W912DS27S0006.pdf
PDF 267 KB Posted
- Solicitation number
- W912DS27S0006
- Issued by
- Nassau County, New York
About this file
This Request for Information (RFI) is issued by the U.S. Army Corps of Engineers, New York District, on behalf of the United States Merchant Marine Academy (USMMA) for a Design-Build Single Award Task Order Contract (SATOC) to rehabilitate approximately 2,800 linear feet of seawall at the USMMA campus in Kings Point, New York. The project scope encompasses advancing a government-furnished 35% design to 100% completion across nine distinct segments, obtaining all required federal, state, and local permits, and reconstructing the degraded seawall with varying construction types including timber bulkheads, steel sheet pile structures, and concrete walls. The RFI was published November 12, 2026, with responses due by December 4, 2026, at 4:00 AM EST. This market research solicitation is for information purposes only and does not constitute a binding commitment; the Government intends to issue a formal Request for Proposals in Spring 2027, with construction anticipated to commence in early 2028. The SATOC will operate as an Indefinite Delivery/Indefinite Quantity contract with an estimated total capacity of $70,000,000 over a five-year period, with individual task orders anticipated to range from $10,000,000 to $25,000,000.
The procurement is classified under NAICS code 237990 (Other Heavy and Civil Engineering Construction) with a small business size standard of $45 million. All work must comply with the USMMA Campus Design Guide, Engineering Design Standards, International Building Code (IBC), GSA standards, and Department of Defense Unified Facilities Criteria (UFC). The Government is seeking information regarding contractor interest, capabilities, and qualifications to perform the design-build work and has requested responses limited to five pages in PDF format addressing sixteen substantive questions concerning coastal engineering experience, geotechnical capabilities, permitting expertise with Clean Water Act Section 401 and Section 404 requirements, marine construction equipment and staging strategies, numerical modeling capabilities, and anticipated technical and schedule risks. No set-asides are designated for this opportunity. Responses should be submitted via email to Contract Specialist Mohenda Surage at mohenda.r.surage@usace.army.mil or Project Manager Richard Gussenhoven at Richard.Gussenhoven@usace.army.mil at the USACE New York District Contracting Division located at 26 Federal Plaza, Room 1630, New York, New York 10278-0004.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
An official website of the United States government Here’s how you know
Home Search Data Bank Data Services Help
Contract Opportunity
Version Current Record
Classification
Description
Contact Information
Attachments/Links
Pre-Award
Solicitation Details
Opportunity
RFI USMMA Campus Modernization Program SATOC Seawall Project
Active
Notice ID W912D S27S00
Related Notice (blank)
Contract Opportunity Type Sources Sought
Inactive Dates Nov 12, Inactive Policy Manual
Response Date Dec 04, 4:00 AM
EST
Published Date Nov 12, 3:19 PM
EST
Department/Ind. Agency
DEPT OF DEFENSE
https://sam.gov/ https://sam.gov/ https://sam.gov/ https://sam.gov/search/ https://sam.gov/reports/awards/standard https://sam.gov/data-services https://sam.gov/help javascript:void(0) javascript:void(0);
javascript:void(0);
javascript:void(0);
javascript:void(0);
javascript:void(0);
javascript:void(0);
Classification
Description
Sub-tier
DEPT OF THE ARMY
Major Command
US ARMY CORPS OF
ENGINEERS
Sub Command 1, 2, 3
ENGINEER DIVISION NORTH ATLANTIC
ENDIST NEW YORK
Office
W2SD ENDIST NEW YORK
Original Set Aside (blank)
Product Service Code
Y1PZ -
CONST
RUCTIO
N OF
OTHER
NON-
BUILDI
NG
FACILIT
IES
NAICS
Code 237990
- Other Heavy and Civil Enginee ring Constru ction
Place of Performance United States Merchant Marine Academy, Kings Point, NY
Initiative None
THIS IS A REQUEST FOR INFORMATION
ANNOUNCEMENT ONLY
This announcement is issued solely for market research purposes in accordance with Revolutionary FAR Overhaul (RFO) Part 10, Market Research. The U.S. Army Corps of Engineers (USACE), New York District, is seeking information regarding the interest, capability, and qualifications of firms that may be capable of performing the require-ment described below.
This RFI is for planning and informational purposes only. It does not constitute a so-licitation, Request for Proposals (RFP), Invitation for Bids (IFB), or commitment by the Government to issue a solicitation or award a contract. Responses to this RFI are not offers and cannot be accepted by the Government to form a binding contract.
The Government will not pay for, reim-burse, or otherwise compensate respon-dents for costs associated with preparing or submitting information in response to this RFI. The Government does not intend to rank submissions or provide individual re-sponses to interested firms. Information submitted and clearly marked as “Proprietary” will be handled accordingly.
The U.S. Army Corps of Engineers, New York District is issuing this Request for Information (RFI) for an Indefinite Delivery/Indefinite Quantity, Single Award Task Order Contract (SATOC) to determine interest, capabilities, and qualifications to for Design-Build contractors. The NAICS codes for this procurement is 237990, Size Standard is $45 Million. The Request for Proposals is planned to be issued in the Spring of 2027 with construction to begin early in 2028. The estimated SATOC capac-ity is $70,000,000 with the anticipated Task Order magnitude between $10,000,000 and $25,000,000. Work under this contract is ex-pected to begin in winter of 2028.
The SATOC will be for contractor to replace/restore 2,800-foot seawall at the United States Merchant Marine Academy, Kings Point, NY. The project will be con-structed within the access-controlled instal-lation along the waterfront of the United States Merchant Marine Academy. Adjacent facilities will remain occupied during con-struction with minimal disruption to opera-tions requiring precise construction plan-ning. Work for this project is described below:
1. Project Purpose and Program Context USACE and USMMA have undertaken an agreement to modernize the campus in its entirety providing upgraded Barracks, Academic Buildings, Training Buildings, Athletic Facilities and Waterfront Spaces.
The Seawall will serve to protect critical land side facilities essential to the educa-tion and training of Midshipmen from storm, wave action, and tidal erosion.
2. Existing Conditions The existing seawall along the United States Merchant Marine Academy (USMMA) cam-pus shoreline extends approximately 2,800 linear feet and is aligned generally north– south along the western waterfront. The seawall exhibits significant variability in height, construction type and functional purpose along with its length.
At the northern end (north of Hague Basin), the shoreline protection system transitions through several construction types in se-quence: beginning with a timber (wooden) bulkhead, followed by a stone and mortar wall, then reverting to a timber bulkhead and transitioning to a steel sheet pile bulk-head with a concrete cap. (See Attachment - USMMA Seawall Site Map)
Within the Hague Basin, the shoreline struc-tures consist primarily of steel sheet pile bulkheads and stone façade walls. Presume the stone façade walls incorporate a con-crete core based on visual assessment.
South of Hague Basin, the shoreline is pre-dominantly stabilized by a concrete seawall with riprap protection, which further transi-tions to cast-in-place (poured) concrete only toward the southern extent. The southernmost seawall segment, segment 9, includes stabilizing the adjacent slope to address its instability, mitigate further ero-sion, and support a future 12 ft. wide roadway/walkway to connect existing roads on campus.
3. Design and Construction Scope This project will rehabilitate/restore 2,800-feet of seawall at the United States Merchant Marine Academy. The scope in-cludes progressing the government pro-vided 35% design consisting of nine seg-ments to 100% Design, completing all re-quired permitting documents, reconstruct-ing the seawall, and restoring the waterfront.
The contractor will review, validate, and ad-vance the government-furnished 35% Design RFP package to 65% and 100% Issued for Construction (IFC) submittals across civil, structural, coastal, and geotechnical disciplines. Following design finalization for a segment construction will commence to remove and/or restore the degraded segment of seawall.
The contractor will be required to complete the work in accordance with all required permits, certifications and licenses required by Federal, State, and local law for the exe-cution of this work.
4. Design Standards and Performance Requirements
All work will meet the USMMA Campus Design Guide and Engineering Design Standards which contain DOT standards in-cluding the International Building Code (IBC), GSA standards, and DoD Unified Facilities Criteria (UFC).
5. Acquisition Strategy and Contracting Approach The Government intends to establish a Design-Build (D-B) Single Award Task Order Contract (SATOC) Indefinite-Delivery, Indefinite-Quantity (IDIQ) contract with a total contract capacity of $70,000,000 over an anticipated five-year ordering period.
INFORMATION REQUESTED FROM
RESPONDENTS
Areas of particular interest to the govern-ment are responses to the following ques-tions:
1) Is your firm interested in competing for this project? If so, do you anticipate propos-ing as an integrated prime contractor/Designer of Record (DOR) team, a joint venture (JV), or a prime construction contractor with a subcontracted design firm?
2) Based on the anticipated scope (steel sheet pile, bulkhead replacement, concrete seawall replacement, splash pads, and drainage system replacement), what per-centage of the construction work do you anticipate self-performing with your own labor and equipment versus subcontracting?
3) Describe your teams experience over the past 5–10 years designing and constructing coastal infrastructure or shoreline stabiliza-tion projects of similar scale (exceeding 2,000 linear feet) or projects involving mul-tiple, distinct structural wall types within a single contract.
4) What is the largest existing bulkhead or seawall replacement contract (by total dol-lar value and approximate linear footage) that your firm has completed as the prime contractor and/or Designer of Record?
(Please specify whether each project was ex-ecuted as Design-Build or Design-Bid-Build).
5) In a Design-Build delivery model, how would your team approach executing in-water geotechnical borings in tidal Long Island Sound conditions? Do you possess the in-house marine equipment and per-sonnel to perform this subsurface investiga-tion, or would you subcontract it to a spe-cialized marine geotechnical firm?
6) Given that the 2,800-foot seawall is di-vided into 9 distinct segments with varying construction types (e.g., sheet pile, gravity wall, revetment), what specific technical challenges or efficiencies do you foresee in transitioning between these different wall typologies?
7) Describe your experience obtaining and/or working in compliance with Clean Water Act Section 401 Water Quality Certifications through the New York State Department of Environmental Conservation (NYSDEC) and Section 404 permits through USACE Regulatory, including managing de-sign and construction schedules around Long Island Sound tidal and seasonal in-water work windows. What other permits would you anticipate on this project?
8) To minimize shoreline exposure, tidal vulnerability, and site disruption, would you recommend designing and construct-ing the 9 segments sequentially, concur-rently in clusters, or prioritized by existing structural degradation? Based on your rec-ommended approach, what is your esti-mated overall duration (broken down by design/permitting vs. construction)?
9) Considering the varying geometry and coastal exposure of the 9 segments along Long Island Sound, do you anticipate utiliz-ing land-based equipment, marine-based barges/vessels, or a hybrid approach for de-molition, material delivery, and staging?
What specific site access, staging, or upland constraints should the Government clarify or address in the Design-Build Request for Proposal (RFP)?
10) Describe your team’s in-house or sub-consultant capabilities to perform ad-vanced coastal engineering and numerical modeling, including nearshore wave trans-formation, wave overtopping, toe scour, and sea-level change lifecycle analysis.
Which specific modeling tools or field mea-surements (e.g., spectral wave models such as SWAN/STWAVE, Boussinesq models, or Acoustic Doppler Current Profiler [ADCP] current measurements) do you anticipate needing to support final design?
11) Describe your team’s experience man-aging complex marine geotechnical risks along Long Island Sound or similar coastal environments, specifically regarding Soil- Structure Interaction (SSI) modeling, lateral earth/hydrostatic loading, and global slope stability analysis in soft, saturated marine sediments or variable glacial till strata.
12) Based on your experience with coastal Design-Build solicitations, what specific baseline coastal, hydrographic, and geotechnical data (e.g., historical storm surge/water-level statistics, offshore wave hindcast data, recent bathymetric/topographic surveys, or pre-liminary boring logs) do you expect the Government to provide in the 35% RFP package so that your team can accurately price and propose on the project?
13) Assuming the Government provides re-gional water-level statistics and baseline offshore wave data in the 35% RFP, what site-specific numerical modeling (e.g., nearshore wave transformation, EurOtop wave overtopping, localized toe-scour analysis, or USACE Sea Level Change pro-jections) would your team anticipate exe-cuting post-award to finalize the design across the 2,800-foot alignment?
14) Given the variable subsurface stratigra-phy of Long Island Sound, what supple-mental field investigations (e.g., Standard Penetration Test [SPT] borings, Cone Penetration Testing [CPT], laboratory test-ing) and geotechnical modeling (e.g., PLAXIS 2D/3D, SEEP/W seepage and piping analysis, or global slope stability) do you anticipate performing post-award to ad-vance the 35% concept into a sealed, Issued-for-Construction (IFC) foundation and wall design?
15) How will regional regulatory moratori-ums and site usage restrictions along Long Island Sound (e.g., Essential Fish Habitat [EFH] and winter flounder/anadromous fish spawning windows, protected avian nesting seasons, and peak summer recreational beach/waterway usage) impact your pro-posed mobilization, staging, and construc-tion sequencing across the 9 segments?
16) Are there specific materials anticipated for this seawall replacement (e.g., marine-grade steel sheet piling compliant with fed-eral domestic sourcing requirements, spe-cialized corrosion coatings, custom precast concrete units, or specific armor stone gra-dations) that are currently experiencing ex-tended fabrication lead times or significant price volatility?
17) What do you view as the top three tech-nical, schedule, or commercial risks for this 9-segment Design-Build project (e.g., un-foreseen subsurface boulders/obstructions in glacial till, coastal storm events during open excavation, or permitting/utility de-lays), and how can the Government best structure the RFP or allocate risk to mitigate them?
INFORMATION REQUESTED FROM
RESPONDENTS
All interested, capable, qualified, and re-sponsive firms are encouraged to reply to this announcement. The Government is re-questing that interested firms furnish the following information in addition to re-sponses to the questions above:
Corporate Information
1. Company name, address, point of contact, telephone number, and e-mail address.
2. Geographical areas in which you are capable of servicing.
3. Business-size and socioeconomic sta-tus, as applicable:
a. Small or large business firm as de-fined by SBA, or
b. Certified HUBZone firm, or
c. Service-Disabled Veteran Owned Small Business (SDVOSB) firm, or
d. SBA certified 8(a) firms.
4. Contractor’s comments or recommen-dations. Please provide, if any.
SUBMISSION INSTRUCTIONS
Due Date: All responses must be submitted no later than the date and time specified on the first page of this RFI. Limit response to 5 pages.
Format: Submissions should be in Adobe PDF format. The file name should be:
Contact Information
Attachments/Links
Links
[Company Name]_Response_RFI_W912DS- 27-S-0008.pdf.
Submission: Responses shall be submitted via email only to the following points of contact:
Contract Specialist: Mohenda Surage at mohenda.r.surage@usace.army.mil
Project Manager: Richard Gussenhoven at Richard.Gussenhoven@usace.army.mil
Primary Point of Contact
Mohenda Surage
Alternative Point of Contact
(blank)
Email mohenda.r.surage@usace.army.
mil
Phone Number 9177908088
Email (blank)
Phone Number (blank)
Contracting Office Address
KO CONTRACTING DIVISION
26 FEDERAL PLAZA ROOM 16 300
NEW YORK, NY 10278-0004 USA
WARNING
Attachments
No attachments have been added to this opportunity.
Link
PIEE Solicitation Module Link for W912DS27S0006
Web Based Training for the PIEE Solicitation Module
Registration Instructions for the PIEE Solicitation Module
Department of Defense Procurement Toolbox
Our Website
About This Site
Our Community
Release Notes
System Alerts
Our Partners
Acquisition.gov
USASpending.gov
Grants.gov
More Partners
Policies
Terms of Use
Privacy Policy
Restricted Data Use
Freedom of Information Act
Accessibility
Customer Service
Help
Check Entity Status
Federal Service Desk
External Resources
Contact
This is a U.S. General Services Administration Federal Government computer system that is "FOR OFFICIAL USE ONLY." This system is subject to monitoring. Individuals found performing unauthorized activities are subject to disciplinary action including criminal prosecution.
https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?noticeId=W912DS27S0006¬iceType=SourcesSought https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/index.xhtml https://www.acq.osd.mil/asda/dpc/ce/cap/docs/piee/PIEE_Solicitation_Module_Vendor_Access_Instructions.pdf https://toolbox-piee.eb.mil/ https://sam.gov/about/this-site https://interact.gsa.gov/group/integrated-award-environment-iae-industry-community https://www.fsd.gov/gsafsd_sp?id=kb_category&kb_category=ccf4380a1ba67410fe314000f54bcb16&kb_id=f66d8e6cdb76d4100d73f81d0f9619c https://sam.gov/alerts https://acquisition.gov/ https://usaspending.gov/ https://grants.gov/ https://sam.gov/about/partners https://sam.gov/about/terms-of-use https://sam.gov/about/terms-of-use#privacy https://sam.gov/about/terms-of-use#restricted https://www.gsa.gov/reference/freedom-of-information-act-foia https://sam.gov/about/accessibility https://sam.gov/help https://sam.gov/content/status-tracker https://www.fsd.gov/gsafsd_sp https://sam.gov/about/external-resources https://sam.gov/about/contact https://www.gsa.gov/
SAM.gov An official website of the U.S. General Services Administration
This system contains Controlled Unclassified Information (CUI). All individuals viewing, reproducing or disposing of this information are required to protect it in accordance with 32 CFR Part 2002 and GSA Order CIO 2103.2 CUI Policy.
File details come from the government source that posted it. Updated .