B.08.03 Amendment 03.pdf

PDF 383 KB Posted

Attached to
FIMI PL 84-99 FY23 Federal contract opportunity
Solicitation number
W912DS23B0006
Issued by
Department of the Army Corps of Engineers Engineering District New York

About this file

This document is an amendment to a solicitation for the Fire Island Inlet to Moriches Inlet PL 84-99 Rehabilitation Project from Saltaire to Seaview in Suffolk County, New York. The U.S. Army Corps of Engineers, New York District will dredge approximately 800,000 cubic yards of beach fill from an existing offshore Atlantic Ocean Borrow Area using a hopper dredge as part of rehabilitation efforts. There is also an option to dredge approximately 500,000 additional cubic yards of beach fill for the Downtown Montauk Beach shoreline. The amendment provides revisions to drawings and specifications, answers questions from prospective bidders for informational purposes only, and removes the CD submission requirement from the bid package.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this modification is to:

Answ er questions to prospective bidders for informational purpsoes only.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Jul-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS23B0006

X 9B. DATED (SEE ITEM 11)

08-May-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Jul-2023

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS23B0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been added by full text:

AMENDMENT 03

W912DS-23-B-0006

Amendment No.3

To Bidders The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED and REISSUED:

2. The following DRAWINGS have been ADDED:

3. The following DRAWINGS have been REVISED but NOT REISSUED:

4. The following DRAWINGS have been DELETED:

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

3. The following SPECIFICATION SECTIONS have been REVISED and REISSUED in their entirety:

4. The following SPECIFICATION SECTIONS have been REVISED but NOT REISSUED:

REVISED SPECIFICATIONS:

Questions and Answers:

The following questions and answers are provided for information only. Nothing contained below amends or revises any provision of the solicitation.

This is for bidder’s reference only, and is not to be considered as a part of the Contract Documents.

Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided and as posted in the FBO.

RFI SET #1:

Question 1. Sheet G-001 Drawing Index shows Drawing No. C-109 was added to the drawings but not included in the most recent Amendment. Was Option - Downtown Montauk Beach Fill Plan Sheet 3 added? If so, please provide the drawing.

Response: Drawing C-109 was deleted, not added.

W912DS23B0006

Question 2: The Contractor request that the CD requirement required in the bid package be removed from this contract as it is a complex process to burn the CD prior to turning in the bid.

Response: CD requirement will be removed from the bid package.

(End of Summary of Changes)