Specs-part1.pdf
PDF 16 MB Posted
- Solicitation number
- W912DS19R0005
About this file
Specs Part 1 of 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912DS19R0005-Amendment0002.pdf | ||
| CTC.pdf | ||
| W912DS19R0005-Amendment0001.pdf | ||
| Specs-part2.pdf | ||
| W912DS19R0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building knowledge
Job Order Contract Technical Specifications
Book 1 of 5 CSI Divisions 01 - 07 May 2018
Seneca Army Depot
This Page Intentionally Left Blank
Table of Contents
May 2018 Seneca Army Depot TOC - 1
01 General Requirements
01 22 16 00 No Specification Required 01 32 33 00 Allowances 01 32 33 00a Schedule Of Values 01 32 33 00b Contract Modification Procedure 01 32 33 00c Payment Procedures 01 32 33 00d Special Procedures for Historic Treatment 01 32 33 00e LEED Requirements 01 32 33 00f References 01 32 33 00g Abbreviations, Acronyms, Definitions, and Symbols 01 32 33 00h Cutting and Patching 01 51 13 00 Electrical Renovation 01 51 13 00a Panelboards 01 52 13 00 Temporary Facilities and Controls 01 54 23 00 Scaffolding Tubular Steel 01 54 23 00a Unit Masonry Assemblies 01 56 26 00 Sediment Removal 01 56 26 00a Erosion Control 01 58 13 00 Signage 01 71 23 16 Execution Requirements 01 74 19 00 Construction Waste Management
02 Existing Conditions
02 32 13 00 Subsurface Drilling, Sampling, And Testing 02 41 13 13 Selective Demolition 02 41 13 13a Portland Cement Concrete Removal 02 41 16 13 Building Demolition 02 58 13 00 Farm-Type Wire Fencing 02 58 13 00a Snow And Other Temporary Fencing 02 61 00 00 Excavation And Handling Of Contaminated Material 02 61 13 00 Underground Storage Tank Removal 02 61 13 00a Precision Testing Of Underground Fuel Oil Tanks 02 61 13 00b Hydrostatic Pressure Testing Of Air Receiving Tanks 02 81 00 00 Disposal Of Hazardous Materials 02 82 16 00 Encapsulation (Lock-Down) Of Asbestos-Containing Materials 02 82 33 00 Removal Of Friable Asbestos-Containing Materials 02 82 33 00a Removal Of Nonfriable Asbestos-Containing Materials 02 83 19 13 Removal And Disposal Of Lead-Containing Paint 02 83 19 13a Lead Paint Related Abatement Procedures 02 83 19 13b XRF Testing For Lead-Based Paint 02 83 19 13c Lead Dust Wipe, Air And Tclp Sampling And Analysis 02 84 16 00 Removal of Fluorescent Light Ballasts/Capacitors and Fluorescent Light Tubes 02 84 16 00a Interior Lighting 02 84 16 00b Exterior Lighting 02 84 33 00 Overhead Electrical Distribution 02 87 13 33 Mold Remediation 02 87 16 13 Bird And Bird Waste Abatement
03 Concrete
03 01 30 71 Concrete Rehabilitation 03 05 00 00 Cast-In-Place Concrete 03 11 16 00 Rusticated Concrete Finishes 03 11 16 00a Cast-In-Place Architectural Concrete 03 31 13 00 Cement Concrete Pavement 03 31 13 00a Roller Compacted Concrete Pavement 03 31 13 00b Portland Cement Concrete Overlays 03 31 13 00c Steel Reinforced Portland Cement Concrete Overlays 03 31 13 00d Fiber Reinforced Portland Cement Concrete Overlays 03 31 13 00e Miscellaneous Cast-In-Place Concrete 03 35 23 00 Exposed Aggregate Surface Concrete Walls
TOC - 2 Seneca Army Depot
03 37 13 00 Shotcrete 03 37 13 00a Glass Fiber Reinforced Concrete 03 40 00 00 Tilt-Up Precast Concrete 03 41 16 00 Plant-Precast Structural Concrete 03 41 16 00a Precast Lighweight Roof Slabs 03 41 23 00 Architectural Precast Concrete 03 41 26 00 Unbonded Post-Tensioned Concrete 03 51 13 00 Cementitious Wood-Fiber Deck 03 51 16 00 Gypsum Plank Decking 03 51 16 00a Gypsum Concrete Decks 03 53 00 00 Concrete Floor Topping 03 54 16 00 Cement-Based Underlayment
04 Masonry
04 01 20 51 Clay Masonry Restoration And Cleaning 04 01 40 52 Stone Restoration And Cleaning 04 01 40 91 Stone Masonry 04 23 13 00 Glass Unit Masonry Assemblies 04 41 00 00 Dimension Stone Cladding 04 41 00 00a Interior Stone Facing 04 43 16 00 Stone Flooring 04 72 00 00 Cast Stone
05 Metals
05 05 23 00 Structural Steel 05 12 23 00 Cold-Formed Metal Framing 05 14 16 00 Structural Aluminum 05 15 16 00 Ornamental Metal 05 21 19 00 Steel Joists 05 31 00 00 Steel Deck 05 50 00 00 Metal Fabrications 05 51 13 00 Metal Stairs 05 51 13 00a Fabricated Spiral Stairs 05 52 13 00 Pipe And Tube Railings 05 53 13 00 Gratings 05 58 16 00 Ornamental Formed Metal 05 73 00 00 Miscellaneous Ornamental Metals 05 73 00 00a Ornamental Railings
06 Wood, Plastics, and Composites
06 01 20 91 Wood Restoration 06 05 23 00 Timber Bridge Components 06 05 23 00a Miscellaneous Carpentry 06 05 23 00b Heavy Timber Construction 06 05 73 33 Wood Decking 06 10 00 00 Rough Carpentry 06 11 13 00 Rough Carpentry Renovation 06 15 13 00 Exterior Rough Carpentry 06 16 23 00 Sheathing 06 17 13 00 Structural Glued-Laminated Timber 06 17 33 00 Metal-Plate-Connected Wood Trusses 06 22 13 00 Exterior Finish Carpentry 06 22 13 00a Interior Finish Carpentry 06 25 16 00 Paneling 06 41 13 00 Interior Architectural Woodwork 06 41 13 00a Residential Cabinets 06 42 19 00 Plastic Paneling
Seneca Army Depot TOC - 3
06 46 29 00 Exterior Architectural Woodwork 06 48 13 00 Wood Doors 06 51 13 00 Plastic Lumber 06 51 13 00a Composite Plastic Lumber 06 51 13 00b Structural Plastic Lumber 06 74 13 00 Pultruded Fiberglass Industrial Grating 06 82 00 00 Pultruded Fiberglass Structural Shapes
07 Thermal And Moisture Protection
07 01 50 81 Built-Up Coal-Tar Roofing 07 01 50 81a Membrane Reroofing Preparation 07 05 13 00 CSPE Membrane Roofing 07 05 13 00a APP-Modified Bituminous Membrane Roofing 07 05 13 00b SBS-Modified Bituminous Membrane Roofing 07 11 13 00 Bituminous Dampproofing 07 13 13 00 Bituminous Waterproofing 07 13 53 00 Self-Adhering Sheet Waterproofing 07 13 53 00a Elastomeric Sheet Waterproofing 07 14 13 00 Hot Fluid-Applied Rubberized Asphalt Waterproofing 07 14 16 00 Cold Fluid-Applied Waterproofing 07 16 13 00 Modified Cement Waterproofing 07 16 16 00 Crystalline Waterproofing 07 16 19 00 Metal-Oxide Waterproofing 07 17 13 00 Bentonite Waterproofing 07 19 13 00 Water Repellents 07 21 13 13 Building Insulation 07 21 13 13a Modified Bitumous Protected Membrane Roofing 07 22 16 00 Fluid-Applied Protected Membrane Roofing 07 24 13 00 Polymer-Based Exterior Insulation And Finish System (EIFS) 07 24 13 00a Water-Drainage Exterior Insulation and Finish System (EIFS) 07 31 13 00 Asphalt Shingles 07 31 16 00 Metal Shingles 07 31 26 00 Slate Shingles 07 31 29 13 Wood Shingles And Shakes 07 31 33 00 Composite Rubber Shingles 07 32 13 00 Clay Roof Tiles 07 32 16 00 Concrete Roof Tiles 07 41 13 00 Metal Roof Panels 07 41 13 00a Sheet Metal Roofing 07 42 13 19 Glazing 07 46 16 00 Metal Wall Panels 07 46 16 00a Metal Plate Wall Panels 07 46 16 00b Siding 07 46 63 00 Insulated-Core Metal Wall Panels 07 51 13 00 Built-Up Asphalt Roofing 07 53 16 00 EPDM Membrane Roofing 07 54 19 00 Polyvinyl-Chloride (PVC) Roofing 07 54 23 00 Thermoplastic Polyolefin (TPO) Roofing 07 56 00 00 Coated Foamed Roofing 07 62 00 00 Sheet Metal Flashing And Trim 07 63 00 00 Common Work Results for Plumbing 07 71 23 00 Manufactured Roof Specialties 07 72 13 00 Packaged, Outdoor, Central-Station Air-Handling Units 07 72 13 00a Intake and Relief Ventilators 07 72 23 00 Roof Accessories 07 72 56 00 Radiant-Heating Electric Cables 07 72 56 00a Heat Tracing for Fire-Suppression Piping 07 72 56 00b Heat Tracing for Plumbing Piping 07 72 56 00c Heat Tracing for HVAC Piping 07 81 16 00 Sprayed Fire-Resistive Materials 07 82 00 00 Board Fire Protection 07 84 13 16 Through-Penetration Firestop Systems 07 84 13 16a Fire-Resistive Joint Systems 07 84 13 16b Firestopping 07 91 23 00 Joint Sealants 07 95 13 13 Architectural Joint Systems 07 95 13 16 Roof Expansion Assemblies
TOC - 4 Seneca Army Depot
08 Openings
08 01 11 61 Steel Doors And Frames 08 01 11 61a Steel Entry Doors 08 01 52 61 Wood Windows 08 05 13 00 Stainless Steel Doors And Frames 08 05 13 00a Flush Wood Doors 08 11 63 13 Steel Storm Doors 08 11 63 13a Security Window Screens and Doors 08 11 63 23 Aluminum Storm Doors 08 11 73 00 Sliding Metal Fire Doors 08 14 16 00 Stile And Rail Wood Doors 08 16 13 00 Fiberglass Reinforced Plastic (FRP) Doors and Frames 08 31 13 00 Access Doors And Frames 08 32 13 00 Sliding Aluminum-Framed Glass Doors 08 32 19 00 Sliding Wood-Framed Glass Doors 08 33 23 00 Overhead Coiling Doors 08 33 23 00a Overhead Coiling Grilles 08 33 36 00 Side Coiling Grilles 08 34 49 13 Radiation Protection 08 34 53 00 Security Grilles 08 34 56 00 Detention Doors And Frames 08 34 59 00 Security Vault Doors 08 34 59 00a Vault Doors and Day Gates 08 34 59 00b Modular Vaults 08 34 73 16 Sound Control Doors 08 35 13 13 Folding Doors 08 36 13 00 Sectional Overhead Doors 08 36 23 00 Vertical Lift Doors 08 38 13 00 Flexible Doors 08 42 13 00 Aluminum-Framed Entrances And Storefronts 08 42 26 00 All-Glass Entrances And Storefronts 08 42 29 23 ICU/CCU Entrance Doors 08 42 33 00 Revolving Entrance Doors 08 44 13 00 Glazed Aluminum Curtain Walls 08 44 13 00a Structural-Sealant-Glazed Curtain Walls 08 44 13 00b Sloped Glazing Assemblies 08 45 23 00 Unit Skylights 08 45 23 00a Metal-Framed Skylights 08 45 23 00b Structured-Polycarbonate-Panel Assemblies 08 45 23 00c Fiberglass-Sandwich-Panel Assemblies 08 51 13 00 Aluminum Windows 08 51 13 00a Aluminum Replacement Windows 08 51 23 00 Steel Windows 08 51 69 00 Aluminum Storm Windows 08 53 13 00 Vinyl Windows 08 56 19 00 Security Windows 08 62 00 00 Roof Windows 08 71 23 00 Door Hardware 08 71 23 00a Detention Door Hardware 08 75 00 00 Automatic Door Operators 08 83 13 00 Mirrors 08 84 00 00 Plastic Glazing 08 87 23 16 Fragment Retention Film For Glass 08 88 53 00 Security Glazing 08 90 00 00 Louvers And Vents
09 Finishes
09 01 60 91 Portland Cement Terrazzo Flooring 09 01 60 91a Carpet 09 22 13 00 Gypsum Plaster
Seneca Army Depot TOC - 5
09 22 13 00a Gypsum Veneer Plaster 09 22 13 00b Portland Cement Plaster 09 22 16 13 Non-Load-Bearing Steel Framing 09 22 36 23 Lath and Plaster Renovation 09 23 13 00 Gypsum Board Renovation 09 28 13 00 Gypsum Board 09 28 13 00a Gypsum Board Shaft-Wall Assemblies 09 31 00 00 Ceramic Tile 09 51 13 00 Acoustical Panel Ceilings 09 51 23 00 Acoustical Tile Ceilings 09 54 23 00 Acoustical Metal Pan Ceilings 09 54 23 00a Linear Metal Ceilings 09 63 13 00 Brick Flooring 09 64 13 00 Wood Flooring 09 64 23 00 Wood Sports-Floor Assemblies 09 65 13 13 Cork Flooring 09 65 13 13a Resilient Wall Base And Accessories 09 65 13 33 Resilient Floor Tile 09 65 13 33a Resilient Sheet Flooring 09 65 13 33b Linoleum Floor Coverings 09 65 66 00 Fluid-Applied Athletic Flooring 09 65 66 00a Resilient Sports-Floor Coverings 09 66 23 00 Resinous Matrix Terrazzo Flooring 09 67 16 00 Resinous Flooring 09 68 13 00 Carpet Tile 09 69 13 00 Access Flooring 09 69 33 00 Cable Management System 09 72 13 00 Wall Coverings 09 84 13 00 Acoustical Wall Panels 09 91 13 00 Exterior Painting 09 91 13 00a Wood Stains and Transparent Finishes 09 91 13 00b High-Temperature-Resistant Coatings 09 91 23 00 Interior Painting 09 91 23 00a Multicolored Interior Coatings 09 93 23 53 Floor Treatment Refinishing Wood Floors 09 96 00 00 High-Performance Coatings 09 96 46 00 Intumescent Paints 09 96 56 00 Fiberglass Reinforced Epoxy Coating 09 96 66 00 Cementitious Coatings
10 Specialties
10 11 13 13 Visual Display Surfaces 10 13 16 00 Directories 10 14 00 00 Vitrified Brick Pavement Replacement 10 14 53 00 Traffic Signs 10 17 16 13 Telephone Specialties 10 21 13 13 Toilet Compartments 10 21 13 19 Solid Surface Material Toilet Compartments 10 21 16 17 Shower and Dressing Compartments 10 21 16 17a Cubicle Curtains and Tracks 10 22 13 00 Wire Mesh Partitions 10 22 19 13 Demountable Partitions 10 22 43 00 Operable Panel Partitions 10 26 13 00 Impact-Resistant Wall Protection 10 28 13 13 Toilet And Bath Accessories 10 28 13 13a Detention Toilet Accessories 10 28 16 13 Bath Accessories 10 28 19 16 Plumbing Fixtures 10 44 13 00 Fire Protection Cabinets 10 44 16 13 Fire Extinguishers 10 51 13 00 Metal Lockers 10 51 13 00a Wire Basket Lockers 10 51 26 00 Solid Plastic Lockers 10 55 23 23 Postal Specialties 10 56 13 16 Metal Storage Shelving 10 71 13 13 Exterior Shutters 10 73 13 13 Awnings
TOC - 6 Seneca Army Depot
10 73 26 13 Extruded Aluminum Walkway Cover 10 75 16 00 Flagpoles 10 81 13 00 Oriented Flexible Netting Bird Barrier 10 86 00 00 Detention Furniture
11 Equipment
11 11 33 00 Paint Spray Booths 11 12 16 00 Parking Control Equipment 11 12 16 00a Prefabricated Control Booths 11 13 13 00 Loading Dock Equipment 11 14 13 16 Turnstiles 11 21 63 00 Food Service Equipment 11 30 13 13 Residential Appliances 11 30 13 13a Refrigerators 11 30 13 13b Gas Ranges 11 30 13 13c Electric Ranges 11 32 13 00 Unit Kitchens 11 41 33 00 Residential Casework 11 52 13 13 Projection Screens 11 53 13 00 Laboratory Fume Hoods 11 61 23 00 Folding And Portable Stages 11 66 13 00 Playground Equipment And Structures 11 66 13 00a Recreational Facilities 11 66 13 00b Gymnasium Equipment 11 66 53 00 Gymnasium Dividers 11 68 23 13 Playing Fields 11 82 19 00 Packaged Incinerators 11 82 26 00 Waste Compactors 11 98 12 00 Detention Enclosures
12 Furnishings
12 01 60 00 Fixed Audience Seating 12 21 13 13 Horizontal Louver Blinds 12 21 13 13a Vertical Louver Blinds 12 22 13 00 Draperies and Tracks 12 24 13 00 Roller Shades 12 24 13 00a Pleated Shades 12 36 23 13 Stone Countertops 12 36 61 16 Solid Polymer Fabrications 12 48 13 13 Floor Mats And Frames 12 48 13 13a Foot Grilles 12 56 53 00 Laboratory Casework 12 59 13 00 Systems Furniture 12 62 23 00 Portable Bleachers 12 66 13 00 Telescoping Stands
13 Special Construction
13 12 13 00 Water Distribution 13 27 53 16 Floor Safes 13 34 16 13 Fixed Wood Bleachers (Exterior) 13 34 16 13a Demountable Bleachers (Exterior) 13 34 16 13b Grandstands And Bleachers 13 34 19 00 Metal Building Systems 13 42 63 16 Security Ceiling Systems 13 47 13 13 Cathodic Protection
Seneca Army Depot TOC - 7
14 Conveying Equipment
14 01 20 71 Electric Traction Elevators 14 01 20 71a Hydraulic Elevators 14 11 00 00 Dumbwaiters 14 24 13 00 Hydraulic Freight Elevators 14 26 00 00 Limited-Use/Limited-Application Elevators 14 31 00 00 Escalators 14 41 16 00 Personnel Lifts 14 42 13 00 Wheelchair Lifts 14 45 13 00 Vehicle Lifts 14 91 33 00 Chutes
21 Fire Suppression
21 05 00 00 Common Motor Requirements for Fire Suppression Equipment 21 05 13 00 Common Work Results for Fire Suppression 21 05 13 00a Vibration And Seismic Controls For Fire-Suppression Piping And Equipment 21 05 19 00 Fire-Suppression Systems Insulation 21 05 19 00a Meters and Gages for Plumbing Piping 21 05 19 00b Meters and Gages for HVAC Piping 21 11 19 00 Fire-Suppression Standpipes 21 12 29 00 Piped Utilities Basic Materials And Methods 21 13 13 00 Wet-Pipe Fire-Suppression Sprinklers 21 13 16 00 Dry-Pipe Fire-Suppression Sprinklers 21 13 39 00 Foam Fire Extinguishing 21 16 00 00 Pressure-Maintenance Pumps 21 16 00 00a Controllers for Fire-Pump Drivers 21 22 16 00 Clean-Agent Extinguishing Systems 21 24 00 00 Fiberglass Reinforced Polyester (FRP) Flush Doors 21 30 00 00 Electric-Drive, Centrifugal Fire Pumps 21 30 00 00a Diesel-Drive, Centrifugal Fire Pumps 21 31 13 00 Electric-Drive, Vertical-Turbine Fire Pumps 21 31 16 00 Diesel-Drive, Vertical-Turbine Fire Pumps
22 Plumbing
22 01 40 81 Emergency Plumbing Fixtures 22 05 13 00 Common Motor Requirements for Plumbing Equipment 22 05 48 13 Vibration And Seismic Controls For Plumbing Piping And Equipment 22 05 53 00 Identification for Plumbing Piping and Equipment 22 05 76 00 Sanitary Sewerage 22 05 76 00a Storm Drainage Piping Specialties 22 07 19 00 Plumbing Insulation 22 11 16 00 Domestic Water Piping 22 11 16 00a Sanitary Waste And Vent Piping 22 11 16 00b Storm Drainage Piping 22 11 16 00c Hydronic Piping 22 11 16 00d Steam And Condensate Piping 22 11 16 00e Refrigerant Piping 22 11 16 00f General-Service Compressed-Air Piping 22 11 16 00g Compressed-Air Piping For Laboratory And Healthcare Facilities 22 11 16 00h Vacuum Piping For Laboratory And Healthcare Facilities 22 11 16 00i Gas Piping For Laboratory And Healthcare Facilities 22 11 16 00j Chemical-Waste Systems for Laboratory and Healthcare Facilities 22 11 19 00 Electronic Air Cleaners 22 11 23 13 Water Distribution Pumps 22 11 23 13a Packaged Booster Pumps 22 11 23 23 Water Supply Wells 22 11 23 23a Hydronic Pumps 22 12 19 00 Surface Water-Storage Tanks 22 12 19 00a Potable-Water Storage Tanks
TOC - 8 Seneca Army Depot
22 12 23 13 Electric, Domestic Water Heaters 22 12 23 13a Fuel-Fired, Domestic Water Heaters 22 13 19 00 High-Efficiency Particulate Filtration 22 13 19 26 Interceptors 22 13 19 33 General-Duty Valves for Plumbing Piping 22 13 19 33a General-Duty Valves for HVAC Piping 22 13 29 13 Packaged Sewage Pumping Stations 22 13 29 13a Lift Station 22 13 29 13b Sewage Pumps 22 14 29 13 Sump Pumps 22 15 13 00 General-Service Packaged Air Compressors and Receivers 22 31 16 00 Water Softeners 22 35 23 00 Domestic Water Heat Exchangers 22 42 19 00 Porcelain Steel Bathtub Liners and Surrounds 22 43 00 00 Medical Plumbing Fixtures 22 46 13 13 Security Plumbing Fixtures 22 47 13 00 Drinking Fountains And Water Coolers
23 Heating, Ventilating, And Air-Conditioning (HVAC)
23 01 10 91 Sequence Of Operation 23 01 10 91a Testing, Adjusting, And Balancing 23 01 30 51 Air Duct Cleaning 23 05 13 00 Common Work Results for HVAC 23 05 16 00 Expansion Fittings and Loops for Plumbing Piping 23 05 16 00a Expansion Fittings and Loops for HVAC Piping 23 05 29 00 Steam Distribution 23 05 29 00a Hangers and Supports for Plumbing Piping and Equipment 23 05 29 00b Hangers and Supports for HVAC Piping and Equipment 23 05 48 13 Vibration And Seismic Controls For HVAC Piping And Equipment 23 05 53 00 Identification for HVAC Piping and Equipment 23 05 93 00 Processed Water Piping 23 07 13 00 HVAC Insulation 23 09 00 00 HVAC Instrumentation And Controls 23 11 23 00 Relief Wells 23 11 23 00a Monitoring Wells 23 11 23 00b Facility Natural-Gas Piping 23 11 23 00c Facility Liquefied-Petroleum Gas Piping 23 13 23 16 Facility Fuel-Oil Piping 23 21 13 23 Radiant Heating Piping 23 22 23 13 Steam Condensate Pumps 23 25 13 00 HVAC Water Treatment 23 31 13 13 Metal Ducts 23 31 13 13a HVAC Casings 23 31 13 16 Tailpipe Exhaust Equipment 23 31 13 33 Duct Accessories 23 31 16 13 Nonmetal Ducts 23 33 13 13 Draft Control Devices 23 34 13 00 Axial Fans 23 34 16 00 Centrifugal Fans 23 34 16 00a Power Ventilators 23 34 33 00 Air Curtains 23 36 13 00 Diffusers, Registers, And Grilles 23 41 13 00 Particulate Air Filtration 23 42 13 00 Gas-Phase Air Filtration 23 44 00 00 Interlocking Resilient Flooring 23 51 13 13 Breechings, Chimneys, And Stacks 23 52 13 00 Electric Boilers 23 52 23 00 Cast-Iron Boilers 23 52 33 16 Condensing Boilers 23 52 33 16a Water-Tube Boilers 23 52 36 00 Fire-Tube Boilers 23 53 16 00 Feedwater Equipment 23 53 16 00a Deaerators 23 54 16 13 Furnaces 23 55 23 13 Radiant Heating and Cooling Units
Seneca Army Depot TOC - 9
23 55 23 13a Radiant-Heating Electric Panels 23 55 33 00 Fuel-Fired Unit Heaters 23 55 33 00a Unit Heaters 23 57 13 00 Heat Exchangers 23 61 16 00 Centrifugal Water Chillers 23 61 16 00a Rotary-Screw Water Chillers 23 62 13 00 Indirect-Fired Absorption Water Chillers 23 63 13 00 Condensing Units 23 63 13 00a Air-Cooled Condensers 23 63 13 00b Split-System Air-Conditioning Units 23 64 13 16 Direct-Fired Absorption Water Chillers 23 64 16 16 Fan-Coil Units 23 64 23 00 Reciprocating Water Chillers 23 64 23 00a Scroll Water Chillers 23 65 13 00 Cooling Towers 23 72 13 00 Air-To-Air Energy Recovery Units 23 74 16 00 Modular Indoor Central-Station Air-Handling Units 23 74 16 00a Rooftop Replacement Air Units 23 74 16 00b Self-Contained Air-Conditioners 23 74 23 13 Direct-Fired, Makeup Air Units 23 74 23 13a Indirect-Fired, Packaged H&V Units 23 81 13 11 Packaged Terminal Air Conditioners 23 81 23 00 Computer-Room Air-Conditioners 23 82 16 00 Air Coils 23 82 16 00a Unit Ventilators 23 82 29 00 Convection Heating Units 23 84 13 00 Humidifiers 23 84 16 33 Dehumidification Units
26 Electrical
26 05 00 00 Common Work Results for Electrical 26 05 13 00 Conductors And Cables 26 05 13 00a Undercarpet Cables 26 05 13 00b Medium-Voltage Cables 26 05 19 13 Raceways And Boxes 26 05 19 13a Underfloor Raceways For Electrical Systems 26 05 19 16 Common Work Results for Communications 26 05 19 16a Common Work Results for Electronic Safety and Security 26 05 19 16b Control-Voltage Electrical Power Cables 26 05 19 16c Communications Equipment Room Fittings 26 05 19 16d Communications Backbone Cabling 26 05 19 16e Communications Horizontal Cabling 26 05 19 16f Conductors and Cables for Electronic Safety and Security 26 05 19 23 Monorails With Electric Powered Hoists 26 05 19 23a Cranes, Overhead Electric, Underrunning (Under 20,000 Pounds) 26 05 26 00 Lightning Protection 26 05 26 00a Grounding And Bonding 26 05 29 00 Hangers And Supports For Electrical Systems 26 05 29 00a Vibration And Seismic Controls For Electrical Systems 26 05 33 16 Wiring Devices 26 05 36 00 Cable Trays 26 05 53 00 Electrical Identification 26 09 23 00 Lighting Controls 26 09 23 00a Lighting Control Devices 26 09 23 00b Electrical Power Monitoring And Control 26 09 23 00c Motor-Control Centers 26 09 23 00d Central Dimming Controls 26 09 23 00e Modular Dimming Controls 26 11 13 00 Secondary Unit Substations 26 11 16 00 Switchgear 26 12 13 00 Medium-Voltage Transformers 26 12 13 00a Low-Voltage Transformers 26 24 13 00 Electricity Metering 26 24 13 00a Enclosed Switches And Circuit Breakers 26 24 13 00b Switchboards 26 24 19 00 Enclosed Controllers 26 24 19 00a Power Distribution Units
TOC - 10 Seneca Army Depot
26 25 00 00 Enclosed Bus Assemblies 26 28 13 00 Fuses 26 29 23 00 Variable Frequency Controllers 26 31 00 00 Photovoltaic Energy Equipment 26 32 13 13 Packaged Engine Generators 26 33 43 00 Central Battery Inverters 26 33 43 00a Nurse Call 26 33 43 00b Public Address and Mass Notification Systems 26 33 53 00 Static Uninterruptible Power Supply 26 35 33 00 Power Factor Correction Capacitors 26 36 13 00 Transfer Switches 26 43 13 00 Transient Voltage Suppression 26 55 61 00 Stage Lighting 26 55 68 00 Exterior Athletic Lighting
27 Communications
27 05 26 00 Intercommunications and Program Systems 27 11 19 00 Loose-Tube Gel-Filled Fiber Optic Cables 27 51 33 00 Educational Intercommunications and Program Systems 27 53 13 00 Clock And Program Control
28 Electronic Safety And Security
28 16 11 00 Perimeter Security 28 16 11 00a Intrusion Detection 28 16 11 00b Security Access 28 21 00 00 Video Surveillance 28 46 00 00 Oil/Water Separator 28 46 21 33 Digital, Addressable Fire-Alarm System 28 46 21 33a Zoned (DC Loop) Fire-Alarm System
31 Earthwork
31 05 13 00 Earthwork 31 05 13 00a Subdrainage 31 11 00 00 Site Clearing 31 13 13 00 Tree Protection And Trimming 31 23 16 13 Excavation Support And Protection 31 23 16 26 Embankment 31 23 19 00 Dewatering 31 24 13 00 Levee Closure 31 25 14 13 Geosynthetic Fabric 31 25 14 23 Unit Pavers 31 25 14 26 Silt Fences 31 31 16 13 Termite Control 31 31 19 13 Soil Sterilization 31 32 13 16 Soil Stabilization-Lime 31 32 13 19 Soil Stabilization-Vibroflotation 31 32 19 16 Sewage Treatment Lagoons 31 32 19 16a Pond Reservoir Liners 31 36 13 00 Wire Mesh Gabions 31 37 00 00 Riprap 31 41 13 00 Drilled Piers 31 62 13 23 Prestressed Concrete Piles 31 62 16 16 Steel H Piles 31 62 19 00 Timber Piles 31 62 23 13 Concrete-Filled Steel Piles 31 66 15 00 Resistance Pier Systems
Seneca Army Depot TOC - 11
32 Exterior Improvements
32 01 11 53 Asphalt Paving 32 01 11 53a Pavement Joint Sealants 32 01 11 53b Traffic Coatings 32 01 13 62 Crack Sealing Of Bituminous Pavements 32 01 13 62a Spray Applications, Seal Coats, And Surface Treatments 32 01 16 71 Grinding/Grooving Pavement 32 01 16 71a Cold Mix Recycling 32 01 16 74 Bituminous Rejuvenation 32 01 16 74a Central Plant Hot-Mix Recycling 32 11 16 16 Crushed Stone Paving 32 11 16 16a Crushed Stone 32 11 16 16b Select Gravel 32 11 26 19 Asphaltic Concrete Overlays 32 12 13 13 Bituminous Paving-Repair And Resurfacing 32 13 13 33 Decorative Cement Concrete Pavement 32 14 09 00 Exterior Plants 32 14 11 00 Asphalt Concrete Sidewalks 32 14 11 00a Miscellaneous Sidewalks 32 14 11 00b Precast Sidewalks And Pavers 32 14 33 00 Porous Unit Paving 32 16 13 13 Steel Curbs 32 17 23 13 Track, Court, And Playground Markings 32 17 26 00 Tactile/Detectable Warning Tile 32 18 16 13 Playground Surface Systems 32 18 16 13a Synthetic Running Track Surface 32 18 23 13 Lawns And Grasses 32 18 23 29 Colored Athletic Wearing Surface 32 18 23 29a Synthetic Turf 32 31 13 13 Chain-Link Fences And Gates 32 31 13 53 High-Security Chain-Link Fences And Gates 32 31 19 00 Ornamental Metal Fences and Gates 32 31 29 00 Permanent Wood Fencing 32 32 13 00 Segmental Retaining Walls 32 33 13 00 Miscellaneous Site and Street Furnishings 32 33 23 00 Site Furnishings 32 84 13 00 Irrigation Systems 32 91 13 16 Tree Relocation 32 91 19 13 Concrete Revetment 32 91 19 13a Septic Tank Systems
33 Utilities
33 01 10 58 Repair And Maintenance Of Imhoff Tanks 33 01 10 58a Sewer Line Cleaning 33 01 30 42 Repair And Maintenance Of Siphon Tank And Siphons 33 01 30 79 Pipe Lining 33 01 30 81 Underground Ducts And Utility Structures 33 05 07 13 Trenchless Excavation Using Microtunneling 33 11 13 00 Well Repair 33 14 13 23 Sand Drains 33 14 13 23a Hydronic Distribution 33 14 13 23b Ground-Loop Heat-Pump Piping 33 42 11 00 Storm Drainage 33 42 13 13 Culverts
34 Transportation
34 41 13 00 Electrical Traffic Control Signals
TOC - 12 Seneca Army Depot
34 71 13 13 Beam-Type Guardrail 34 71 13 16 Active Vehicle Barriers
35 Waterway and Marine Construction
35 22 26 00 Sluice Gate
41 Material Processing And Handling Equipment
41 22 23 13 Material Handling Hoists 41 22 23 13a Monorails With Air Motor Powered Hoist 41 22 23 13b Monorails With Manual Hoist 41 22 23 23 Ash Hoists
01 - General Requirements
May 2018 No Specification Required Seneca Army Depot 01 22 16 00 - 1
SECTION 01 22 16 00 - NO SPECIFICATION REQUIRED
1.1 GENERAL
A. A separate specification is not required for this item. The description given in the line item of the Construction Task Catalog completely defines the item.
1.2 PRODUCTS - (Not Used)
1.3 EXECUTION - (Not Used)
END OF SECTION 01 22 16 00
No Specification Required May 2018
01 22 16 00 - 2 Seneca Army Depot
THIS PAGE INTENTIONALLY LEFT BLANK
Seneca Army Depot 01 22 20 00 to 01 22 23 00 - 1
Task Specification Specification Description 01 22 20 00 01 22 16 00 No Specification Required 01 22 23 00 01 22 16 00 No Specification Required
01 22 20 00 to 01 22 23 00 - 2 Seneca Army Depot
May 2018 Allowances Seneca Army Depot 01 32 33 00 - 1
SECTION 01 32 33 00 - ALLOWANCES
A. Summary
1. This Section includes administrative and procedural requirements governing the following:
a. Lump-sum allowances.
b. Unit-cost allowances.
c. Quantity allowances.
d. Contingency allowances.
e. Testing and inspecting allowances.
2. See Division 1 Section "Unit Prices" for procedures for using unit prices.
3. See Division 1 Section "Quality Requirements" for procedures governing the use of allowances for testing and inspecting.
B. Selection And Purchase
1. At the earliest practical date after award of the Contract, advise the Contracting Officer of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work.
2. At the Contracting Officer's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work.
3. Purchase products and systems selected by the Contracting Officer from the designated supplier.
C. Submittals
1. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders.
2. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
3. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
D. Coordination
1. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.
E. Lump-Sum, Unit-Cost, and Quantity Allowances
1. Allowance shall include cost to Contractor of specific products and materials ordered by Owner under allowance and shall include taxes, freight, and delivery to Project site.
2. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by Owner under allowance shall be included as part of the Contract Sum and not part of the allowance.
F. Contingency Allowances
1. Use the contingency allowance only as directed for Owner's purposes and only by Change
Orders that indicate amounts to be charged to the allowance.
2. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, taxes, insurance, equipment rental, and similar costs.
3. Change Orders authorizing use of funds from the contingency allowance will include Contractor's related costs and reasonable overhead and profit margins.
4. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order.
Allowances May 2018
01 32 33 00 - 2 Seneca Army Depot
G. Testing And Inspecting Allowances
1. Testing and inspecting allowances include the cost of engaging testing agencies, actual tests and inspections, and reporting results.
2. The allowance does not include incidental labor required to assist the testing agency or costs for retesting if previous tests and inspections result in failure. The cost for incidental labor to assist the testing agency shall be included in the Contract Sum.
3. Costs of services not required by the Contract Documents are not included in the allowance.
4. At Project closeout, credit unused amounts remaining in the testing and inspecting allowance to
Owner by Change Order.
H. Unused Materials
1. Return unused materials purchased under an allowance to manufacturer or supplier for credit to
Owner, after installation has been completed and accepted.
a. If requested by the Contracting Officer, prepare unused material for storage by Owner when it is not economically practical to return the material for credit. If directed by the Contracting Officer, deliver unused material to Owner's storage space. Otherwise, disposal of unused material is Contractor's responsibility.
1.2 PRODUCTS (Not Used)
1.3 EXECUTION
A. Examination
1. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
B. Preparation
1. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
C. Schedule Of Allowances
1. Allowance No. <Insert number>: Include <Insert allowance description> as specified in
Division <Insert Division number> Section "<Insert Section title>" and as indicated in the Construction Task Catalog, <Insert line item number>..
END OF SECTION 01 32 33 00
May 2018 Schedule Of Values Seneca Army Depot 01 32 33 00a - 1
SECTION 01 32 33 00a - SCHEDULE OF VALUES
A. Description Of Work
1. This specification covers the preparation, content and submittal of the schedule of values. The
Schedule of Values is an itemized list that establishes the value or cost of each part of the Work.
It shall be used as the basis for preparing progress payments.
B. Preparation
1. Schedule shall show breakdown of labor, materials equipment and other costs as directed by the
Contracting Officer.
2. Costs shall be in sufficient detail to indicate separate amounts for each major subsection of the
Work. The Contractor may include an item for bond, insurance, temporary facilities and job mobilization.
3. Schedule of Values shall be prepared on 8-1/2-inch by 11-inch white paper.
4. Use the major subsections of the Detailed Scope of Work as the basis for Schedule format. List sub-items of major products or systems as appropriate or when requested by the Contracting Officer.
5. When requested by the Contracting Officer, support values with data that will substantiate their correctness.
6. The sum of the individual values shown on the Schedule of Values must equal the total Job Order Price.
7. Schedule shall show the purchase and delivery costs for materials and equipment that the Contractor anticipates it shall request payment for prior to their installation.
C. Submittal: Submit two copies of Schedule, or any other number of copies as directed by the Contracting Officer, to the Contracting Officer for approval at least 20 days prior to submitting first application for a progress payment. After review by the Contracting Officer, revise and resubmit Schedule as required until it is approved.
1.2 PRODUCTS (Not Used)
1.3 EXECUTION (Not Used)
END OF SECTION 01 32 33 00a
Schedule Of Values May 2018
01 32 33 00a - 2 Seneca Army Depot
May 2018 Contract Modification Procedure Seneca Army Depot 01 32 33 00b - 1
SECTION 01 32 33 00b - CONTRACT MODIFICATION PROCEDURE
A. Summary
1. This Section specifies administrative and procedural requirements for handling and processing
Contract modifications.
2. See Division 1 Section "Allowances" for procedural requirements for handling and processing allowances.
B. Minor Changes In The Work
1. Architect will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions."
C. Proposal Requests
1. Owner-Initiated Proposal Requests: the Contracting Officer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
a. Proposal Requests issued are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.
b. Within time specified in Proposal Request OR 20 days, as directed, after receipt of
Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
1) Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
2) Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
3) Include costs of labor and supervision directly attributable to the change.
4) Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
2. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to the Contracting Officer.
a. Include a statement outlining reasons for the change and the effect of the change on the
Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
b. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
c. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
d. Include costs of labor and supervision directly attributable to the change.
e. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
f. Comply with requirements in Division 1 Section "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.
Contract Modification Procedure May 2018
01 32 33 00b - 2 Seneca Army Depot
3. Proposal Request Form: Use AIA Document G709 for Proposal Requests OR forms provided by Owner, as directed.
D. Allowances
1. Allowance Adjustment: To adjust allowance amounts, base each Change Order proposal on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.
a. Include installation costs in purchase amount only where indicated as part of the allowance.
b. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed.
c. Submit substantiation of a change in scope of work, if any, claimed in Change Orders related to unit-cost allowances.
d. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
2. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the Purchase Order amount or Contractor's handling, labor, installation, overhead, and profit. Submit claims within <Insert number> days of receipt of the Change Order or Construction Change Directive authorizing work to proceed.
Owner will reject claims submitted later than <Insert number> days after such authorization.
a. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents.
b. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.
E. Change Order Procedures
1. On Owner's approval of a Proposal Request, the Contracting Officer will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.
F. Construction Change Directive
1. Construction OR Work, as directed, Change Directive: the Contracting Officer may issue a
Construction OR Work, as directed, Change Directive on AIA Document G714 OR EJCDC Document 1910-8-F, as directed. Construction OR Work, as directed, Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
a. Construction OR Work, as directed, Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
2. Documentation: Maintain detailed records on a time and material basis of work required by the Construction OR Work, as directed, Change Directive.
a. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
1.2 PRODUCTS (Not Used)
END OF SECTION 01 32 33 00b
May 2018 Payment Procedures Seneca Army Depot 01 32 33 00c - 1
SECTION 01 32 33 00c - PAYMENT PROCEDURES
A. Summary
1. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. Schedule Of Values
1. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's
Construction Schedule. Cost-loaded CPM Schedule may serve to satisfy requirements for the Schedule of Values.
a. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Application for Payment forms with Continuation Sheets, Submittals Schedule, and Contractor's Construction Schedule.
b. Submit the Schedule of Values to the Contracting Officer at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment.
c. Subschedules: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values correlated with each phase of payment.
2. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.
a. Identification: Include the following Project identification on the Schedule of Values:
1) Project name and location.
2) Name of Architect.
3) Architect's project number.
4) Contractor's name and address.
5) Date of submittal.
b. Submit draft of AIA Document G703 Continuation Sheets OR EJCDC Document 1910-8-E, as directed.
c. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate.
d. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
e. Provide a separate line item in the Schedule of Values for each part of the Work where
Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
f. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
g. Allowances: Provide a separate line item in the Schedule of Values for each allowance.
Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.
h. Each item in the Schedule of Values and Applications for Payment shall be complete.
Include total cost and proportionate share of general overhead and profit for each item.
1) Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.
i. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.
C. Applications For Payment
Payment Procedures May 2018
01 32 33 00c - 2 Seneca Army Depot
1. Each Application for Payment shall be consistent with previous applications and payments as certified by the Contracting Officer and paid for by Owner.
a. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.
2. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.
3. Payment Application Forms: Use AIA Document G702 and AIA Document G703 Continuation Sheets OR AIA Document G702/CMa and AIA Document G703 Continuation Sheets OR EJCDC Document 1910-8-E OR forms provided by Owner, as directed, as form for Applications for Payment.
4. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. the Contracting Officer will return incomplete applications without action.
a. Entries shall match data on the Schedule of Values and Contractor's Construction
Schedule. Use updated schedules if revisions were made.
b. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
5. Transmittal: Submit 3 signed and notarized original copies of each Application for Payment to
Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.
a. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
6. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from every entity who is lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.
a. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
b. When an application shows completion of an item, submit final or full waivers.
c. Owner reserves the right to designate which entities involved in the Work must submit waivers.
d. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to
Owner.
7. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
a. List of subcontractors.
b. Schedule of Values.
c. Contractor's Construction Schedule (preliminary if not final).
d. Schedule of unit prices.
e. Submittals Schedule (preliminary if not final).
f. List of Contractor's staff assignments.
g. List of Contractor's principal consultants.
h. Copies of building permits.
i. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
j. Initial progress report.
k. Report of preconstruction conference.
l. Certificates of insurance and insurance policies.
8. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
a. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
b. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
May 2018 Payment Procedures Seneca Army Depot 01 32 33 00c - 3
9. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
a. Evidence of completion of Project closeout requirements.
b. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
c. Updated final statement, accounting for final changes to the Contract Sum.
d. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."
e. AIA Document G706A, "Contractor's Affidavit of Release of Liens."
f. AIA Document G707, "Consent of Surety to Final Payment."
g. Evidence that claims have been settled.
h. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.
i. Final, liquidated damages settlement statement.
1.2 PRODUCTS (Not Used)
END OF SECTION 01 32 33 00c
Payment Procedures May 2018
01 32 33 00c - 4 Seneca Army Depot
May 2018 Special Procedures for Historic Treatment Seneca Army Depot 01 32 33 00d - 1
SECTION 01 32 33 00d - SPECIAL PROCEDURES FOR HISTORIC TREATMENT
A. Summary
1. This Section includes special procedures for historic treatment on Project including, but not limited to, the following:
a. Storage and protection of existing historic materials.
b. Temporary protection of historic materials during construction.
c. Protection during application of chemicals.
d. Protection during use of heat-generating equipment.
e. Historic treatment procedures.
f. Removal of bird excrement.
2. This specification applies to all tasks in the Construction Task Catalog® when they are used on Historic Buildings or Historic Sites.
B. Definitions
1. "Preservation": To apply measures necessary to sustain the existing form, integrity, and materials of a historic property. Work may include preliminary measures to protect and stabilize the property.
2. "Rehabilitation": To make possible a compatible use for a property through repair, alterations, and additions while preserving those portions or features that convey its historical, cultural, or architectural values.
3. "Restoration": To accurately depict the form, features, and character of a property as it appeared at a particular period of time by means of the removal of features from other periods in its history and the reconstruction of missing features from the restoration period.
4. "Reconstruction": To reproduce in the exact form and detail a building, structure, or artifact as it appeared at a specific period in time.
5. "Stabilize": To apply measures designed to reestablish a weather-resistant enclosure and the structural reinforcement of an item or portion of the building while maintaining the essential form as it exists at present.
6. "Protect and Maintain": To remove deteriorating corrosion, reapply protective coatings, and install protective measures such as temporary guards; to provide the least degree of intervention.
7. "Repair": To stabilize, consolidate, or conserve; to retain existing materials and features while employing as little new material as possible. Repair includes patching, piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials. Within restoration, repair also includes limited replacement in kind, rehabilitation, and reconstruction, with compatible substitute materials for deteriorated or missing parts of features when there are surviving prototypes.
8. "Replace": To duplicate and replace entire features with new material in kind. Replacement includes the following conditions:
a. Duplication: Includes replacing elements damaged beyond repair or missing. Original material is indicated as the pattern for creating new duplicated elements.
b. Replacement with New Materials: Includes replacement with new material when original material is not available as patterns for creating new duplicated elements.
c. Replacement with Substitute Materials: Includes replacement with compatible…