This document is an amendment to a solicitation for an Indefinite Delivery Indefinite Quantity (IDIQ) Services Contract for Monitoring the Historic Area Remediation Site (HARS) offshore of New York and New Jersey. The amendment provides responses to contractor questions regarding the solicitation requirements. Key details include:
The contract will be for a 5-year period and the scope of work includes collecting sediment and benthic samples, conducting oceanographic data collection and analysis, and other environmental monitoring activities in the New York Bight. The solicitation will use a Best Value Trade-Off (BVTO) evaluation process. The amendment clarifies that the vessel day rate is expected to include fuel and necessary equipment, but dockage may be negotiated separately for individual task orders. It also confirms that 30-foot cores are not routinely required, but the contractor should have the capability to collect them if needed. The majority of cores will likely range from 5-10 feet. The amendment also indicates that 24-hour operations would require two crew shifts. The pricing schedule has a significant portion (37%) of the total survey days designated for 24-hour operations, which the amendment suggests may be reduced based on contractor feedback.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide responses to contractor RFIs.
NOTE: Offerors must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Mar-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS24R0008
X 9B. DATED (SEE ITEM 11)
26-Feb-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Mar-2024
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS24R0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
RFIS
RFI Disclaimer Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.
Question 13: Is the vessel day rate expected to include fuel and dockage?
Response 13: Per the Statement of Work, “All vessels must include, at minimum the following equipment:
navigation systems with tracking capabilities, DGPS, fathometers, standard marine communication and safety equipment, spare parts if needed, fuel, lubricants, and other necessary equipment for safe offshore operation of the vessel. Vessels must be Coast Guard certified and in compliance with the latest published version of the USACE
EM 385-1-1.”
Dockage may not be necessary for all task orders or vessels. Dockage will be negotiated based on local rates for individual task orders.
Question 14: Can you please confirm if 30’ cores will be required? And that a vessel to accommodate cores of that size is required in the response.
Response 14: Thirty foot (30’) cores will not often be requested in task orders under this contract. However, the contractor should have the capability to collect up to 30’ cores, if required.
Question 15: Should we also plan to collect vibracores of shorter lengths i.e. 10-15’ and 20‘? If so, we will want to include costs for additional vessels to accommodate those collections.
Response 15: The majority of cores collected will likely range from 5 – 10 feet.
Question 16: Can you please confirm that the 35-64’, 24-hour vessel is expected to accommodate 2 crews (double shifts?).
Response 16: 24 hour operations would need 2 sets of crew to safely operate the vessel and perform work listed in the task order.
Question 17: The pricing schedule file (PDF named “HARS+Monitoring+Services+Price+Schedule+29JAN2024+rev+18MAR2024.pdf”), has an “Equipment” section with three separate Line Items related to 24 hour operations. In total, there are 89 survey days listed to be 24 hour operations. That is a significant portion (37%) of the total survey days proposed for the program. As the Corps is aware, vessel operating costs will account for the majority of expenses required for the monitoring programs proposed. The purpose of this RFI is to confirm that the Corps wants the Contractor to assume this level of support using such large vessels. Our team has supported the New England District DAMOS program for many years, and a vessel over 55’ has never been necessary to support that mission Response 17: The Contractor may utilize a smaller vessel (<55’) for 12 hour operations, as long as it’s efficient, safe and cost effective. The Corps has utilized 24 hour operations in the New York District AOR for offshore monitoring projects. This capability may be useful depending on availability of smaller vessels for 12 hour operations.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .