Amend 1 Specs 20191231.pdf
PDF 84 KB Posted
- Solicitation number
- W912DS20B0002
About this file
This solicitation announcement is for a coastal storm risk management project located in Suffolk County, New York. The U.S. Army Corps of Engineers, New York District intends to issue an invitation for bid for work including the placement of approximately 550,000-750,000 cubic yards of sand along 4,000 linear feet of beach west of the west Shinnecock Inlet jetty. Sand will be dredged from Borrow Area 6b located approximately 5 miles east of Shinnecock Inlet. The contract value is estimated between $10-25 million. The advertisement and award are projected for December 2019 to January 2020, with a 60 calendar day period of performance from notice to proceed. Interested contractors must register in SAM.gov and monitor the Beta SAM website for the solicitation and any amendments to be posted on or about December 20, 2019, with bids due on or about January 3, 2020. All questions must be submitted in writing to the specified point of contact.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| G-102.pdf | ||
| XYZ data.pdf | ||
| W912DS20B0002-Amendment 2.pdf | ||
| W912DS20B0002 Amendment 0001.pdf | ||
| Amend 1 Plans 20191231.pdf | ||
| W912DS20B0002.pdf | ||
| 100 PCNT WOSI SPECS_20191223.pdf | ||
| wosi_100%_20191220.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WOSI - FCCE, Suffolk County, NY WOSI
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 00 01 COVER SHEET
00 00 02 CHECK LIST FOR BIDDERS
00 10 00 SF 1442 AND BIDDING SCHEDULE
00 21 16 INSTRUCTIONS, CONDITIONS, AND NOTICE TO BIDDERS
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 72 00 CONTRACT CLAUSES
00 90 00 WAGE RATES
00 90 01 REPORT OF OPERATIONS FORM
00 90 02 WATER QUALITY CERTIFICATE
00 90 03 COMPOSITE GRAIN SIZE DISTRIBUTION CURVES AND GRAIN SIZE
SCALES FOR SAND SEDIMENTS
00 90 04 WENTWORTH SCALE
00 90 05 TRANS-ATLANTIC SUBMARINE CABLES
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 11 35 AIR EMISSIONS REQUIREMENTS
01 14 00 WORK RESTRICTIONS
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 56 10.00 18 ENDANGERED SPECIES OBSERVERS (HOPPER DREDGES ONLY)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00.00 18 PROJECT IDENTIFICATION
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 31 - EARTHWORK
31 24 00.00 18 BEACH FILL PLACEMENT
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 31 10.00 18 SAND FENCE
32 94 00 DUNE VEGETATION PLAN
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23.23 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM HOPPER DREDGE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1 Amendment 1
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 2
SECTION 00 00 01
COVER SHEET
01/18
PART 1 GENERAL
NEW YORK DI STRI CT
CORPS OF ENGI NEERS
NEW YORK, NEW YORK 10278- 0090
I NVI TATI ON FOR BI DS
FOR
COASTAL STORM RI SK MANAGEMENT - FCCE
FI RE I SLAND I NLET TO MONTAUK POI NT
WEST OF SHI NNECOCK I NLET I NTERI M PROJECT
SUFFOLK COUNTY, NEW YORK
1. Attached is INVITATION FOR BIDS (IFB) NO. W912DS-20-B-0002
2. BIDS MUST BE SET FORTH full, accurate, and complete information as required by this Invitation for Bids, including attachments. The penalty for making false statements in bids is prescribed under Title 18, United States Code, Section 1001.
3. SUBMISSION OF BIDS: Complete details concerning proper submission of bids are contained in the INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS (Section 00 21 16 ).
4. Note the REQUIREMENT FOR AFFIRMATIVE ACTION of the EQUAL OPPORTUNITY clause as it applies to the contract resulting from this solicitation. (See paragraph NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY in Section 00 21 16 of this IFB).
5. REPRESENTATIONS AND CERTIFICATIONS - SECTION 00 45 00 Bidders and Offerors are required to complete the REPRESENTATIONS AND CERTIFICATIONS and submit them with their bids.
Within Section 00 45 00 , note in particular the PROHIBITION SEGREGATED FACILITIES. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity Clause
(1984 APR).
6. THIS PROJECT IS A CIVIL WORKS PROGRAM PROCUREMENT AND IS NOT FUNDED BY
THE DEPARTMENT OF DEFENSE. BUY AMERICAN ACT - CONSTRUCTION MATERIALS
(MAY 1993) IN ACCORDANCE WITH FAR 52.225-5 APPLIES.
7. Please review all bonds and accompanying documents required to be submitted. Bonds, Powers of Attorney, statements of authenticity and continuing validity, and all related documents MUST NOT bear computer printer-generated signatures and/or seals. Documents bearing signatures and/or seals generated as part of a document, as opposed to
DOCUMENT 00 00 01 Page 1 Amendment being affixed to the document after its generation, will not be accepted. Submission of such documents may render the bid or offer non-responsive and ineligible for award.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
DOCUMENT 00 00 01 Page 2
SECTION 00 00 02
CHECK LIST FOR BIDDERS
01/18
PART 1 GENERAL
ATTACHED IS IFB NO. W912DS-20-B-0002
COASTAL STORM RI SK MANAGEMENT - FCCE
FI RE I SLAND I NLET TO MONTAUK POI NT
WEST OF SHI NNECOCK I NLET I NTERI M PROJECT
SUFFOLK COUNTY, NEW YORKk
ALL INFORMATION REQUIRED BY THE TERMS OF THIS SOLICITATION MUST BE
FURNISHED. MISTAKES OR OMISSIONS MAY RENDER YOUR OFFER INELIGIBLE FOR
AWARD. IMPORTANT ITEMS FOR YOU TO CHECK ARE INCLUDED IN BUT NOT LIMITED
TO THOSE LISTED BELOW. THIS INFORMATION IS FURNISHED ONLY TO ASSIST YOU
IN SUBMITTING A PROPER BID
____HAVE YOU ACKNOWLEDGED ALL AMENDMENTS?
____HAVE YOU COMPLETED THE "REPRESENTATIONS AND CERTIFICATIONS" (SECTION
00 45 00) PORTION OF THE SOLICITATION?
____IS YOUR DUNS NUMBER LISTED ON THE STANDARD FORM 1442?
____IS YOUR BID GUARANTEE PROPERLY SIGNED BY BOTH THE BIDDER AND SURETY
AND ARE ALL SEALS AFFIXED?
____DO THE BID BOND AND ACCOMPANYING DOCUMENTS BEAR SIGNATURES AND SEALS
AFFIXED AFTER THE DOCUMENT WAS GENERATED, AS OPPOSED TO COMPUTER
PRINTER-GENERATED SIGNATURES AND/OR SEALS?
____HAVE YOU ENSURED THAT YOU HAVE NOT RESTRICTED YOUR OFFER BY ALTERING
THE PROVISIONS OF THE SOLICITATION?
____WHEN REQUIRED, HAVE YOU ENTERED A UNIT PRICE FOR EACH PRICE ITEM?
(THE SOLICITATION SPECIFICALLY STATES WHEN THIS IS NECESSARY.)
____ARE DECIMALS IN YOUR PRICES IN THE PROPER PLACE? ARE YOUR FIGURES
LEGIBLE?
____IF YOU HAVE MADE ERASURES OR CORRECTIONS ON YOUR BID, ARE THEY
INITIALED BY THE PERSON SIGNING THE BID?
____DOES THE ENVELOPE CONTAINING YOUR BID PROPERLY IDENTIFY THAT IT ISA
SEALED BID AND DOES IT CONTAIN THE CORRECT SOLICITATION NUMBER AND BID
OPENING TIME?
____WILL YOUR OFFER ARRIVE ON TIME? (SEE PARAGRAPH ENTITLED "LATE
SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS" IN THE
INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS, SECTION 00 21 16 OF
THE SOLICITATION.)
____WILL YOUR OFFER ARRIVE ON TIME? (SEE PARAGRAPH ENTITLED "LATE
SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS" IN THE
INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS, SECTION 00 21 16 OF
DOCUMENT 00 00 02 Page 1
THE SOLICITATION.)
NOTE: THERE ARE INCREASED SECURITY MEASURES AT JACOB K. JAVITS
FEDERAL BUILDING, 26 FEDERAL PLAZA THAT MAY AFFECT THE TIME IT TAKES
TO ENTER THE BUILDING. BIDDERS IS RESPONSIBLE TO ENSURE THAT ITS BID
IS SUBMITTED TIMELY.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
DOCUMENT 00 00 02 Page 2
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
08/15
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the SCHEDULE and described below.
All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 MOBILIZATION AND DEMOBILIZATION
Mobilization shall include all costs for operations accomplished prior to commencement of actual dredging operations, such as transfer of dredge and attendant plant and equipment to site, initial installations of pipe, preparation of beach fill areas, and other incidentals in advance of the actual dredging. Demobilization shall include general preparation for transfer of plant to home base, removal of pipelines, cleanup of beach fill areas, and transfer of plant to its home base. The cost of work other than mobilization and demobilization of the Contractor's dredging plant and equipment shall not be included in this item. For payment for Mobilization and Demobilization see contract clause Section 00 72 00 Contract Clauses.
All costs connected with the mobilization and demobilization of all of the contractor's dredging plant and equipment will be paid for at the contract lump sum price for this item. 60 percent of the lump sum price will be paid to the Contractor upon completion of his mobilization to the work site. The remaining forty percent 40 percent will be included in the final payment for work under this contract.
In the event the Contracting Officer and/or his Representative considers that the amount in this item 60 percent, which represents mobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer and/or his Representative may require the Contractor to justify this portion of the bid. Failure to justify such price to the satisfaction of the Contracting Officer and/or his Representative will result in payment of actual mobilization costs as determined by the Contracting Officer and/or his Representative, at the completion of mobilization and payment of the remainder of this item in the final payment under this contract. The determination of the Contracting Officer and/or his Representative is not subject to appeal.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit
SECTION 01 22 00.00 10 Page 1 price payments will be made are listed in the SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.2.1 Hydraulic Beach Fill Placement
1.2.1.1 Payment
The total amount of material acceptably placed on the beach (from the borrow areas) is to be paid for at the contract unit price as shown on the price schedule (Section 00 10 00 ), shall be measured by the cubic yard in place on the beach by computing the volume between the beach surface shown by a survey made before filling and beach surface shown on a survey after filling. The reference datum shall be NAVD. No payment shall be made for material placed:
(1) In excess of the quantity to the design grade plus the 1.0 foot tolerance. Refer to the Compensated Slope paragraph in section 31 24
00.00 18 BEACH FILL PLACEMENT for exception regarding compensated slope.
(2) For the extent of the project as shown on the contract drawings, above El +14 ft. NAVD plus tolerance on the dune crest; beyond the 1 on 5 slope line on dune side slope plus tolerance, above +8.5 ft NAVD plus tolerance on the berm, and beyond the point where the 1 on 20 slope line from El. +8.5 ft. NAVD plus tolerance, intersects the ocean bottom. Refer to the Compensated Slope paragraph in section 31 24
00.00 18 BEACH FILL PLACEMENT for exception below elevation +3.0 NAVD.
(3) Which was obtained from outside the designated borrow area or below the maximum dredging limit of the borrow area, except as directed by the Contracting Officer or his representative.
1.2.1.2 Original and Final Surveys
The Contractor shall make original and final surveys under the supervision of the Contracting Officer's representative and shall make computations to determine the quantities of materials placed on the beach for acceptance.
1.2.1.3 Surveys for Progress Payments
The Contractor will make any surveys for periods for which progress payments are requested and shall make the computations based on these surveys.
1.2.1.4 Initial and Final Surveys
Initial and final surveys for acceptance will be taken immediately prior to and after fill placement. Before fill, surveys shall not be taken more than 14 days prior to fill placement. Surveys will be taken on parallel profile lines (ranges) spaced at a maximum of 100-foot intervals. The minimum stationing interval will be 25 feet or at breaks in slope.
The Contractor shall conduct the original and final surveys, with the presence of Government representatives, and make the computations based on
SECTION 01 22 00.00 10 Page 2 them. The Contractor shall conduct the surveys for any periods for which progress payments are requested and shall make the computations based on these surveys. All surveys conducted by the Contractor shall be done by a New York licensed surveyor and certified hydrographer subjected to approval by the Contracting Officer.
- The Contractor shall be responsible to conduct all surveys. The Contractor shall maintain work sections - a pre-construction and final acceptance section surveyed while construction is taking place in between.
The pre-construction sections should be maintained at a minimum 300 feet ahead of the fill placement. The Contractor shall make such computations as are necessary to determine the quantities of work performed or finally in place and submit the computation for Government approval.
-Promptly upon completing a survey, the Contractor shall furnish the originals of all field notes and all other records relating to the survey or to the layout of the work to the Contracting Officer, who shall use them as necessary to determine the amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer or his representative. (FAR 52.236-16)
For Beach Fill Placement:
The Contractor will coordinate with the Contracting Officer's representative to maintain work sections. The Contractor will perform preconstruction surveys between 500 feet and 1500 feet in advance of the last acceptance station but not more than 14 days prior to fill placement.
The surveys shall be performed in 100 foot increments. Acceptance surveys shall be performed when 500 linear feet of beach is dressed and graded to template.
For Borrow Area Surveys:
A pre- and post- construction survey of the borrow area at least 100 feet along the length of the borrow area and 25-foot intervals is required for this project to monitor the pre- and post-construction borrow area conditions with other survey methods approved by the COR.
In addition, weekly borrow area surveys are required at 200-foot sections and 5 foot intervals. The Contractor shall compute the volume extracted and furnish all computations, Fathometer plots, and depth readings utilized to the Contracting Officer with each CQC report See
01 45 00.00 10 QUALITY CONTROL
1.2.1.5 Original Field Notes, Computations and Other Records
All original field notes, computations and other records for the purpose of layout of surveys conducted by the Contractor shall be recorded in duplicating field books, the original pages of which shall be furnished promptly to the Contracting Officer, or his representative, at the site of work. The Contractor shall furnish the Contracting Officer, or his representative, profile data for the survey in electronic format specified by the contracting officer. The survey data shall be in a format compatible with both the HYPACK program and in X, Y, Z format, and stored on DVD's. The Contractor shall submit to the Contracting Officer, prior to surveying, a base line drawing showing all offsets, elevation, reference lines and range line locations to be utilized.
SECTION 01 22 00.00 10 Page 3
1.2.1.6 Temporary Fencing
No separate payment shall be made for temporary fencing, and all costs in connection therewith shall be included in the contract unit price for Hydraulic Beach Fill.
1.2.2 Sand Fence
1.2.2.1 Payment
Payment will be made for all plant, labor, equipment, transportation, and materials for site preparation and installation of sand fence in accordance with the Contract Drawings and Specifications.
1.2.2.2 Measurement
Measurement will be by linear feet of fence.
1.2.2.3 Unit of Measure
Unit of measure: Linear feet.
1.2.3 Dune Vegetation
1.2.3.1 Payment
Payment will be made for all items for planting will be measured by the units installed in accordance with the plans and specifications (Section 32 94 00, acres), and to the satisfaction of the Contracting Officer.
1.2.3.2 Measurement
All items for planting will be measured by the units installed in accordance with the plans and specifications (Section 00 10 00 SF 1442 AND BIDDING SCHEDULE), and to the satisfaction of the Contracting Officer.
1.2.3.3 Unit of Measure
The price for all vegetation (e.g., seeds, grasses, plants, trees, etc) and installation shall include the cost of furnishing all labor, materials, equipment, and incidentals necessary to complete this item in accordance with the plans, specifications, and the directions of the Contracting Officer. The price for all plantings shall be in acres. The Contractor shall be paid for percentage complete based on determination of the Contracting Officer during installation. A pre-determined amount will be retained by the Contracting Officer payable when the conditions in Sections 3.3 and 3.4 of Specification Section 00 10 00 SF 1442 AND BIDDING SCHEDULE are met and approved as satisfactory by the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 22 00.00 10 Page 4
SECTION 31 24 00.00 18
BEACH FILL PLACEMENT
PART 1 GENERAL
1.1 MOBILIZATION AND DEMOBILIZATION
Mobilization shall include all costs for operations accomplished prior to commencement of actual dredging operations, such as transfer of dredge and attendant plant and equipment to site, initial installations of pipe, preparation of beach fill areas, and other incidentals in advance of the actual dredging. Demobilization shall include general preparation for transfer of plant to home base, removal of pipelines, cleanup of beach fill areas, and transfer of plant to its home base. The cost of work other than mobilization and demobilization of the Contractor's dredging plant and equipment shall not be included in this item. For payment for Mobilization and Demobilization see contract clause Section 00 72 00 Contract Clauses.
All costs connected with the mobilization and demobilization of all of the contractor's dredging plant and equipment will be paid for at the contract lump sum price for this item. Sixty percent (60%) of the lump sum price will be paid to the Contractor upon completion of his mobilization to the work site. The remaining forty percent (40%) will be included in the final payment for work under this contract.
In the event the Contracting Officer and/or his Representative considers that the amount in this item (60%), which represents mobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer and/or his Representative may require the Contractor to justify this portion of the bid. Failure to justify such price to the satisfaction of the Contracting Officer and/or his Representative will result in payment of actual mobilization costs as determined by the Contracting Officer and/or his Representative, at the completion of mobilization and payment of the remainder of this item in the final payment under this contract. The determination of the Contracting Officer and/or his Representative is not subject to appeal.
1.2 DREDGING OF BORROW AREAS
The beach renourishment to be done under these specifications will be the dredging of the Borrow Areas with placement of the dredged sand along the shoreline, as shown on the contract drawings.
1.3 SCOPE
The work covered by this section consists of furnishing all labor, materials, and equipment, and performing all operations required for removal of material from the designated borrow area as shown on the contract drawing, conducting borrow area pre-and post-removal surveys, transportation and placing the material as beach fill on the Atlantic Ocean shore within the limits specified herein and shown on the drawings, conducting pre- and post-placement beach condition surveys and grab samples GSD analysis as specified.
SECTION 31 24 00.00 18 Page 1
1.4 SITE CONDITIONS
Bidders are expected to examine the site of the work, including the placement areas and decide for themselves the conditions affecting their operations prior to submitting their bids. See Contract Clause entitled:
"SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK" (FAR 52.236-3).
1.5 SEDIMENTATION PERMITS
No local governmental sedimentation or erosion control permits are required for this work except that as required in accordance with Contract Clause entitled: "PERMITS AND RESPONSIBILITIES" (FAR 52.236 7).
1.6 SUBMITTALS
The Contractor shall submit for approval, by the Contracting Officer and/or his Representative, his plan for development of any contractor-furnished placement areas or any modification to the Government furnished placement area. This plan shall show areas or portions thereof to be used. The plan shall also show the manner in which the dredged material will be distributed in the areas. Such plans shall be provided by the contractor at the Preconstruction Conference. If the plan is not accepted the Contractor is to perform the work in accordance with the specifications.
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBITTAL PROCEDURES:
SD-03 Product Data
Grain Size Distribution Curves of beach fill material after placement ; G, RO
SD-11 Closeout Submittals
Before and After Beach Fill Placement Surveys ; G, RO
Before and After Dredge Surveys of the Borrow Area ; G, RO
Weekly Borrow Area Surveys per paragraph INITIAL AND FINAL SURVEYS
1.7 QUALITY CONTROL
a. QUALITY CONTROL: The Contractor shall establish and maintain quality control for material placement to assure compliance with contract requirements, and maintain records of his quality control for all construction operations, including but not limited to the following:
1) Dredging, including suitability of dredged material and manipulation and control of the dredge discharge.
2) Placement of sand fill material, including continuity and order of placement; distribution of material and measures used to control loss of material.
b. The Contractor will have a "NOTICE TO MARINERS" published by the Coast
SECTION 31 24 00.00 18 Page 2
Guard 15 days prior to start of work.
c. Placement Plan: The Contractor shall submit for approval his placement plan at the Preconstruction Conference (Section 01 30 00 ADMINISTRATIVE REQUIREMENTS). The placement plan shall include the particular site(s) to be utilized, all special conditions (i.e., NYSDEC, etc.) specific to sites(s) being used, contractor access to the site(s) locations and cross-section of existing and proposed dikes, maximum elevations and quantities of placement material for each site, weir and drainage structure locations, manner in which the dredged material will be distributed in the areas, etc. Approval of the placement plan by the Contracting Officer or his representative is required prior to placement site(s) preparation. The Contractor shall conduct his work in accordance with the Placement Plan, however, approval of the plan for development of the placement area does not in any manner relieve the Contractor of his responsibility for the adequacy of the design and construction and drainage facilities required. In addition, the Contractor shall also submit at the pre-construction meeting, his plan for road crossings of the discharge pipeline. The contractor shall be responsible for securing the appropriate permits for any road crossings of discharge pipeline or similar activities and may not begin work until such permits are received from the appropriate agencies.
d. Pre-Construction Site Visit: Prior to actual construction of any placement site, the Contractor and the Contracting Officer and/or his representatives shall visit the site(s) for the purpose of delineating areas of access avoidance (cultural resource, protection of existing dune, and/or wetland concerns).
e. Construction/Maintenance of Containment Structure. The Contractor shall construct all retaining dikes, waste weirs and drainage structures as are necessary for confining the dredged material and for controlling placement area effluent until acceptance of all work under the contract.
f. Protection of Structures and Adjacent Areas. The contractor shall be responsible for the maintenance, repair and stability of all dikes, roads and structures, used by him under the contract. The Contractor shall restore all dikes, roads, and areas he disturbs through his operations to a satisfactory condition, as approved by the Contracting Officer or his representative, at no additional cost to the Government.
g. Protection of Existing Dunes and Dune Vegetation: Existing dunes and dune vegetation shall be undisturbed to the maximum extent practicable.
Limits of existing dune and dune vegetation shall be identified and delineated prior to fill placement. Pipelines and access for construction equipment shall not cross existing dunes or dune vegetation except as directed by the Contracting Officer.
h. Inspection of Structures and Adjacent Areas. The Contractor shall inspect all dikes, roads, waste weirs, and adjacent areas utilized during this operation on a daily basis to assure their safety and stability. The Contractor shall include these inspections in his daily quality control report. The inspection shall include but not be limited to structures, equipment, safety, security, drainage and seepage.
i. Reporting Requirements. The Contractor shall maintain a daily written record of all placement site operations. This requirement shall be made a part of the Contractor's Quality Control Plan and each record shall be included in the Contractor's Quality Control Report.
SECTION 31 24 00.00 18 Page 3
j. Containment Structure Restoration. The Contractor shall restore any feature of any containment structures as required to prevent the escape of dredged material from the placement site on to adjacent areas.
k. Control of Placement Area Effluent. The contractor shall monitor and control placement area conditions and placement effluent quality as prescribed in these specifications. The Contractor's Quality control Plan shall identify monitoring requirements and measures, which will be taken to control placement area conditions to insure effluent quality meets the requirements identified in the Water Quality Certificates (Section 00 90 02 Water Quality Certificate).
l. New York State Water Quality Certifications. The contractor shall comply with all requirements identified in the NYSDEC Water Quality Certificate (WQC) including all special conditions. A copy of the WQC is included in Section 00 90 02 WATER QUALITY CERTIFICATE J, Attachment E of this specification.
m. Removal of Containment Area Structures. Any structures (i.e., weirs, pipeline, etc.) installed by the Contractor for use in his placement operations shall be removed and the contractor shall repair and stabilize all areas affected by the removal of these structures as approved by the Contracting Officer.
n. The contractor shall obtain grab samples of the placed fill from: the beach backshore; edge of berm; mean high water (MHW); and mean low water (MLW). One set of samples shall be taken every 200 feet along the placed fill area. A grain size analysis of each sand sample will be made using sieve sizes comparable to the Wentworth size classifications (shown in Section 00 90 04 WENTWORTH SCALE) and the results plotted on an appropriate curve format. The laboratory analysis results and plotted grain size distribution curves shall be furnished with the Daily Construction Quality Reports.
1.8 REPORTING REQUIREMENTS
1.8.1 Daily Report of Operations
The Contractor will, on Eng. Form 4267, be required to prepare and maintain a daily report of operations and inspections and furnish copies thereof to the Contracting Officer or his representative. All the forms prescribed for the required information are in Section 00 90 01 Report of Operations Form. Further instructions on the preparation of the report will be furnished at a pre-construction conference. Attached to the form, the Contractor shall submit a plan of the borrow area indicating the location, depth and extent of his dredging operations for that day.
1.8.2 Dredge Operation Production Records
When a hopper dredge operation is used, the Contractor will submit daily records of hopper loads, including tonnages of empty and fully loaded conditions prior to pumpout. For all types of dredge operations the Contractor will furnish production meter records (using properly calibrated instruments) of suctionline densities and pipeline velocities.
Production meter records and loadmeter records must be cataloged either by time of day or load number.
SECTION 31 24 00.00 18 Page 4
PART 2 PRODUCTS
2.1 CHARACTER OF MATERIALS
The character of materials within the borrow areas is provided in Section 00 90 03 Composite Grain Size Distribution Curves and Grain Size Scales for Sand Sediments. If rock, rubble, or any other debris is encountered during dredging, the Contractor shall immediately cease operations and relocate to another section of the borrow areas. He shall report the encounter with the rock, rubble or any other debris on the quality control form and immediately notify the Contracting Officer, or his representative, verbally, providing location in Long Island Lambert coordinates of the area of rock, rubble or any other debris. Rock, rubble, or any debris larger than two (2) inches in diameter which is excavated and placed on the beach will be removed by the Contractor, totally at his own cost. If the Contractor fails to remove the rock, rubble, or any other debris, such material may be removed by the Government and the cost of such removal may be deducted from the money due, or to become due to the Contractor or may be recovered under his bond. Bidders are expected to examine the site of the work and boring samples and decide for themselves the character of the materials.
2.2 BORROW AREAS
2.2.1 Quantity
2.2.1.1 Off-Shore Borrow Areas
For this project, a sufficient quantity of material suitable for the beach fill is available from the borrow area shown on the Contract Drawings.
2.2.2 Borrow Area Limits
All material shall be dredged from within these areas. In the event any portion of the borrow areas yields material unsuitable for use on the beach, the Contracting Officer, or his representative, may direct that the depth of excavation be changed or that the excavating equipment be moved to other portions of the borrow areas that will yield suitable material.
Under no circumstances shall material be obtained from outside the established limits of the borrow areas. Should it be determined that an area outside the limits of the designated borrow areas was used for borrow, the Contractor shall restore such area to original condition.
Borrow areas limits shown on the drawing are toe of slope.
2.2.3 Soundings
Soundings in the borrow area are shown on the drawings. Dredging in the borrow areas will be allowed to the depths indicated on the drawings.
2.2.4 Slopes
The dredge cuts in the borrow area shall not have side slopes steeper than 1 on 10 3. Borrow area entrance and exit slopes shall not be steeper than 1 on 10 3. Borrow area must have a uniform bottom elevation.
SECTION 31 24 00.00 18 Page 5
2.3 GRAIN SIZE DISTRIBUTION CURVES
2.3.1 After Placement
Submit the Grain Size Distribution Curves of beach fill material after placement to the Contracting Officer for approval.
PART 3 EXECUTION
3.1 ORDER OF WORK
Refer to section 01 14 00 WORK RESTRICTION, "Order of Work" paragraph.
3.2 PLACEMENT OF SAND FILL
3.2.1 Placement
The material dredged from the designated borrow areas shall be placed on the beach fill areas to the specified limits and cross sections shown on the drawings, provided, however, that the provisions of subparagraph 3.2.8(4) shall be controlling with respect to the limits and sections of the beach fill area below El. +3.0 NAVD. The material shall be deposited as evenly as practicable by the hydraulic method to form a comparatively smooth and uniform beach surface. A tolerance of 1.0 foot above El. +3.0 NAVD, measured vertically, will be allowed and paid for on material placed above the required design grades.
3.2.2 Material Deposited Elsewhere
Any material that is placed elsewhere than in places designated or approved by the Contracting Officer, or his representative, will not be paid for, and the Contractor may be required to remove such material, and place it where directed, at his expense.
3.2.3 Dredge Material
Dredge material shall be pumped directly from the dredging vessel to the beach placement area. No bottom placement and re-handling will be allowed.
Dredge discharge shall be manipulated and controlled by the Contractor in such a manner that a minimum of shaping by mechanical equipment will be required and a minimum amount of material will be lost.
3.2.4 Floatable Material
All floatable material excavated, including, without limitation, wood and tires, shall be disposed of at an existing approved upland disposal area.
Should the Contractor encounter floatable material, a copy of a letter granting the permission of appropriate authorities to use an existing approved upland disposal area shall be submitted to the Contracting Officer and/or his representative.
3.2.5 Final Beach Berm
The final beach berm of placed fill shall be shaped above El. +3.0 ft NAVD by bulldozing or other approved means as required, to provide the design beach sections shown on the drawings. No reshaping of the existing beach, which is above the lines and grades of the design section will be permitted.Return Staging area and access roads to their original conditions.
SECTION 31 24 00.00 18 Page 6
3.2.6 Compensated Slope
If the construction template cannot be achieved at the toe of the section, then a compensated slope to offset voids in the construction fill template will be allowed. Such excess material shall be placed below elevation +8.5 ft NAVD and graded at the design slope to +3.0 ft NAVD with all material below +3.0 ft NAVD being the uncontrolled hydraulic slope of the material; and the payable quantity shall not exceed the deficiency in template volume plus tolerance.
3.2.6.1 Acceptance of Fill Section
A fill section will not be accepted unless the payable quantity equals or exceeds the cross sectional volume between the design grade and the pre-existing grades (excludes tolerance).
3.2.7 Dredge Discharge
It is intended that dredge discharge shall be manipulated and controlled by the Contractor in such a manner that a minimum of shaping by mechanical equipment will be required and a minimum amount of material will be lost.
3.2.8 Placement of Dredged Material
Placement of dredged material on the beach fill area shall be subject to the following conditions:
(1) Any discharge pipeline crossing navigation channels must be submerged so that sufficient depth for navigation exists.
(2) Such discharge pipeline must be marked by signs, lights or other devices to insure safety to navigation by day and by night. All of these devices shall be in complete accordance with Coast Guard regulations. The contractor shall provide a written discussion of pipeline markings in the Accident Prevention Plan. Refer to section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS for the Accident Prevention Plan requirements.
(3) The discharge pipeline shall be arranged as approved by the Contracting Officer or his representative.
(4) It is expected that in placing the sand fill hydraulically, most of the silt and other fines being pumped will be washed into the ocean and dissipated by wave action. Ponding of the dredge effluent will not be allowed. However, baffles or dikes to control the flow of the dredge effluent will be required. The final seaward slope of the sand fill to be placed below El. +3.0 ft NAVD shall be the uncontrolled hydraulic slope of the material placed by the dredging process, estimated to be a 1 vertical to 15 horizontal slope down to the ocean bottom. The dredge effluent shall in all cases return directly to the ocean and not to the inshore side of the fill.
(5) A dike shall be constructed at the inshore limit of fill to prevent the dredge effluent from extending beyond the contract limits.
(6) Tracked vehicles shall be operated on the fill in such manner so that they do not cause excessive gouging.
(7) The Contractor shall be solely responsible for any damage caused by
SECTION 31 24 00.00 18 Page 7 him to any boardwalk, structures, existing dune or dune vegetation, pavement, curbs, signs, lamps, bulkhead, seawall, groin, beach grass, or any other property adjacent to the beach fill areas, and shall be required to repair at his own expense any such damage caused during the performance of work under this contract. Prior to the commencement of operations and after completion thereof, a joint inspection by representatives of the Contractor, The Contracting Officer and local interests pertaining to the above will be made.
(8) In order to provide access for pedestrians across the pipeline in beach use areas within the contract limits, the pipeline shall be ramped with sand on both sides at a 1V:10H slope over the top elevation of the pipe at pedestrian access ways or at 500-foot intervals. Width of the ramps shall be 10 feet. The Contractor may provide another method of maintaining pedestrian thoroughfare across the pipe-line upon approval by the Contracting Officer or his representative. Pedestrian thoroughfare shall be maintained for the duration of the contract. Also, in order to provide for the safety of persons using the beach, Points of Contact are listed in Section 01 30 00 ADMINISTRATIVE REQUIREMENTS.
During all pumping operations, the Contractor shall provide personnel to maintain visual control at the end of the discharge line. Radio contact shall also be provided by the Contractor to enable such personnel to halt dredging in case of emergency.
(9) The Contractor may be directed to move to another location within the Borrow Area if undesirable material begins to be pumped onto the beach (i.e. silt).
(10) The area where filling operations are in progress shall be floodlighted during the hours of darkness. Illumination shall be provided by using portable light equipment such as model No.LDA I6 MTVE manufactured by ALLMAND BROS. INC. of HOLDREIRE, or approved equal. A minimum of 3-foot candles of illumination shall be maintained in the immediate vicinity of the pipe discharge.
(11) Monitoring the discharge operation by radio communication from the discharge location to the leverman during all pumping operations is required.
(12) A placement section will not be accepted for final survey unless the section is graded and dressed so as to eliminate any undrained pockets, abrupt lumps, and depressions in the beach fill surface.
(13) During all pumping operations, the Contractor shall provide personnel to maintain visual control of the end of the discharge line.
Radio contact shall also be provided by the Contractor to enable such personnel to halt dredging in case of emergencies or undesirable material placement as directed by the COE.
(14) A temporary dike shall be constructed at the inshore limit of the fill to prevent the dredging effluent from extending beyond the contract limits.
(15) Completed work on the beach fill placement will be accepted in 500-foot long sections. Upon completion of all filling operations within an acceptance section, the fill shall be graded and dressed so as to eliminate any un-drained pockets, abrupt lumps, and depressions in the beach fill surfaces. The bank caused by ocean wave erosion shall be graded
SECTION 31 24 00.00 18 Page 8 down to a slope not steeper than one (1) foot vertical to twenty (20) fifteen (15) feet horizontal to Elev. +3.0 NAVD. Final surveys as required in paragraph entitled QUANTITY SURVEYS of the Special Contract Requirements may not be performed until fill is graded and dressed. Final acceptance of the beach fill work will be as defined in paragraph entitled FINAL EXAMINATION AND ACCEPTANCE in section 01 30 00 ADMINISTRATIVE
REQUIREMENTS.
(16) The Contractor shall obtain grab samples of placed fill from: the beach back-shore; edge of berm; mean high water (MHW); and mean low water (MLW). One set of samples shall be taken every 200 feet along the placed fill area. A grain size analysis of each sand sample will be made using sieve sizes comparable to the Wentworth size classifications (shown on Section 00 90 04 WENTWORTH SCALE) and the results plotted on the curve format in section 00 90 03 Composite Grain Size Distribution Curves and Grain Size Scales for Sand Sediments. The laboratory analysis results and plotted grain size distribution curves shall be furnished with the Daily Construction Quality Reports.
3.3 PLANT
The Contractor agrees to keep on the job sufficient plant to meet the requirements of the work. The plant shall be in a satisfactory operating condition and capable of safely and efficiently performing the work as set forth in the specifications. The plant shall be subject to the inspection of the Contracting Officer and/or his Representative at all times. No reduction in the capacity of the plant employed on the work shall be made except by written permission of the Contracting Officer and/or his Representative. The measure of the "capacity of the plant" shall be its actual performance on the work to which these specifications apply.
3.3.1 Scows
The use of scows is prohibited.
3.3.2 Hydraulic Pipelines
All pipelines for hydraulic dredging Plant must be kept in good condition at all times and any leaks or breaks along their length shall be promptly repaired. All breaks in any pipeline shall be reported on the Contractor's Daily Quality Control Report for the date the break occurred. An estimation of the duration of the break and the quantity of misplaced material shall be provided in the report.
3.3.3 Marking of Floating Dredge Pipelines
The contractor shall be required to mark floating dredge pipelines in accordance with the requirements of 88.15 of Annex V of U.S. Navigation Rules, inland, COMDTINST M 16672.2A, dated 23 December 1983. Dredge pipelines that are floating or supported on trestles shall display one row of yellow lights, visible all around the horizon for at least 2 miles on a clear, dark night. The lights shall flash at 50 or 70 times per minute and be places not less than 1 and not more than 3-5 meters (9.8 - 16 feet) above the water. The lights shall be sufficient in number to clearly show the length and course of the pipeline.
3.3.4 Dredge Pipelines Crossing Navigable Channels
The arrangement of any pipeline crossing a navigable channel shall be
SECTION 31 24 00.00 18 Page 9 approved by the Contracting Officer. Where the pipeline crosses a navigable channel the spacing of the lights shall not be more than 10 meters (33 feet) apart. Two red lights, visible all around the horizon for at least 2 miles on a clear, dark night, shall be displayed at each end of the pipeline, including the ends in a channel where the pipeline is separated to allow vessels to pass (whether open or closed). The lights shall be one meter (3.3 feet) apart in a vertical line with the lower light at the same height above the water as the flashing yellow light.
3.3.5 Submerged Pipelines
Any discharge pipeline submerged to cross a navigation channel shall be submerged so that sufficient depth for navigation exists. Such discharge pipeline shall be marked by signs, lights or other devices to insure safety to navigation by day and by night. All of these devices shall be in complete accordance with Coast Guard regulations.
3.3.6 Road Crossings
A detailed plan of the pipeline route to be used by the Contractor shall be submitted prior to laying of the pipeline. A ramp over any discharge pipeline crossing any roadways at the project site(s) shall be provided.
Additionally, adequate signs (caution and stop, if necessary), and flashing warning lights, shall be provided by the contractor to ensure safety to vehicles and their occupants using the roadway. Under no circumstances shall any portion of the paved portion of any roadway be disturbed. If the roadway is disturbed, the Contractor shall provide an adequate base to allow traffic to pass over the pipeline, and repairs to the roadway after completion of the project area, such that the roadway is restored to a condition equal to or better than the condition prior to disturbance. In addition, prior to placement of the pipeline across any roadway, the Contractor shall contact personnel at the appropriate municipality to determine if the warning signs and lights are adequate for safety purposes.
3.3.7 Towing Vessels
A sufficient number of vessels of adequate size and horsepower, each designed, outfitted, and equipped for towing service, shall be available at all times to move both self- and non-self propelled plant against tides, current, and winds during severe weather conditions.
3.4 DREDGE LOCATION CONTROL
The Contractor is required to have electronic positioning equipment that will accurately compute and plot the position of the dredge. Whenever dredging operations are underway, the location of the dredge shall be continuously monitored and the dredge location, in Long Island Lambert Coordinates, shall be recorded at intervals not to exceed one (1) minute.
Such records, and an accurate map showing actual dredging locations, shall be furnished to the Contracting Officer, or his representative daily as part of the Quality Control Reports. The electronic positioning equipment shall be installed on the dredge so as to monitor, as closely as possible, the actual location of the cutterhead or dragarm. This equipment shall be continuously accessible by the Government representative on board the dredge, who must be able to verify equipment calibration at any time. The electronic positioning equipment shall be required to be calibrated monthly, maintained and operated so that the maximum error for the coordinates recorded do not exceed 3 feet. The location on the dredge of
SECTION 31 24 00.00 18 Page 10 the master antenna and the distance and direction from the master antenna to the cutterhead shall be reported on the Quality Control Reports. No dredging will take place outside the borrow area limits as shown on the drawings. Dredging outside of the borrow area limits will result in immediate shutdown of work. The Contractor's methods of location of the dredge shall be submitted with the quality control plan. Information to be submitted shall include a written description of the equipment, including applicable manufacturers brochure and data, and previous jobs on which the equipment has been used.
3.4.1 Dredging Depth Monitoring Equipment
The Contractor shall have in continuous operation whenever dredging operations are underway, electronic equipment which measures the cutterhead or dragarm depth. The depth measuring device (as approved by the Contracting Officer or Contracting Officer Representative) shall be used and interfaced with the electronic positioning equipment required in Paragraph 3.4. The depth measuring device shall be calibrated by a bar check daily. This equipment shall be accessible to the Government Representative onboard the dredge, who shall be able to verify calibration. Vertical accuracy shall be + or -0.1 foot. Records required for dredge location (Paragraph 3.4) shall also include depth corrected for tide (elevation reference to MLW). Details of the depth measuring device shall be submitted with the quality control plan.
3.5 NOTIFICATION OF ON-SHORE BARGE OPERATION
A minimum of one hour's notice must be furnished by the Contractor to the Contracting Officer, or his representative, and concurrently to the municipal or local agency responsible for beach operations prior to a barge coming on shore between the hours of 9 AM and 7 PM. Barges will not be allowed to come on shore on weekends or State holidays between the hours 9 AM and 7 PM. At no time will a barge be allowed to come on shore in an area other than the immediate work area.
3.6 BUOY REMOVAL
The Contractor shall notify the Coast Guard at least 15 days prior to the date desired for having buoys removed or relocated which interfere with dredging operations. Requests shall be made in writing to:
COMMANDER (OAN)
FIRST COAST GUARD DISTRICT
408 ATLANTIC AVENUE
BOSTON, MASS. 02110
or by telephoning (617) 223 8337
3.7 TEMPORARY FENCES
3.7.1 Land Booster Pumps
If land booster pumps are used, a temporary protective stock mesh wire fence shall be installed by the Contractor around the booster facility.
This fence shall have either wood or steel posts of adequate size installed to the acceptance of the contracting office, and/or his representative, and the wire mesh shall conform to federal specification rr-f221 & int. Am-1, table ix, type ii, style 8, chicken fencing 6'-0" high, 4"x6" mesh, 14 ½ gage wire, design 2672-6 or approved substitute.
The fence shall be removed by the Contractor at the completion of the work
SECTION 31 24 00.00 18 Page 11 or when directed by the contracting officer and/or his representative and all material used shall remain property of the contractor.
3.7.2 Beach Access
Beach access ramps and stairs to the work areas within 500 ft of the designated work area shall be closed by the contractor by erection of a minimum 4 feet high wire mesh snow fence.
The Contractor shall also provide signage at the beach access points indicating "DO NOT ENTER - CONSTRUCTION AREA", as approved by the Contracting Officer.
Ramps, stairs, or other access features requiring closure will be identified during on-site pre-construction meeting between the Corps of Engineers, the Contractor, and local interests.
3.7.3 Sand Fence
Sand fence will be installed on the beach enclosing the 1000-foot long designated work section from the backshore limit of fill to the mean high water line.