Provide responses to prospective bidder questions for informational purposes only.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
J
PAGE OF PAGES
1 4
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
08-Aug-2018
4. REQUISITION/PURCHASE REQ. NO.
W16ROE81643546
5. PROJECT NO.(Ifapplicable)
6. ISSUED BY CODE W912DS 7. ADMINISTERED BY (Ifother than item 6) CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
See Item 6
8. NAME AND ADDRESS OF CONT RACT OR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICIT AT ION NO.
W912DS18B0017
X 9B. DATED (SEE ITEM 11)
16-Jul-2018
10A. MOD. OF CONT RACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. T HIS ITEM ONLY APPLIES TO AMENDMENT S OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt ofthis amendment prior to the hour and date specified in the solicitation or as amended by one ofthe following methods:
(a) By completing Items 8 and 15, and returning 1 copies ofthe amendment; (b) By acknowledging receipt ofthis amendment on each copy ofthe offer submitted;
or (c) By separate letter or telegramwhich includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. Ifby virtue ofthis amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegramor letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNT ING AND APPROPRIAT ION DAT A (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICAT IONS OF CONT RACTS/ORDERS.
IT MODIFIES T HE CONT RACT /ORDER NO. AS DESCRIBED IN ITEM 14.
A. T HIS CHANGE ORDER IS ISSUED PURSUANT T O: (Specify authority) THE CHANGES SET FORT H IN ITEM 14 ARE MADE IN THE
CONT RACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED TO REFLECT THE ADMINIST RAT IVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO T HE AUT HORIT Y OF FAR 43.103(B).
C. T HIS SUPPLEMENTAL AGREEMENT IS ENT ERED INT O PURSUANT TO AUT HORIT Y OF:
D. OTHER (Specify type of modification and authority)
E. IMPORT ANT : Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT /MODIFICAT ION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to:
1. Provide responses to prospective bidder questions for informational purposes only.
Please see continuation page. NOTE: Bidders must acknow ledge receipt of this amendment by date specified in the bid (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separateletter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304)
Except as provided herein, all terms and conditions ofthe document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONT RACTING OFFICER (Type or print)
TEL: EMAIL:
15B. CONT RACT OR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNIT ED ST AT ES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
08-Aug-2018
EXCEPTION TO SF 30
30-105-04
ST ANDARD FORM 30 (Rev. 10-83) APPROVED BY OIRM 11-84 Prescribed by GSA
FAR (48 CFR) 53.243
W912DS18B0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 3
BIDDER’S QUESTION AND GOVERNMENT REPLY:
Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below.
These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only ”and do not revise the solicitation, plans or specifications.
Question 1: Section 00 73 00, Paragraph 1.2 states that the apparent low bidder is required to obtain Environmental Clearance on all quantity as per the Supply/Services Schedule. Please provide some clarity on the intent and scope of this requirement, as it has not been present in prior specifications for this project
Answer 1: SECTION 00 73 00, Paragraph 1.2 which states the following: “The Apparent Low Bidder is required to obtain Environmental Clearance on all quantity as per the Supply/Services (Price) Schedule,” Is hereby omitted from this contract.
Question 2: Paragraph 4 of The Water Quality Certificate for this project outlines a restriction to in-water work from June 1 to September 30 & January 15 to May 15, limiting the in-water work window for this project to 107 days. This is at odds with Section 00 73 00, Paragraph 1.2 which designates 190 days to complete the work.
Please clarify whether the finfish window will be applicable to this project, reducing the completion period to only 107 days.
Answer 2: The U.S. Army Corps of Engineers (USACE) applied to New York State Department of Environmental Conservation for an amendment to the Water Quality Certificate (WQC) to allow dredging to be performed until the end of March. If the USACE receives the amended WQC it will be provided through an amendment to the prospective bidders.
Question 3: Please confirm that dredging and beach fill operations may be performed 24 hours per day, 7 days per week.
Answer 3: Dredging and beach fill operations will be allowed to be performed 24 hours per day, 7 days per week.
Question 4: Please confirm that, should the government elect to relocate any Seabeach Amaranth, said relocation will not be considered under the scope of work for this project.
Answer 4: If Seabeach Amaranth plant(s) need to be relocated, the relocation effort will not be considered under the contractor’s scope of work for this project.
Question 5: Various sections of the specifications note that the quantity to be dredged is 1,800,000 CY; however, the Price Schedule also notes 1,800,000 CY as the quantity to be paid, measured in place on the fill. This does not account for a Dig / Fill ratio. Please clarify if 1.8MCY is the dredge volume or the intended Pay fill volume
Answer 5: The required volume to be placed is 1,800,000 CY, as stated in the revised sections of the specifications, SECTION 00 73 00, SPECIAL CONTRACT REQUIREMENTS, Part1, 1.11 ESTIMATED QUANTITIES and SECTION 01 11 00, SUMMARY OF WORK, Part 1, 1.2.1 PROJECT DESCRIPTION.
Question 6: Further to the above, if 1.8MCY is the pay fill quantity, there is not a significant buffer between required pay and allowable dredge volume. Would grade in the dredge area be lowered to provide additional quantity?
Answer 6: The hydrographic survey performed on 12 - 15 June 2018 for the project specifications indicates a total estimated quantity of 2,602,190 CY of material is available in the channel and deposition basins. This information can be found in the revised section of the specifications, SECTION 00 73 00, SPECIAL CONTRACT REQUIREMENTS, Part 1, 1.11 ESTIMATED QUANTITIES.
Question 7: Do surveys performed by the contractor require a PLS?
Answer 7: No.
Question 8: Can contractors elect to dig multiple areas in tandem to allow for a more efficient/cost effective cut width?
Answer 8: Dredging is required to be performed in the order stated in SECTION 35 20 23, Part 3 EXECUTION, 3.2.1 Order of Work, however, if any scheduled dredging area does not provide sufficient cut width for the contractor’s dredge he will be allowed to include a portion of the adjacent dredging area to fulfill the dredge’s cut width.