B.01.01_-_ABSTRACT.pdf
PDF 14 KB Posted
- Attached to
- Albeni Falls Dam Spillway Modification, Spillway Deicing Federal contract opportunity
- Solicitation number
- W912DW-16-B-0010
About this file
Abstract for bids read on 18 July 2016
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| R0002.pdf | ||
| R0002.pdf | ||
| R0001.pdf | ||
| 16B0010.PDF | ||
| P2-371437_AFSD-00-COMPILATION-100_RTA.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION
1. Solicitation No.
2. Date Issued:
3. Date Opened:
4. Issuing Office:
Department of the Army Corps of Engineers, Seattle District P.O. Box 3755 Seattle, WA 98124-2255
5. Project Title:
Unrestricted
6. Number of Amendments Issued: 2
1st Apparent low = IMCO $799,000.00
% Difference From GE: 34%
2nd Apparent low = RSCI $1,174,200.00
% Difference From GE: 97%
3rd Apparent low = BriVo $1,260,849.00
% Difference From GE: 111%
SIGNATURE: Bid Opening Officer: Sara Edwards
AFD Spillway Modifications Spillway Deicing, Avbeni Falls Dam, ID
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
8. GOVERNMENT ESTIMATE
(Check A, B or C and Complete D, E F) A. Hired Labor B. Reasonable Contract (w/out profit) XX C. Reasonable Contract (w/ profit)
7A. ITEM 7B. DESCRIPTION OF OFFERED ITEM 7C. EST 7D. UNIT 7E. UNIT 7F. AMOUNT
NUMBER QTY PRICE
BASE ITEMS
0001 Mobilization and Demobilization 1 Job 72,799.00$ 72,799.00$
Remove Existing Electrical Feeder from Diesel Room to the Five Control Panels 1 Job 2,105.00$ 2,105.00$
Furnish, Install, and Test 2 New Electrical feeders 1 Job 46,925.00$ 46,925.00$
Furnish, Install, and Test New Compressed Air Piping from Diesel Room to the First Air Bubbler Outlet 1 Job 21,271.00$ 21,271.00$
Furnish, Install, and Test 39 New Air Bubbler Outlets 1 Job 38,453.00$ 38,453.00$
Furnish, Install, and Test New Seal System for each of the 10 Spillway Gates’ Upper Leaves 1 Job 98,387.00$ 98,387.00$
Furnish, Install, and Test New Control and Power Wiring for the Seal Heater Systems 1 Job 147,118.00$ 147,118.00$
Furnish, Install, and Test New High Pressure Water Pipeline from the Standby Generator Room the length of the spillway to the start of Spill Bay 1 1 Job 41,617.00$ 41,617.00$
Furnish, Install, and Test New Portable Hot Water Pressure Washer, and Necessary
Equipment and Flexible Hosing to connect to the water pipeline running the length of the spillway 1 Job 19,617.00$ 19,617.00$
Furnish, Install, and Test New Prototype hot Water Pressure Washing System in Spill Bay 10 consisting of piping and hot water nozzles to spray the gate seals. 1 Job 21,402.00$ 21,402.00$
0011 Furnish O&M Manuals 1 Job 50,000.00$ 50,000.00$ 0012 Furnish As-Built Drawings 1 Job 20,000.00$ 20,000.00$
0013 Furnish Training of Government Personnel 1 Job 17,257.00$ 17,257.00$ 0014 Furnish Spare Parts and Accessories 1 Job -$ -$
596,951.00$ TOTAL BASE & OPTIONAL
9. OFFERS
NO. 1 RSCI NO. 2 NO. 3
A. Boise, ID 83706 A. BriVo Corporation A. IMCO General Construction, Inc
Cheney, WA 99004 Ferndale, WA 98248
B. Bid Security Type/Amt : 20% Bid Bond B. Bid Security Type/Amt : 20% Bid Bond B. Bid Security Type/Amt : 20% Bid Bond Business Size: Size here Business Size: Size here Business Size: Size here
C. Amendments Acknowledged: Number acknowledged C. Amendments Acknowledged: number ack C. Amendments Acknowledged: number ack
D. ITEM 7C. ESTE. UNIT F. AMOUNT D. ITEM 7C. EST E. UNIT F. AMOUNT D. ITEM 7C. EST E. UNIT F. AMOUNT
NO. QTY PRICE NO. QTY PRICE NO. QTY PRICE
BASE
ITEMS BASE ITEMS BASE ITEMS
0001 1 46,400.00$ 46,400.00$ 0001 1 196,366.00$ 196,366.00$ 0001 1 125,000.00$ 125,000.00$ 0002 1 8,900.00$ 8,900.00$ 0002 1 36,883.00$ 36,883.00$ 0002 1 3,000.00$ 3,000.00$ 0003 1 76,900.00$ 76,900.00$ 0003 1 132,006.00$ 132,006.00$ 0003 1 100,000.00$ 100,000.00$ 0004 1 36,200.00$ 36,200.00$ 0004 1 107,991.00$ 107,991.00$ 0004 1 50,000.00$ 50,000.00$ 0005 1 60,800.00$ 60,800.00$ 0005 1 87,702.00$ 87,702.00$ 0005 1 55,000.00$ 55,000.00$ 0006 1 386,400.00$ 386,400.00$ 0006 1 148,371.00$ 148,371.00$ 0006 1 179,000.00$ 179,000.00$ 0007 1 261,400.00$ 261,400.00$ 0007 1 157,315.00$ 157,315.00$ 0007 1 115,000.00$ 115,000.00$ 0008 1 85,000.00$ 85,000.00$ 0008 1 99,079.00$ 99,079.00$ 0008 1 55,000.00$ 55,000.00$ 0009 1 19,400.00$ 19,400.00$ 0009 1 51,870.00$ 51,870.00$ 0009 1 25,000.00$ 25,000.00$ 0010 1 111,200.00$ 111,200.00$ 0010 1 142,920.00$ 142,920.00$ 0010 1 20,000.00$ 20,000.00$ 0011 1 50,000.00$ 50,000.00$ 0011 1 50,000.00$ 50,000.00$ 0011 1 50,000.00$ 50,000.00$ 0012 1 20,000.00$ 20,000.00$ 0012 1 20,000.00$ 20,000.00$ 0012 1 20,000.00$ 20,000.00$ 0013 1 11,600.00$ 11,600.00$ 0013 1 30,346.00$ 30,346.00$ 0013 1 2,000.00$ 2,000.00$ 0014 -$ 0014 -$ 0014 -$
TOTAL BASE ITEMS 1,174,200.00$ TOTAL BASE ITEMS 1,260,849.00$ TOTAL BASE ITEMS 799,000.00$
File details come from the government source that posted it. Updated .