCUIT BREAKER GALLERY PLAN VIEW -- 15 KV SWITCHGEAR UNIT 3 -- REMOVAL
CIRCUIT BREAKER GALLERY PLAN VIEW -- 15 KV SWITCHGEAR UNIT 2 -- REMOVAL
CIRCUIT BREAKER GALLERY PLAN VIEW -- 15 KV SWITCHGEAR UNIT 1 -- REMOVAL
TRANSVERSE SECTION -- -- REMOVAL
POWERHOUSE PLAN VIEW -- ELEVATION 2042 & 2047 -- REMOVAL
POWERHOUSE PLAN VIEW -- ELEVATION 2060 -- REMOVAL
W
D W -1
-R -0
A F P -1 .9
-6 -0
A -0 /2
A F P -1 .9
G -0
X X
X .d g n
K F
L O
R E
N C
E
G-002
IN
D
E X O
F D
R A
W
IN
G S
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
P O
R T
L A
N D
O R
E G
O N
H Y
D R
O E
L E
C T
R
IC
D
E S
IG
N C
E N
T E
R
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
S E
A T
T L E D
IS
T R
IC
T
S T
E V
E N R
M
IL
E S P .E
.8 K
V
A N
D
V S
W
IT
C H
G E
A R
P O
W E
R H
O U
S E
P E
N D O
R E
IL
L E R
IV
E R
ID
A H
O
A L
B E
N I F
A L L S P
R O J E
C T
A N
S I F
G
H D
C B
P E
D T
R O
W B
R
ID
G E
S E
A T
T L E
W A
S H
IN
G T
O N
ELECTRICAL DEMOLITION
GENERAL
DRAWING NO.
NO.
SHEET
TITLE
INDEX OF CONTRACT DRAWINGS
NO.
SHEET
DRAWING NO. TITLE
ELECTRICAL INSTALLATION
R0001
T W
O D
R A
W
IN
G S A
D D
E D A
S P
A R
T O
F A
M E
N D
M E
N T R
DRAWING PLOT SIZE: ANSI B
D
C
A
B
S O
L
IC
IT
A T
IO
N N
O
F
IL
E N
A M
E
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D A
T E
F
IL
E N
U M
B E
R
S
IZ
E
S U
B M
IT
T E
D B
Y
P L
O T S
C A
L E
P L
O T D
A T
E
C O
N T
R A
C T N
O
IDENTIFICATION
SHEET
1 2 3 4 5 6
E
D E
S C
R
IP
T
IO
N M
A R
K D
A T
E A
P P
R of Engineers
US Army Corps
/8 /2
BORDER VERSION UPDATE [09-2012]
G-002SHEET NAME:g2hdcncg BY USERNAME:DATE AND TIME PLOTTED: 3/8/2017 1:17:23 PM
NOTES:
3. DRAWING ADDED AS PART OF AMENDMENT R0001
2. LIGHT WEIGHT TEXT INDICATES EQUIPMENT INTENDED TO REMAIN OR REUSED.\
1. HEAVY WEIGHT TEXT INDICATES EQUIPMENT TO BE REMOVED.
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
P O
R T
L A
N D
O R
E G
O
H Y
D R
O E
L E
C T
R
IC
D
E S
IG
N C
E N
T E
R
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
S E
A T
T L E
W A
S H
IN
G T
O N
S E
A T
T L E D
IS
T R
IC
T
S
E V
E N R
M
IL
E S P .E
A N
S I F
P -1 .9
E
D
X X
X .d g n
G
H D
C N
C G
K
W O
M A
C K
K F
L O
R E
N C
E
R E
M O
V A
L S
H E
E T
C O
N D
U
IT
A
N D C
A B
L E S
C H
E D
U L E
ED803
.8
D
V S
W
IT
C H
G E
A R
P O
W E
R H
O U
S E
P E
N D O
R E
IL
L E R
IV
E R
ID
A H
O W
D W -1
-R -0
L
B E
N I F
A L L S P
R O J E
C
R0001
D R
A W
IN
G A
D D
E D A
S P
A R
T O
F A
M E
N D
M E
N T R
DRAWING PLOT SIZE: ANSI B
D
C
A
B
S O
L
IC
IT
A T
IO
N N
O
F
IL
E N
A M
E
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D A
T E
F
IL
E N
U M
B E
R
S
IZ
E
S U
B M
IT
T E
D B
Y
P L
O T S
C A
L E
P L
O T D
A T
E
C O
N T
R A
C T N
O
IDENTIFICATION
SHEET
1 2 3 4 5 6
E
D E
S C
R
IP
T
IO
N M
A R
K D
A T
E A
P P
R of Engineers
US Army Corps
/8 /2
BORDER VERSION UPDATE [09-2012]
ED801SHEET NAME:g2hdcncg BY USERNAME:DATE AND TIME PLOTTED: 3/8/2017 1:14:34 PM
SEATTLE DISTRICT
3. DRAWING ADDED AS PART OF AMENDMENT R0001.
2. LIGHT WEIGHT TEXT INDICATES EQUIPMENT INTENDED TO REMAIN OR REUSED.
1. HEAVY WEIGHT TEXT INDICATES EQUIPMENT TO BE REMOVED.
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
P O
R T
L A
N D
O R
E G
D R
O E
L E
C T
R
IC
D
E S
IG
N C
E N
T E
R
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
S E
A T
T L E
W A
S H
IN
G T
O N
S E
A T
T L E D
IS
T R
E V
E N R
M
IL
E S P .E
A N
S I
P -1 .9
E
D
X X
X .d g n
G
H D
C N
C G
K
W O
M A
C K
K F
L O
R E
N C
E
R E
M O
V A
L S
H E
E T
C O
N D
U
IT
A
N D C
A B
L E S
C H
E D
U L
ED804
.8
D
V S
W
IT
C H
G E
A R
P O
W E
R H
O U
S E
P E
N D O
R E
IL
L E R
IV
E R
ID
A H
O W
D W -1
-R -0
L
B E
N I F
A L L S P
R O J E
C
R0001
D R
A W
IN
G A
D D
E D A
S P
A R
T O
F A
M E
N D
M E
N T R
DRAWING PLOT SIZE: ANSI B
D
C
A
B
S O
L
IC
IT
A T
IO
N N
O
F
IL
E N
A M
E
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D A
T E
F
IL
E N
U M
B E
R
S
IZ
E
S U
B M
IT
T E
D B
Y
P L
O T S
C A
L E
P L
O T D
A T
E
C O
N T
R A
C T N
O
IDENTIFICATION
SHEET
1 2 3 4 5 6
E
D E
S C
R
IP
T
IO
N M
A R
K D
A T
E A
P P
R of Engineers
US Army Corps
/8 /2
BORDER VERSION UPDATE [09-2012]
ED801SHEET NAME:g2hdcncg BY USERNAME:DATE AND TIME PLOTTED: 3/8/2017 1:15:55 PM
ITEM DESCRIPTIONUNITQTY
MATERIALS LIST
PLATE
NAME
(AS REQ'D)
DIMENSION
ENGRAVED DESCRIPTION
SIZE
FONT
1 X 4"50
1 X 4"
1 X 4"
1 X 4"
1 X 4"
" TEXT4
" TEXT4
" TEXT4
" TEXT4
" TEXT4
XQ01
XQ02
XQ04
54 55
2 2
1 X 4"48
49 1 X 4"
" TEXT4
" TEXT4
XJ01
XJ02
56 57
1 X 4"
1 X 4"
" TEXT4
" TEXT4
TQ01
TQ02
1 1 EA
ELECTROSWITCH SERIES 24 WITH LED NAMEPLATE, PISTOL GRIP TYPEEA72
STEEL SHEET
NTS
LAYOUT
SC4 LOWER PANEL
NOTES:
46 47
1 X 4"47 " TEXT4
1 X 4"46 " TEXT4
3 FROM UNIT 1
FROM UNIT 2
STANDBY GEN BKR # 1
STANDBY GEN BKR #2
3. DRAWING MISSING FROM ORIGINAL SOLICITATION
IDENTICAL IN COLOR AND SIZE.
2. REPLICATE EXISTING MIMIC BUS WITH NEW
1. BOLD ITEMS INDICATE NEW EQUIPMENT.
P -1 .9
-6 -1
A /3
A F P -1 .9
E -2
X X
X .d g n
K F
L O
R E
N C
E
.8
D
V S
W
IT
C H
G E
A R
P O
W E
R H
O U
S E
D T
R O
W B
R
ID
G E
E-210
IN
S
T A
L L
S T
E V
E N R
M
IL
E S P .E
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
P O
R T
L A
N D
O R
E G
O N
H Y
D R
O E
L E
C T
R
IC
D
E S
IG
N C
E N
T E
R
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
S E
A T
T L E D
IS
T R
IC
T P
E N
D O
R E
IL
L E R
IV
E R
ID
A H
O G
H
D C
B P
E
A N
S I F
A L
B E
N I F
A L L S P
R O J E
C T
NAMEPLATE SCHEDULE
P A
R T
IA
L L
A Y
O U
T
S E
A T
T L E
W A
S H
IN
G T
O N
S C
P
A N
E L E
L E
V A
T
IO
N V
IE
W
W
D W -1
-R -0
D
R A
W
IN
G M
IS
S
IN
G F
R O
M O
R
IG
IN
A L S
O L
IC
A T
IO
N
A D
D E
D I
N A
M E
N D
M E
N T R
R0001
DRAWING PLOT SIZE: ANSI B
D
C
A
B
S O
L
IC
IT
A T
IO
N N
O
F
IL
E N
A M
E
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D A
T E
F
IL
E N
U M
B E
R
S
IZ
E
S U
B M
IT
T E
D B
Y
P L
O T S
C A
L E
P L
O T D
A T
E
C O
N T
R A
C T N
O
IDENTIFICATION
SHEET
1 2 3 4 5 6
E
D E
S C
R
IP
T
IO
N M
A R
K D
A T
E A
P P
R of Engineers
US Army Corps
/8 /2
BORDER VERSION UPDATE [09-2012]
E-210SHEET NAME:g2hdcncg BY USERNAME:DATE AND TIME PLOTTED: 3/8/2017 1:12:20 PM
2. LIGHT WEIGHT TEXT INDICATES EQUIPMENT INTENDED TO REMAIN OR REUSED.
1. HEAVY WEIGHT TEXT INDICATES EQUIPMENT TO BE INSTALLED.
1 1/2 55
P
W E
R H
O U
S E
A L
B E
N I F
A L L S P
R O J E
C T
P E
N D O
R E
IL
L E R
IV
E R
ID
A H
O
.8 K
V A
N D
V S
W
IT
C H
G E
A R
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
P O
R T
L A
N D
O R
E G
D R
O E
L E
C T
R
IC
D
E S
IG
N C
E N
T E
R
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
S E
A T
T L E
W A
S H
IN
G T
O N
S E
A T
T L E D
IS
T R
E V
E N R
M
IL
E S P .E
A N
S I F
G
H D
C B
P E
K
W O
M A
C K
K F
L O
R E
N C
E
IN
S
T A
L L
S H
E E
T
C O
N D
U
IT
A
N D C
A B
L E S
C H
E D
U L
E-802
P -1 .9
-6 -9
A /4
/0
/2
P -1 .9
E -8
X X
X .d g n
C
O N
D U
IT
S
IZ
E A
N D C
A B
L E L
E N
G T
H H
A V
E B
E E
N R
E V
IS
E D
R0001
/9 /2
DRAWING PLOT SIZE: ANSI B
D
C
A
B
S O
L
IC
IT
A T
IO
N N
O
F
IL
E N
A M
E
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D A
T E
F
IL
E N
U M
B E
R
S
IZ
E
S U
B M
IT
T E
D B
Y
P L
O T S
C A
L E
P L
O T D
A T
E
C O
N T
R A
C T N
O
IDENTIFICATION
SHEET
1 2 3 4 5 6
E
D E
S C
R
IP
T
IO
N M
A R
K D
A T
E A
P P
R of Engineers
US Army Corps
/9 /2
BORDER VERSION UPDATE [09-2012]
E-802SHEET NAME:g2hdcncg BY USERNAME:DATE AND TIME PLOTTED: 3/9/2017 10:16:51 AM
This page intentionally left blank.
g3ctccbm Line
| Amendment 0001 |
| 01 11 10.00 26 |
| 01 22 00.00 10 |
| 00 73 00-A |
| PLANS_R0001 |
| G-002 - INDEXS OF DRAWINGS |
| ED803 - CONDUIT AND CABLE SCHEDULE -- SHEET 3 -- REMOVAL |
| ED804 - CONDUIT AND CABLE SCHEDULE -- SHEET 4 -- REMOVAL |
| E-210 - SC4 PANEL ELEVATION VIEW -- PARTIAL LAYOUT -- INSTALL |
| E-802 - CONDUIT AND CABLE SCHEDULE -- SHEET 2 -- INSTALL |