W912DS23B0007 Amendment 00002.pdf

PDF 784 KB Posted

Attached to
Maintenance Dredging of NY & NJ Channels, Seguine/Ward/Outerbridge Reaches, Federal Navigation Project
Solicitation number
W912DS23B0007
Issued by

About this file

This amendment provides responses to bidder questions regarding solicitation number W912DS23B0007 for maintenance dredging of navigation channels in New York and New Jersey. The U.S. Army Corps of Engineers, New York District, will only require dredging of shoals hatched on contract drawings. While an environmental bucket is required, conventional dredging may be allowed temporarily by state permit if refusal is met in gravel or sand not removable by environmental bucket. Bidders must account for this in pricing. Only material within the required dredging prism must be removed to grade.

View the file

Other files

File Type Posted
Bid Abstract.pdf PDF
W912DS23B0007 Amendment 00001.pdf PDF
c - SWO23 Plans_4.11.23.pdf PDF
d - SWO23 Specs_5.5.23.pdf PDF
W912DS23B0007.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Answ er questions to prospective bidders for informational purposes only.

NOTE: Bidders must acknow ledge receipt of this amendment by the date specif ied in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF1442, by separate letter, or by signing the block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE DATE BID, LATE

MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 30-May-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS23B0007

X 9B. DATED (SEE ITEM 11)

08-May-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

30-May-2023

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS23B0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 00002

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

The following questions and answers are provided for information only. Nothing contained below amends or revises any provision of the solicitation. This is for bidder’s reference only, and is not to be considered as a part of the Contract Documents. Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided and as posted on SAM.Gov.

Q1. Sheets 4 to 11 on the plans show the dredging areas for each shoal hatched. There are sections of the channel that are not hatched which show material above 35ft MLLW. Will the Contractor ONLY be required to dredge shoals shown as hatched on the contract drawings?

A1. Only shoals that are hatched are required to be dredged.

Q2. Several locations in the channel show material composed of gravel and/or sand, this material cannot be dredged with the required environmental bucket. An environmental bucket will only penetrate weight of rod (WOR) mud by design.

A) When refusal is met, will these areas be allowed to remain undredged, or B) will there be any requirement to remove material further with a heavier duty non-environmental bucket? C) If so, how will payment be handled for the bucket change delays and the less productive digging? D) Is a non-environmental bucket allowed?

A2. The contractor will be responsible for removing all material from the required dredging prism as specified in this solicitation. If during dredging operations the contractor finds that in a particular contract area they are unable to penetrate the bottom using the required environmental bucket, a request to the State(s) will be made by USACE to allow the temporary use of a conventional non-environmental bucket in that specific area, so grade can be achieved. Bidders need to account for this possibility in their bids.

(End of Summary of Changes)