This document is a modification to an existing Water Quality Certification for the Jones Inlet Dredging project. The modification allows dredging of the shoal at the seaward end of the project to begin on October 1st so that a cutterhead dredge may access the interior portion of the channel, and changes the activity restriction window for winter flounder dredging to be from January 1st to May 31st in the interior portions of the channel north of buoy Red #8. The related federal contract opportunity is for the FY22 Maintenance Dredging of the Jones Inlet, NY Federal Navigation Project being conducted by the Department of the Army Corps of Engineers Engineering District New York.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract signed.pdf | ||
| amendment 0001.pdf | ||
| 04 - JI Plan Drawing All sheets 1 - 12 reduced.pdf | ||
| W912DS22B0018.pdf | ||
| 03 - JI Technical Specification 2022 05 - 17 - 2022 .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
July 13, 2022
William Vanterpool Unites States Army Corps of Engineers 26 Federal Plaza, 16-414 New York, NY 10278
Re: Application #1-2820-01787/00012 Jones Inlet Dredging
Dear Permittee:
The Department of Environmental Conservation (DEC) has reviewed your request to modify the above referenced Water Quality Certification (WQC) in accordance with the Uniform Procedures Regulations (6NYCRR Part 621). It has been determined that dredging the shoal at the seaward end of the project beginning on October 1 so the cutterhead dredge may access the interior portion of the channel will not have significant adverse impacts to winter flounder.
Therefore, Condition 8 of the above mentioned WQC is hereby modified to read:
8. Activity Restriction Windows for Winter Flounder: To protect the spawning and early life stages of winter flounder there shall be no dredging from January 1 to May 31 inclusive of each year in the interior portions of the channel, defined as north of the buoy labeled “Red #8” on the approved plans.
This letter is a modification to the original WCQ and must be available at the job site whenever authorized work is in progress.
All other terms and conditions remain as written in the original WQC.