AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912DW-17-B-0004 FY17 MEDEVAC Aircraft Maintenance Hangar, Yakima Training Center, WA
1.The purpose of this R0004 provides for the follow ing:
(see next page)
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Sep-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW-17-B-0004
X 9B. DATED (SEE ITEM 11)
22-Aug-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Sep-2017
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CENWS-CT
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DW-17-B-0004
R0004
a. Section 02 41 00-A Hazardous Materials Survey Report Addendum: Yakima Training Center, Building 223, WA Note: In regards to General Wage Decision WA170045, revision 9 will be posted on Amendment R0005, when available, on Friday, 9/15/17.
2. The proposal due date and time remains as Thursday, 21 Sep 2017 at 2:00 p.m. LOCAL TIME.
3. The attached revised sections are to be replaced in their entirety. Specifications changes are generally identified, for convenience, either by strikeout for deletions, and double underlining of text for additions or a single dark line in the margin. All portions of the revised sections shall apply whether or not changes have been indicated.
4. All other terms and conditions of the Solicitation remain unchanged.
Enclosures:
Section 02 41 00-A
This page intentionally blank
Page 1 of 2 INNOVEX Environmental Management, Inc.
December 2, 2016
Brad Endres Jacobs Engineering Group 777 Main Street Fort Worth, TX 76102
Subject: Hazardous Materials Survey Report Addendum: Yakima Training Center, Building
Mr. Brad Endres, Innovex Environmental Management, Inc. (INNOVEX) is submitting this addendum to the previously issued Hazardous Materials Survey Report for Building 223 at Yakima Training Center (YTC) dated November 9, 2016. Per the request of Jacobs Engineering Group (JACOBS), INNOVEX collected additional suspect asbestos containing materials (ACM) inside the boilers and water tanks at Building 223 on November 16, 2016. The boilers and water tanks were previously not opened to access for sampling. Additionally, INNOVEX identified an additional paint coating to be sampled. This addendum includes the following documents:
Table 1 (Revised) — Asbestos Containing Materials Sample Inventory, YTC Building 223.
Table 1 has been revised to include the additional sampling of suspect ACM inside the boilers and water tanks at Building 223. Fifteen suspect ACM samples were collected. The samples are labeled as 223-19A, 223-19B, 223-20A, 223-20B, 223-21A, 223-21B, 223- 22A, 223-22B, 223-23A, 223-23B, 223-24A, 223-24B, 223-25A, 223-25B, and 223-25C.
Table 2 (Revised) — Lead-Containing Paint Sample Inventory, YTC Building 223. Table 2 has been revised to include the sampling of an additional paint coating identified during sampling on November 16, 2016. The additional sample is labeled as 223-Pb-12.
Revised Appendix C — The samples identified above were submitted to EMSL Analytical, Inc. on November 17, 2016 for Asbestos Analysis of Bulk Materials by EPA 600/R-93/116 using Polarized Light Microscopy (PLM) and Lead in Paint Chips by Flame Atomic Absorption Spectroscopy (FAAS). No asbestos or lead was detected in any of the samples collected as identified above.
If you have any questions regarding this submission, please feel free to contact me at 206-841-4091 or andrea.winder@innovex.net.
Hazardous Materials Survey Report Addendum JACOBS December 2, 2016 Yakima Training Center Building 223, Yakima, Washington
Page 2 of 2 INNOVEX Environmental Management, Inc.
Sincerely, Innovex Environmental Management, Inc.
Andrea Winder, Senior Project Environmental Scientist AHERA Building Inspector No. 156318
ATTACHMENTS:
Table 1 (Revised) Asbestos Containing Materials Sample Inventory Table 2 (Revised) Lead-Containing Paint Sample Inventory Appendix C Laboratory Analytical Reports:
EMSL Laboratory Analytical Report, 511601806 (Bulk Asbestos Materials) EMSL Laboratory Analytical Report, 511601805 (Lead Paint Chip)
Sample ID Sample Date Material Description Location Lab Description Bulk Asbestos1
223-01A 10/13/2016 CMU and Grout Northeast Wall Room 1 CMU/Grout ND
223-01B 10/13/2016 CMU and Grout North Wall Room 1 CMU/Grout ND
223-02A 10/13/2016 Concrete Pad Boiler #1 Room 1 Concrete Pad ND
223-02B 10/13/2016 Concrete Pad Boiler #3 Room 1 Concrete Pad ND
223-03 10/13/2016 Concrete Floor North Entrance Room 1 Concrete Floor ND
223-04A 10/13/2016 Gray Soft Window Putty Bathroom Window N Wall Gray Soft Window Putty ND
223-04B 10/13/2016 Gray Soft Window Putty Northeast Adjacent Bathroom Gray Soft Window Putty ND
223-05A 10/13/2016 Gray Hard Window Putty Bathroom Window North Wall Gray Hard Window Putty ND
223-05B 10/13/2016 Gray Hard Window Putty Northwest Window Room 1 Gray Hard Window Putty ND
223-06A 10/13/2016 White Hard Window Putty Northeast Window Room 1 White Hard Window Putty ND
223-06B 10/13/2016 White Hard Window Putty Southwest Window Room 1 White Hard Window Putty ND
Black Wrap 24-in Pipe Elbow TSI Black Wrap ND
Gray Insulation TSI Gray Insulation ND
Black Wrap 24-in Pipe Elbow TSI Black Wrap ND
Gray Insulation TSI Gray Insulation ND
Black Wrap 24-in Pipe Elbow TSI Black Wrap ND
Gray Insulation TSI Gray Insulation ND
Silver Paint Silver Paint ND
White Wrap 24-in Pipe @ penetration TSI White Wrap ND
Gray Insulation TSI Gray Insulation ND
Silver Paint Silver Paint ND
White Wrap 24-in Pipe @ penetration TSI White Wrap ND
Gray Insulation TSI Gray Insulation ND
Light Green Wrap 6-in Pipe Elbow TSI White/Green Wrap ND
Gray Insulation TSI Gray Insulation ND
Light Green Wrap 6-in Pipe Elbow TSI White/Green Wrap ND
Gray Insulation TSI Gray Insulation ND
Light Green Wrap 6-in Pipe Elbow TSI White/Green Wrap ND
Gray Insulation TSI Gray Insulation ND
Table 1 (Revised) Asbestos-Containing Materials Sample Inventory
YTC Building 223 Yakima, Washington
223-09B 10/13/2016
223-09C 10/13/2016 Above Boiler #3 Room 1
10/13/2016
Above Boiler #4 Room 1
223-09A 10/13/2016 Boiler #2 Room 1
223-08B
Above Boiler #4 Room 1
Above Boiler #3 Room 1
223-07A 10/13/2016 Above Boiler #3 Room 1
223-07B 10/13/2016 Above Boiler #4 Room 1
INTERIOR
223-07C 10/13/2016 Above Boiler #3 Room 1
223-08A 10/13/2016
Table 1 Asbestos-Containing Materials YTC_Addendum_F Page 1 Innovex Environmental Management, Inc.
Table 1 (Revised) Asbestos-Containing Materials Sample Inventory
YTC Building 223 Yakima, Washington
INTERIOR
Light Green Boiler Tank Wrap TSI White/Green Wrap ND
Gray Insulation TSI Gray Insulation ND
Light Green Boiler Tank Wrap TSI White/Green Wrap ND
Gray Insulation TSI Gray Insulation ND
Light Green Boiler Tank Wrap TSI Light Green Boiler Wrap/Mag ND
Gray Insulation TSI Gray Insulation ND
White Wrap 4-in Pipe TSI White Wrap ND
Pink Insulation TSI Pink Insulation ND
White Membrane TSI White Membrane ND
White Wrap 4-in Pipe TSI White Wrap ND
Pink Insulation TSI Pink Insulation ND
White Membrane TSI White Membrane ND
223-12A 10/13/2016 Woven Gasket East End Boiler #3 Room 1 Woven Gasket ND
223-12B 10/13/2016 Woven Gasket West End Boiler #5 Room 1 Woven Gasket ND
223-13 10/13/2016 White Wrap Surrounding 2-in Pipe East End Boiler #4 Room 1 White Wrap Surrounding 2-in Pipe 65% Chrysotile
223-18A 10/13/2016 Brown Insulation TSI East End Boiler #3 Room 1 Brown Insulation ND
223-18B 10/13/2016 Brown Insulation TSI East End Boiler #4 Room 1 Brown Insulation ND
Black rubber gasket Black non-fibrous material ND
Tan mastic Tank mastic ND
Black rubber gasket Black non-fibrous material ND
Tan mastic Tank mastic ND
223-20A 11/16/2016 Orange coating Water Tank #2 (formerly referred to as Boiler #2), beneath fiberglass insulation surrounding tank Yellow coating ND
223-20B 11/16/2016 Orange coating Water Tank #2 (formerly referred to as Boiler #2), beneath fiberglass insulation surrounding tank Orange coating ND
223-21A 11/16/2016 Brown rope gasket Boiler #3, East end surrounding hatch door Tan fiberous material ND
223-21B 11/16/2016 Brown rope gasket Boiler #3, East end surrounding hatch door Tan fiberous material ND
223-22A 11/16/2016 Black mastic Boiler #3, East end surrounding inside hatch Black mastic ND
223-22B 11/16/2016 Black mastic Boiler #3, West end surrounding inside hatch Black mastic ND
223-11B 10/13/2016
Next to Boiler #5 Room 1
223-10A 10/13/2016 West End Boiler #2 Room1
223-10B 10/13/2016 West End Boiler #2 Room1
223-10C 10/13/2016 East End Boiler #2 Room 1
223-11A 10/13/2016
Next to Boiler #5 Room 1
223-19A 11/16/2016 Water tank #2 (formerly referred to as Boiler #2), hatch opening
223-19B 11/16/2016 Water tank #2 (formerly referred to as Boiler #2), hatch opening
Table 1 Asbestos-Containing Materials YTC_Addendum_F Page 2 Innovex Environmental Management, Inc.
Table 1 (Revised) Asbestos-Containing Materials Sample Inventory
YTC Building 223 Yakima, Washington
INTERIOR
223-23A 11/16/2016 White gasket Boiler #5, West end, hatch opening White fibrous material ND
223-23B 11/16/2016 White gasket Boiler #5, West end, hatch opening White fibrous material ND
White fiberglass insulation White fiberglass insulation ND
Black mastic Black mastic ND 223-24B 11/16/2016 White fiberglass insulation Boiler #3, West end, inside hatch White fiberglass insulation ND 223-25A 11/16/2016 White mag insulation Boiler #3, West end, interior of hatch door White non-fibrous material ND 223-25B 11/16/2016 White mag insulation Boiler #3, West end, interior of hatch door White non-fibrous material ND 223-25C 11/16/2016 White mag insulation Boiler #4, West end, interior of hatch door White non-fibrous material ND
223-01C 10/13/2016 CMU and Grout West Exterior Wall CMU/Grout ND
223-14 10/13/2016 Black Asphaltic Roofing Field, Southeast Black Asphaltic Roofing ND
223-15 10/13/2016 Black Asphaltic Flashing Roof perimeter, Southeast Black Asphaltic Flashing 6% Chrysotile
223-16 10/13/2016 Black Penetration Mastic 3'x3' Raised Vent Roof, Southeast Black Penetration Mastic ND
223-17 10/13/2016 Gray Penetration Mastic 4-in Vent Pipe, Southeast Gray Penetration Mastic 10% Chrysotile
NOTES:
EPA = U.S. Environmental Protection Agency ND = not detected OSHA = Occupational Safety and Health Administration PLM = polarized light microscopy TSI = Thermal System Insulation WAC = Washington Administrative Code
EXTERIOR
ROOF
223-24A Boiler #3, West end, inside hatch
11/16/2016
CMU = cement masonry unit DOSH = Washington State Department of Occupational Safety and Health
Laboratory analyses conducted by EMSL Analytical, Inc. Seattle, WashingtonBold and shading denotes that the sample contains asbestos in quantities greater than 1% to all asbestos exposure in the workplace.
Bold denotes detectible concentrations of asbestos. Chapter 296-62 WAC, Part I-1
NESHAP = National Emission Standards for Hazardous Air Pollutants 1Analyzed by polarized light microscopy and EPA Method 600/R-93/116 ACM = Asbestos-containing material
Table 1 Asbestos-Containing Materials YTC_Addendum_F Page 3 Innovex Environmental Management, Inc.
Table 2 (Revised) Lead-Containing Paint Sample Inventory
YTC Building 223 Yakima, Washington
223-Pb-01 10/13/2016 Red/Concrete/Floor Bathroom Entrance 6.3%
223-Pb-02 10/13/2016 Gray/Metal/Boiler Panel North End Room 1 *
223-Pb-03 10/13/2016 White/Glass/Window Bathroom North Wall 0.012%
223-Pb-04 10/13/2016 White/Concrete/Column Northeast Wall Room 1 0.044%
223-Pb-05 10/13/2016 White, Gray/CMU/Wall Northeast Wall Room 1 0.22%
223-Pb-06 10/13/2016 Light Green/Boiler Wrap/Boiler Tank Boiler #2 Room 1 <LRL
223-Pb-07 10/13/2016 Dark Green/Boiler Wrap/6-in Pipe Boiler #1 Room 1 <LRL
223-Pb-08 10/13/2016 Orange/Galvanized/2-in Natural Gas Pipe Boiler #4 Room 1 14%
223-Pb-09 10/13/2016 Silver/Boiler Wrap/24-in Pipe Boiler #4 Room 1 <LRL
223-Pb-10 10/13/2016 Black/Boiler Wrap/24-in Pipe Boiler #4 Room 1 <LRL
223-Pb-12 11/16/2016 Black/Metal/Water Tank Base Water Tank #2 (formerly referred to as Boiler #2) <LRL
223-Pb-11 10/13/2016 Yellow, Gray/CMU/Exterior Wall Exterior North <LRL
<LRL
NOTES:
Laboratory analyses conducted by EMSL Analytical, Inc. Seattle, Washington CMU = Cement Masonry Unit Bold and shading denotes detectibe concentrations of lead above the laboratory reporting limit. EPA = U.S. Environmental Protection Agency
LRL = Laboratory Reporting Limit 2Chapters WAC 296-62-07521 and 296-155-176 apply to all lead worker exposures in the workplace. WAC = Washington Administrative Code
* = Insufficient amount of sample. Not analyzed. Pb = lead
< = not detected at a concentration exceeding the laboratory reporting limit
Analytical Results1 (percent by weight)
1Lead analysis by EPA SW 846 3050B/7000B
Sample ID Sample Date Paint Color/Substrate/Component Location
INTERIOR
EXTERIOR
Lead-Containing Paint2
EMSL Analytical, Inc.
3317 3rd Ave S, Suite D 2nd floor Seattle, WA 98134
Tel/Fax: (206) 269-6310 / (206) 900-8789 http://www.emsl.com / seattlelab@emsl.com
511601806EMSL Order:
Customer ID: INVX42
Customer PO:
Project ID:
Attention: Phone:Andrea Winder (425) 242-0437
Fax:Innovex Environmental Management
Received Date:16310 NE 80th St. 11/17/2016 9:20 AM
Analysis Date:Suite 300 11/21/2016
Collected Date:Redmond, WA 98052 11/16/2016
Project: YTC Building 223-Boilers and Water Tanks
Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized
Light Microscopy
Sample Description Appearance % Fibrous % Non-Fibrous
Non-Asbestos Asbestos
% Type
223-19A-Gasket
511601806-0001
None DetectedNon-fibrous (Other)100%Black
Non-Fibrous
Homogeneous
Black rubber gasket/blue caulk;
Water tank #2, hatch opening
223-19A-Mastic
511601806-0001A
None DetectedNon-fibrous (Other)100%Tan
Non-Fibrous
Homogeneous
Black rubber gasket/blue caulk;
Water tank #2, hatch opening
223-19B-Gasket
511601806-0002
None DetectedNon-fibrous (Other)100%Black
Non-Fibrous
Homogeneous
Black rubber gasket/blue caulk;
Water tank #2, hatch opening
223-19B-Mastic
511601806-0002A
None DetectedNon-fibrous (Other)100%Tan
Non-Fibrous
Homogeneous
Black rubber gasket/blue caulk;
Water tank #2, hatch opening
223-20A
511601806-0003
None DetectedNon-fibrous (Other)40%Cellulose60%Yellow
Fibrous
Homogeneous
Orange coating;
Water tank #2, beneath fiberglass insulation-covering tank
Result includes a small amount of inseparable attached material
223-20B
511601806-0004
None DetectedNon-fibrous (Other)40%Cellulose60%Orange
Fibrous
Homogeneous
Orange coating;
Water tank #2, beneath fiberglass insulation-covering tank
Result includes a small amount of inseparable attached material
223-21A
511601806-0005
None DetectedNon-fibrous (Other)10%Glass90%Tan
Fibrous
Homogeneous
Brown rope gasket;
Boiler #3, East end surrounding inside hatch
223-21B
511601806-0006
None DetectedNon-fibrous (Other)10%Glass90%Tan
Fibrous
Homogeneous
Brown rope gasket;
Boiler #3, East end surrounding inside hatch
223-22A
511601806-0007
None DetectedNon-fibrous (Other)100%Black
Non-Fibrous
Homogeneous
Black mastic; Boiler
#3, East end surrounding inside hatch
223-22B
511601806-0008
None DetectedNon-fibrous (Other)100%Black
Non-Fibrous
Homogeneous
Black mastic; Boiler
#3, West end interior coating inside hatch
223-23A
511601806-0009
None DetectedNon-fibrous (Other)60%Cellulose40%White
Fibrous
Homogeneous
White gasket; Boiler
#5, West end, hatch opening
223-23B
511601806-0010
None DetectedNon-fibrous (Other)60%Cellulose40%White
Fibrous
Homogeneous
White gasket; Boiler
#5, West end, hatch opening
Initial report from: 11/21/2016 18:39:16
Page 1 of 2ASB_PLM_0008 - 1.71 Printed: 11/21/2016 3:39 PM
Tel/Fax: (206) 269-6310 / (206) 900-8789 http://www.emsl.com / seattlelab@emsl.com
511601806EMSL Order:
Customer ID: INVX42
Customer PO:
Project ID:
Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized
Light Microscopy
Sample Description Appearance % Fibrous % Non-Fibrous
Non-Asbestos Asbestos
% Type
223-24A-Insulation
511601806-0011
None DetectedGlass100%White
Fibrous
Homogeneous
Fiberglass insulation/black mastic; Boiler #3, West end, inside hatch
223-24A-Mastic
511601806-0011A
None DetectedNon-fibrous (Other)100%Black
Non-Fibrous
Homogeneous
Fiberglass insulation/black mastic; Boiler #3, West end, inside hatch
223-24B
511601806-0012
None DetectedGlass100%White
Fibrous
Homogeneous
Fiberglass insulation/black mastic; Boiler #3, West end, inside hatch
223-25A
511601806-0013
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
White mag insulation;
Boiler #3, West end inside hatch door
223-25B
511601806-0014
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
White mag insulation;
Boiler #3, West end inside hatch door
223-25C
511601806-0015
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
White mag insulation;
Boiler #4, West end inside hatch door
Analyst(s)
Rudy Baum (10)
Rebecca Ferrell (8)
Lauren Kerber, Laboratory Manager or Other Approved Signatory
EMSL maintains liability limited to cost of analysis . This report relates only to the samples reported and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. Interpretation and use of test results are the responsibility of the client. This report must not be used by the client to claim product certification, approval, or endorsement by NVLAP, NIST or any agency of the federal government . Non-friable organically bound materials present a problem matrix and therefore EMSL recommends gravimetric reduction prior to analysis. Samples received in good condition unless otherwise noted. Estimated accuracy, precision and uncertainty data available upon request. Unless requested by the client, building materials manufactured with multiple layers (i.e. linoleum, wallboard, etc.) are reported as a single sample. Reporting limit is 1%
Samples analyzed by EMSL Analytical, Inc. Seattle, WA NVLAP Lab Code 200613
Initial report from: 11/21/2016 18:39:16
Page 2 of 2ASB_PLM_0008 - 1.71 Printed: 11/21/2016 3:39 PM
OrderID: 511601806
ConcentrationAnalyzed RDL LeadClient SampleDescription Collected
Test Report: Lead in Paint Chips by Flame AAS (SW 846 3050B/7000B)*
EMSL Analytical, Inc.
3317 3rd Ave S, Suite D 2nd floor, Seattle, WA 98134 Phone/Fax: 2062696310 / (206) 900-8789 http://www.emsl.com seattlelab@emsl.com
Attn: Andrea Winder Innovex Environmental Management 16310 NE 80th St.
Suite 300 Redmond, WA 98052
Received: 11/17/16 9:20 AM
YTC Building 223-Boilers and Water Tanks
Fax:
Phone: (425) 242-0437
Project:
11/16/2016Collected:
511601805 CustomerID: INVX42 CustomerPO:
ProjectID:
EMSL Order:
Site: Black/Metal/Water Tank Base/Water Tank #2 Base <0.050 % wt11/21/2016
511601805-0001 0.05011/16/2016223-Pb-12 % wt
Page 1 of 1Test Report PB w/RDL-7.32.3 Printed: 11/21/2016 3:10:14 PM
Lauren Kerber, Laboratory Manager or other approved signatory
*Analysis following Lead in Paint by EMSL SOP/Determination of Environmental Lead by FLAA. Reporting limit is 0.010 % wt based on the minimum sample weight per our SOP. Unless noted, results in this report are not blank corrected. This report relates only to the samples reported above and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities. Samples received in good condition unless otherwise noted. "<" (less than) result signifies that the analyte was not detected at or above the reporting limit. Measurement of uncertainty is available upon request. The QC data associated with the sample results included in this report meet the recovery and precision requirements unless specifically indicated otherwise.
Definitions of modifications are available upon request.
Samples analyzed by EMSL Analytical, Inc. Seattle, WA
Initial report from 11/21/2016 15:10:14 http://www.emsl.com mailto:seattlelab@emsl.com
OrderID: 511601805
Hazardous Materials Survey Report Joint Base Lewis-McChord (JBLM)
Building 3423
2nd Division Drive and Mastin Avenue Tacoma, Washington
November 9, 2016
Prepared For:
Fort Worth, TX 76102
Prepared By:
16310 NE 80th Street Suite 300 Redmond, WA 98052 www.innovex.net http://www.innovex.net/
Hazardous Materials Survey Report_JBLM_F i
CERTIFICATION
The technical material and data contained in this document were prepared under the supervision and direction of the undersigned, whose seal is affixed below.
Hazardous Materials Survey JBLM Building 3423 JACOBS November 9, 2016 Joint Base Lewis-McChord, Tacoma, Washington
Hazardous Materials Survey Report_JBLM_F ii
HAZARDOUS MATERIALS SURVEY
JBLM BUILDING 3423
TACOMA, WASHINGTON
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY ................................................................................................................ ES-iv
1.0 INTRODUCTION
2.0 PROPERTY DESCRIPTION
3.0 HAZARDOUS MATERIALS SURVEY
3.1 ASBESTOS-CONTAINING MATERIAL
3.1.1 Procedures and Methodology
3.1.2 Results
3.1.3 Presumed Asbestos-Containing Materials
3.2 LEAD
3.2.1 Procedures and Methodology
3.2.2 Results
3.3 POLYCHLORINATED BIPHENYLS
3.3.1 Procedures and Methodology
3.3.2 Results
3.4 MERCURY
3.5 CHLOROFLUOROCARBONS
3.6 BUILDING OCCUPANT-DERIVED WASTE
4.0 RECOMMENDATIONS
4.1 ASBESTOS
4.2 LEAD
4.3 POLYCHLORINATED BIPHENYLS
4.4 MERCURY
4.5 CHLOROFLUOROCARBONS
4.6 BUILDING OCCUPANT-DERIVED WASTE
5.0 LIMITATIONS
Hazardous Materials Survey Report_JBLM_F iii
TABLES
Table 1 Asbestos-Containing Materials Sample Inventory Table 2 Lead-Containing Paint Sample Inventory
FIGURES
Figure 1 Property Location Map Figure 2 Interior and Exterior / Asbestos and Lead Sample Locations
APPENDICES
Appendix A Photo Log Appendix B Certifications Appendix C Laboratory Analytical Reports:
EMSL Laboratory Analytical Report, 511601605 (Bulk Asbestos Materials) EMSL Laboratory Analytical Report, 091620597 (Lead Paint Chip)
Hazardous Materials Survey Report_JBLM_F iv
EXECUTIVE SUMMARY
Jacobs Engineering Group commissioned Innovex Environmental Management, Inc. to complete a hazardous materials survey for Building 3423 located at 2nd Division Drive and Mastin Avenue on Joint Base Lewis-McChord, Tacoma, Washington (the Property). The purpose of this hazardous material survey was to identify, to the extent feasible, regulated building materials that may require abatement before demolition activities. This survey included the inspection of the on- Property, 1958-vintage building (former administration building).
The survey complies with Washington State Labor and Industries good faith inspection and the Puget Sound Clean Air Agency asbestos survey requirements to determine whether materials to be worked on or removed contain hazardous materials, such as lead and/or asbestos. This document is not meant to be used as a hazardous materials specification for abatement. Any reliance on this report by a third party is at such party’s sole risk
The following regulated building materials were identified during the course of the survey.
Regulated Material Material Description Quantity Asbestos 9-in Red Vinyl Floor Tile and associated black mastic 1,400 square feet
Black/yellow mastic associated with 12-in Beige, Gray Vinyl Floor Tile
520 square feet
Gray hard window glazing 800 linear feet Lead-containing paint White paint chip on galvanized 4-in pipe located in Janitors Closet, Storage Room, Utility Room, and Men’s and Women’s Restrooms.
Brown/White/Blue paint chip on all exterior window frames and doors.
Brown is the surface paint chip.
Off White paint chip on all interior and exterior CMU walls.
Polychlorinated biphenyls
Fluorescent light ballasts “No PCB” labeling observed during the survey
Mercury Fluorescent tubes 68 tubes High Intensity Discharge bulbs 3 bulbs Mercury thermostats No thermostats were observed during the survey; however, the Utility Room was not accessed and may contain thermostats.
Chlorofluorocarbons HVAC unit No HVAC systems were observed during the survey; however, the roof was not accessed. An HVAC system may be present on the roof.
Building occupant-derived waste
Electric baseboard heaters 11 wall heaters
Access was not provided to the Utility Room or roof of the Property building. Non-destructive sampling was performed. Hidden suspect asbestos containing materials such as vermiculite may
Hazardous Materials Survey Report_JBLM_F v be present in the cement masonry walls, along with pipe insulation inside the interior walls.
Vintage-electrical wire covering was identified in the 1958-vintage building but not sampled.
This executive summary is presented solely for introductory purposes, and the information contained in this section should be used only in conjunction with the full text of this report.
Hazardous Materials Survey Report_JBLM_F Page 1 of 6
JBLM BUILDING 3423
TACOMA, WASHINGTON
1.0 INTRODUCTION
Innovex Environmental Management, Inc. (INNOVEX) has prepared this report at the request of Jacobs Engineering Group (JACOBS) to present the results of the hazardous materials survey conducted at Joint Based Lewis-McChord (JBLM) Building 3423, in Tacoma Washington (the Property). The Property location is shown on Figure 1. This survey included an inspection of the Property. The hazardous materials survey of the Property included the sampling and analysis of suspect asbestos-containing material (ACM), lead-containing components, PCB-containing light ballasts, mercury-containing light tubes, cooling systems that may contain chlorofluorocarbons (CFCs), and building occupant-derived waste (BODW).
The purpose of the hazardous materials survey was to locate and identify building materials and components at the Property that may require special handling and/or disposal during any future demolition or construction activities.
The hazardous materials survey was conducted by Ms. Andrea Winder and Ms. Cristina Tillberry, Asbestos Hazard Emergency Response Act (AHERA) Building Inspectors. In addition, Ms.
Winder is a Washington State Department of Commerce (WSDOC)-certified Lead-Based Paint Inspector, as defined in Chapter 365-230 of the Washington Administrative Code (WAC 365-230).
Copies of the AHERA and WSDOC certifications are provided in Appendix B.
This report includes inspection findings and presents the laboratory analytical results from samples collected from the Property
2.0 PROPERTY DESCRIPTION
The Property is developed with a one-story, masonry and cement-framed 1958-vintage building (former administration building) at JBLM, that covers approximately 3,040 square feet of space.
Heat was provided by electric wall heaters.
3.0 HAZARDOUS MATERIALS SURVEY
The hazardous materials survey was performed on October 20, 2016. The scope of work was conducted to meet the objectives of the hazardous materials survey included the following:
Visual inspection of the interior and exterior of the Property for the presence of suspect ACM, lead-containing paint; PCB-containing light ballasts; mercury-containing light tubes and thermostats; CFC-containing refrigerant units; and BODW.
Collection and analysis of bulk samples to confirm whether the suspect building material was asbestos-containing.
Collection and analysis of suspect lead-containing paint samples to confirm whether the associated paint contained lead.
Documentation of the number of PCB-containing light ballasts; mercury-containing fluorescent and high-intensity discharge (HID) light bulbs and thermostats; potential CFC-containing components; and BODW at the Property.
Preparation of this report.
Hazardous Materials Survey Report_JBLM_F Page 2 of 6
3.1 ASBESTOS-CONTAINING MATERIAL
INNOVEX conducted a survey for suspect ACM on the Property, which included collecting bulk samples of miscellaneous and thermal system insulation (TSI) materials, in accordance with AHERA sampling protocol (U.S. Environmental Protection Agency [EPA] 1987).
3.1.1 Procedures and Methodology
Sample locations of identified suspect ACM were chosen by the inspectors in accessible locations. The following sampling procedures were followed:
Personal protective equipment, including gloves, was donned prior to sample collection.
Sample containers were labeled with identification numbers.
Sample locations and material type were documented on a sampling data form.
Samples were extracted using a decontaminated knife or chisel to cut out or scrape off approximately 1 tablespoon of the material. When layers were present in the building material, all layers were penetrated and incorporated into each specific sample.
Each sample was placed in a resealable plastic bag, which was then sealed.
Sampling tools were decontaminated with wet wipes, and material generated during sampling was wet-wiped to remove debris.
Protective clothing, wet wipes, rags, and drop cloths were placed in a labeled plastic waste bag for disposal.
Sample bags were then placed in a large, labeled, resealable plastic bag for transport to
EMSL Analytical, Inc. (EMSL), of Seattle, Washington, a National Voluntary Laboratory Accreditation Program (NVLAP) laboratory, using chain-of-custody protocols for Bulk Asbestos Analysis by Polarized Light Microscopy, EPA Method 600/R-93/116
3.1.2 Results
INNOVEX collected a total of 41 samples of suspect ACM from the interior and exterior of the Property building. Sample locations are presented on Figure 2, and an inventory of the samples is provided in Table 1. Laboratory analytical reports are provided in Appendix C. Building materials identified as asbestos-containing include the following:
Interior
Approximately 1,400 square feet of 9-in Red Vinyl Floor Tile (VFT) and the associated black mastic (samples 3423-01A through 3423-01D) located in Rooms 1 through 3, Offices 1 through 3, and the Storage Room (Photos 2 and 3, Appendix A).
Approximately 520 square feet of black/yellow mastic associated with 12-in beige/gray VFT (sample 3423-02A) located in Halls 1 and 2 (Photo 4, Appendix A).
Exterior
Approximately 800 linear feet of gray hard window glazing (samples 3423-14A and 3423-14B) located on north, south, east and west exterior window-frames.
3.1.3 Presumed Asbestos-Containing Materials
The following building component was not tested during the survey but should be presumed to contain asbestos:
Vintage electrical wire located throughout the Property building.
Hazardous Materials Survey Report_JBLM_F Page 3 of 6
3.2 LEAD
INNOVEX conducted a survey for interior and exterior paint coatings on the Property building, which included collecting representative paint chip samples from each color and/or layer identified.
3.2.1 Procedures and Methodology
Sample locations of identified painted surfaces were chosen by the inspector in accessible locations. The following sampling procedures were followed:
Personal protective equipment, including gloves and/or protective coveralls, was donned prior to sample collections.
Sample containers were labeled with identification numbers.
Sample locations were documented on a sampling data form.
Each sample was placed in a resealable plastic bag, which was then sealed.
Protective clothing, wet wipes, rags, and drop cloths were placed in a labeled plastic waste bag for disposal.
Sample bags were then placed in a large, labeled, resealable plastic bag for transport to
EMSL, an American Industrial Hygiene Association Laboratory Accreditation Program laboratory using chain-of-custody protocols for submitting and analyzing lead by EPA Method
SW 846 3050B/7000B.
3.2.2 Results
Seven paint chip samples were collected from representative interior and exterior painted surfaces on the Property building. An inventory of the samples is provided in Table 2; sample locations are presented on Figure 2. Laboratory analytical reports are provided in Appendix C.
The following samples were identified as lead-containing:
White/Galvanized/4-in Pipe (sample 3423-Pb-04) located in the Janitors Closet, Storage
Room, Utility Room, and Men’s and Women’s Restrooms (Photo 5, Appendix A).
Brown, White, Blue/Wood/Window Frame (sample 3423-Pb-06) located on all exterior window frames and doors. Brown paint chip is the surface layer (Photo 6, Appendix A).
Off White/CMU/Wall (sample 3423-Pb-07) located on all interior and exterior CMU walls
(Photo 6, Appendix A).
3.3 POLYCHLORINATED BIPHENYLS
Suspect PCB-containing light ballasts were inspected from the interior of the Property building.
3.3.1 Procedures and Methodology
Representative fluorescent light fixtures were observed for suspect PCB-containing ballasts. The following inspection procedures were followed.
Personal protective equipment, including gloves, was donned prior to ballast inspection.
Electrical power was disconnected at the light fixtures prior to inspecting the ballasts.
Fluorescent light tubes were removed from the fixtures after which the light fixture covers were removed.
Hazardous Materials Survey Report_JBLM_F Page 4 of 6
Representative fluorescent light ballasts were inspected for “No PCBs” labeling.
Light fixture covers and tubes were reconnected to the fluorescent light fixtures after inspection.
3.3.2 Results
All representative fluorescent light ballasts inspected for PCB labeling in the Property building were branded with “No PCBs” labeling.
3.4 MERCURY
Fluorescent and HID light tubes, which may contain mercury, were inventoried during the survey.
INNOVEX personnel counted 68 fluorescent and three HID light tubes at the Property. The specific number and locations of the fluorescent and HID light tubes were as follows:
Room 1—Twelve fluorescent light tubes were identified.
Room 2—Four fluorescent light tubes were identified.
Room 3—Four fluorescent light tubes were identified.
Office 1—Four fluorescent light tubes were identified.
Office 2—Four fluorescent light tubes were identified.
Office 3—Four fluorescent light tubes were identified.
Women’s Restroom (WRR)—Two fluorescent light tubes were identified.
Men’s Restroom (MRR)—Two fluorescent light tubes were identified.
Storage Room—Two fluorescent light tubes were identified.
Janitors Closet—Fourteen fluorescent light tubes were identified.
Hall 1—Eight fluorescent light tubes were identified.
Hall 2—Eight fluorescent light tubes were identified.
Exterior Door to Utility Room—One HID light tube was identified (Photo 7, Appendix A) West Exterior Wall—Two HID light tubes were identified (Photo 1, Appendix A)
No mercury-containing thermostats were observed at the Property during the survey; however, the Utility Room was not accessed and may contain mercury-containing thermostats.
3.5 CHLOROFLUOROCARBONS
No HVAC units were observed at the Property during the survey; however, the roof was not accessed and may contain HVAC units that may contain refrigerant.
3.6 BUILDING OCCUPANT-DERIVED WASTE
Hazardous material associated with building occupant activities was observed in the Property building during the survey. The readily identifiable hazardous waste item noted during the survey included 11 electric baseboard heaters in Rooms 1, 2, and 3; Offices 1, 2, and 3; Storage Room;
Men’s and Women’s Restrooms; and, Halls 1 and 2.
Hazardous Materials Survey Report_JBLM_F Page 5 of 6
4.0 RECOMMENDATIONS
Based on the information gathered during the hazardous materials survey, INNOVEX makes the following recommendations.
4.1 ASBESTOS
Planning and coordination of ACM removal should begin prior to renovation and/or demolition activities. The ACM identified in this report should be removed by certified, trained, and protected personnel using appropriate work practices and engineering controls prior to disturbance by renovation or demolition, as outlined in WAC 296-2, I-1.
Any additional, previously unsampled, suspect materials encountered during renovation and/or demolition activities should be sampled by a certified AHERA Building Inspector and analyzed by a NVLAP-accredited laboratory to evaluate asbestos content prior to disturbing the material.
4.2 LEAD
A representative sample of the demolition waste associated with samples 3423-Pb-04, 3423-Pb- 06, and 3423-Pb-07, each of which contained elevated concentrations of lead, should be collected and analyzed using a toxicity characteristic leaching procedure (TCLP) to characterize the waste for disposal. Demolition waste streams with leachable lead concentrations exceeding 5.0 milligrams per liter when prepared for analysis using the TCLP method are considered hazardous and require special handling according to federal and state regulations, including 40 CFR 247.
Any contractor who may come in contact with materials containing lead at any detectable concentration is required to address worker exposure responsibilities as outlined in WAC 296- 155-176.
Should additional, previously unsampled, painted surfaces be revealed through renovation and/or demolition activities, INNOVEX recommends the coatings be sampled by a WSDOC-certified inspector and analyzed to evaluate lead content prior to destruction, removal, or personnel exposure.
4.3 POLYCHLORINATED BIPHENYLS
During demolition activities, any light ballast without “No PCBs” labeling should be handled and disposed of according to state and federal regulations (i.e., workers should employ proper personal protective equipment when handling the ballasts and properly store the ballasts in sealed plastic bags or buckets to minimize potential contact with any exposed or leaking PCB-containing oil). All PCB waste must be labeled, manifested, transported, and disposed of according to federal and state regulations, including 40 CFR 761.
4.4 MERCURY
Fluorescent and HID light tubes may contain mercury vapors. These tubes and mercury-containing heat thermostats should be removed without breakage and disposed of property in accordance with WAC 173-303-573, the Standards for Universal Waste Management.
Hazardous Materials Survey Report_JBLM_F Page 6 of 6
4.5 CHLOROFLUOROCARBONS
During demolition activities, HVAC systems should be evacuated of refrigerant prior to being impacted by demolition activities. Any discharge of spent CFCs to the environment constitutes disposal and is subject to full regulation under WAC 173-303, Dangerous Waste Regulations. All refrigerant must be properly transported, recycled, and reclaimed in accordance with all applicable federal, state, and local regulations by an authorized hazardous waste handler.
4.6 BUILDING OCCUPANT-DERIVED WASTE
During demolition activities, any BODW identified should be separated from the general demolition waste stream, transported by an authorized hazardous materials transporter, and disposed of at an authorized waste facility.
5.0 LIMITATIONS
The services described in this report were performed consistent with generally accepted professional consulting principles and practices. No other warranty, expressed or implied, is made. These services were performed consistent with our current consulting agreement with the client. This report is solely for the use and information of our client unless otherwise noted. Any reliance on this report by a third party is at such party’s sole risk.
INNOVEX was not provided access to the Utility Room or the roof. The Utility Room was locked at the time of the survey. Manuel Camacho (JBLM, Maintenance) was contacted during the survey to access the Utility Room and the roof. According to Mr. Camacho, the lock on the Utility Room door was stuck in-place and was inaccessible. INNOVEX was subsequently unable to sample suspect ACM in the Utility Room (Photo 8, Appendix A). Mr. Camacho was also unable to locate a ladder to access the roof and the inclement weather outside prevented safe access to the roof.
INNOVEX was subsequently unable to sample suspect ACM on the roof.
INNOVEX performed non-destructive sampling of suspect ACM, per the request of Mr. Camacho.
INNOVEX was therefore unable to access inside the wall cavities inspecting for suspect ACM.
Hidden suspect ACM such as vermiculite may be present in the cement masonry walls, along with insulation piping inside the interior walls.
Opinions and recommendations contained in this report apply to conditions existing when services were performed and are intended only for the client, purposes, locations, time frames, and project parameters indicated. INNOVEX is not responsible for the impacts of any changes in environmental standards, practices, or regulations subsequent to performance of services.
INNOVEX does not warrant the accuracy of information supplied by others or the use of segregated portions of this report.
Table 1: Asbestos-Containing Material Sample Inventory
9-in Red VFT Red Floor Tile 5% Chrysotile
Black Mastic Black Mastic 8% Chrysotile
9-in Red VFT Red Floor Tile 5% Chrysotile
Black Mastic Black Mastic 2% Chrysotile
9-in Red VFT Red Floor Tile 5% Chrysotile
Black Mastic Black Mastic 8% Chrysotile
Yellow Mastic Yellow Mastic ND
9-in Red VFT Red Floor Tile 5% Chrysotile
Mastic Black Mastic 8% Chrysotile
12-in Beige, Gray VFT Beige/Gray Floor Tile ND
Black/Yellow Mastic Black/Yellow Mastic 2% Chrysotile
12-in Beige, Gray VFT Beige/Gray Floor Tile ND
Yellow Mastic Yellow Mastic ND
White Caulk White Caulk ND
3423-03A 10/20/2016 Green Multi-shape Ceramic Floor Tile Grout WRR Center Floor Gray Grout ND
3423-03B 10/20/2016 Green Multi-shape Ceramic Floor Tile Grout MRR Center Floor Gray Grout ND
3423-04A 10/20/2016 4-in Green Ceramic Wall Tile Grout WRR Doorway Wall Gray Grout ND
3423-04B 10/20/2016 4-in Green Ceramic Wall Tile Grout MRR Doorway Wall Gray Grout ND
Red Carpet Red/Black Carpet ND
Yellow Mastic Yellow Mastic ND
Red Carpet Red/Black Carpet ND
Yellow Mastic Yellow Mastic ND
Blue Carpet Blue Carpet ND
Yellow Mastic Yellow Mastic ND
Blue Carpet Blue Carpet ND
Yellow Mastic Yellow Mastic ND
4-in Black CB Black Cove Base ND
White Mastic White Mastic ND
4-in Black CB Black Cove Base ND
White Mastic White Mastic ND
4-in Blue CB Blue Cove Base ND
White Mastic White Mastic ND
4-in Blue CB Blue Cove Base ND
White Mastic White Mastic ND
3423-05B 10/20/2016 Room 1 Center
3423-02B 10/20/2016 Hall 1 Janitor Closet Doorway
Table 1 Asbestos-Containing Materials Sample Inventory
JBLM Building 3423 Tacoma, Washington
3423-05A 10/20/2016 Room 1 Adj. Hall 2
3423-01D 10/20/2016 Room 1 Adj. Hall 2 Beneath Red Cpt
3423-02A 10/20/2016
Hall 2 Adj. Office 3
INTERIOR
3423-01A 10/20/2016 Storage Room Doorway Beneath Blue Cpt
3423-01B 10/20/2016 Office 2 Beneath Blue Cpt
3423-01C 10/20/2016 Room 1 Adj. Hall 1 Beneath Red Cpt
10/20/2016 Office 3 Doorway
3423-06B 10/20/2016 Office 1 Doorway
3423-06A
3423-07A 10/20/2016 Hall 2 Adj. Office 1
3423-07B 10/20/2016 Hall 1 Adj. Room 1
3423-08A 10/20/2016 Office 2 Doorway
3423-08B 10/20/2016 Office 1 Doorway
Table 1 Asbestos-Containing Materials JBLM_F Page 1 Innovex Environmental Management, Inc.
Table 1 Asbestos-Containing Materials Sample Inventory
JBLM Building 3423 Tacoma, Washington
INTERIOR
3423-09A 10/20/2016 GWB Room 1 South Wall White GWB ND
3423-09B 10/20/2016 GWB Room 2 North Wall White GWB ND
3423-09C 10/20/2016 GWB Room 3 North Wall White GWB ND
GWB Drywall ND
White Caulk Caulk ND
3423-09E 10/20/2016 GWB Room 1 Northeast Wall White GWB ND
3423-10C 10/20/2016 CMU and Grout Office 1 East Wall Gray Grout ND
3423-10D 10/20/2016 CMU and Grout Hall 2 Between Office 2 & 3 Gray Grout ND
3423-10E 10/20/2016 CMU and Grout Hall 1 Between Storage & Janitor Closet Gray Grout ND
3423-11A 10/20/2016 2'x4' Drop Ceiling Tile, Wormhole Office 1 Center Tan Ceiling Tile ND
3423-11B 10/20/2016 2'x4' Drop Ceiling Tile, Wormhole Office 3 Center Tan Ceiling Tile ND
3423-12A 10/20/2016 12-in Cork Ceiling Tile Office 2 Above Drop Ceiling Tan Ceiling Tile ND
3423-12B 10/20/2016 12-in Cork Ceiling Tile Room 2 Above Drop Ceiling Tan/White/Yellow Ceiling Tile ND
3423-13A 10/20/2016 4-in Pipe Elbow TSI Janitor Closet White/Yellow Insulation ND
3423-13B 10/20/2016 4-in Pipe Elbow TSI Storage Room White/Yellow Insulation ND 3423-13C 10/20/2016 4-in Pipe Elbow TSI Storage Room White/Yellow Insulation ND
3423-10A 10/20/2016 CMU and Grout South Exterior Wall Gray Grout ND 3423-10B 10/20/2016 CMU and Grout East Exterior Wall Gray Grout ND 3423-14A 10/20/2016 Gray Hard Window Glazing East Exterior Wall Gray Hard Window Glazing 3% Chrysotile 3423-14B 10/20/2016 Gray Hard Window Glazing West Exterior Wall Gray Hard Window Glazing 3% Chrysotile 3423-15A 10/20/2016 Gray Soft Window Glazing East Exterior Wall Gray Soft Window Glazing ND 3423-15B 10/20/2016 Gray Soft Window Glazing West Exterior Wall Gray Soft Window Glazing ND 3423-16A 10/20/2016 White Soft Window Glazing East Exterior Wall White Soft Window Glazing ND 3423-16B 10/20/2016 White Soft Window Glazing West Exterior Wall White Soft Window Glazing ND
NOTES:
GWB = Gypsum Wallboard
MRR = Men's Restroom
ND = not detected
OSHA = Occupational Safety and Health Administration
PLM = polarized light microscopy
TSI = Thermal System Insulation
VFT = Vinyl Floor Tile
WAC = Washington Administrative Code
WRR = Women's Restroom
NESHAP = National Emission Standards for Hazardous Air Pollutants
CB = cove base
EPA = U.S. Environmental Protection Agency
ACM = Asbestos-Containing Material
DOSH = Washington State Department of Occupational Safety and Health
CMU = cement masonry unit
Bold denotes detectible concentrations of asbestos. Chapter 296-62 WAC, Part I-1 applies to all asbestos exposure in the workplace.
Laboratory analyses conducted by EMSL Analytical, Inc. Seattle, Washington
Bold and shading denotes that the sample contains asbestos in quantities greater than 1%
1Analyzed by polarized light microscopy using EPA Method 600/R-93/116
Hall 2 Northeast Wall
EXTERIOR
3423-09D 10/20/2016
Table 1 Asbestos-Containing Materials JBLM_F Page 2 Innovex Environmental Management, Inc.
Table 2: Lead-Containing Paint Sample Inventory
Sample ID Sample Date Paint Color/Substrate/Component Location Analytical Results1
(percent by weight)
3423-Pb-01 10/20/2016 Gray/GWB/Wall Room 1 Northeast <LRL
3423-Pb-02 10/20/2016 Red/GWB/Wall Room 2 Northwest <LRL
3423-Pb-03 10/20/2016 Gray/CMU/Wall Room 3 East <LRL
3423-Pb-04 10/20/2016 White/Galvanized/4-in Pipe Janitor Closet 0.12%
3423-Pb-05 10/20/2016 Brown/Wood/Door Frame Hall 1 WRR Doorway <LRL
3423-Pb-06 10/20/2016 Brown, White, Blue/Wood/Window Frame Exterior Northeast 0.76%
3423-Pb-07 10/20/2016 Off white/CMU/Wall Exterior South 0.028%
<LRL
Laboratory analyses conducted by EMSL Analytical, Inc. Seattle, Washington EPA = U.S. Environmental Protection Agency Bold and shading denotes detectibe concentrations of lead above the laboratory reporting limit. GWB = Gypsum Wallboard
LRL = Laboratory Reporting Limit 2Chapters WAC 296-62-07521 and 296-155-176 apply to all lead worker exposures in the workplace. Pb = Lead
WAC = Washington Administrative Code
WRR = Womens RestroomCMU = Cement Masonry Unit
Table 2 Lead-Containing Paint Sample Inventory
JBLM Building 3423 Tacoma, Washington
INTERIOR
EXTERIOR
Lead-Containng Paint 2
< = not detected at a concentration exceeding the laboratory reporting limit
1Lead analysis by EPA SW 846 3050B/7000B
NOTES:
Table 2 Lead-Based Paint JBLM_F Page 1 Innovex Environmental Management, Inc.
Figure 1: Project Location Map
November 2, 2016
DRAWN BY
DESIGNED BY
16310 NE 80th St., Suite 300
Redmond, WA 98052
(800) 988-7880
Andrea Winder
Innovex Environmental
ICD
FIGURE 1
Property Location Map
LATTITUDE 47D 04M 32S NORTH
LONGITUDE 122D 34M 18S WEST
US GEOLOGICAL SURVEY - 2014
7.5 MINUTE QUADRANGLE MAP
FORT LEWIS, WASHINGTON
BUILDING 3423
JOINT-BASE LEWIS MCCHORD
TACOMA, WASHINGTON
PROPERTY LOCATION
Figure 2: Interior and Exterior / Asbestos and Lead Sample Locations
FIGURE 2
Interior and Exterior/
Asbestos and Lead Sample
Locations
BUILDING 3423
JOINT-BASE LEWIS MCCHORD
TACOMA, WASHINGTON
November 2, 2016
DRAWN BY
DESIGNED BY
16310 NE 80th St., Suite 300
Redmond, WA 98052
(800) 988-7880
Andrea Winder
Innovex Environmental
ICD
LEGEND
APPENDIX A
PHOTO LOG
INNOVEX ENVIRONMENTAL MANAGEMENT
Client: Jacobs Engineering Group Site Name: JBLM Building 3423 Photographer: Andrea Winder
PHOTO 1
View of the…