Amendment 0006 Spec
View the file
Other files for this federal contract opportunity
Show all 50
FY16 DODEA PN AM0033 Replace Elementary School has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WEST POINT ELEMENTARY SCHOOL REPLACEMENT W91236-15-D-0014
SECTION 32 18 16.13
PLAYGROUND PROTECTIVE SURFACING
04/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D1557 (2012) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D2047 (2011) Static Coefficient of Friction of Polish-Coated Floor Surfaces as Measured by the James Machine
ASTM D412 (2006a; R 2013) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension
ASTM D6112 (2013) Compressive and Flexural Creep and Creep-Rupture of Plastic Lumber and Shapes
ASTM D648 (2007) Deflection Temperature of Plastics Under Flexural Load in the Edgewise Position
ASTM F1292 (2013) Impact Attenuation of Surface Systems Under and Around Playground Equipment
ASTM F1487 (2011) Playground Equipment for Public Use
ASTM F1951 (2014) Standard Specification for Determination of Accessibility of Surface Systems Under and Around Playground Equipment
CONSUMER PRODUCT SAFETY COMMISSION (CPSC)
CPSC Pub No 325 (2010) Handbook for Public Playground Safety
1.2 DEFINITIONS
1.2.1 Critical Height
The fall height at which the protective surfacing meets the requirements of
SECTION 32 18 16.13 Page 3
ASTM F1292.
1.2.2 Designated Play Surface
Any elevated surface for standing, walking, sitting, or climbing; or a flat surface a minimum 2 inches wide having up to a maximum 30 degree angle from horizontal. In some play events the platform surface will be the same as the designated play surface. However, the terms should not be interchanged as they do not define the same point of measurement according to ASTM F1487.
1.2.3 Head Injury Criteria (HIC)
A measure of impact severity that considers the duration over which the most critical section of the deceleration pulse persists as well as the peak level of that deceleration. Head impact injuries are not believed to be life threatening if the HIC does not exceed a value of 1,000.
1.2.4 Impact Attenuation
The ability of protective surfacing to reduce and dissipate the energy of an impacting body.
1.2.5 Maximum Equipment Height
The highest point on the equipment (i.e.: roof ridge, top of support pole).
1.2.6 Play Event
A piece of manufactured playground equipment that supports one or more play activities.
1.3 SYSTEM DESCRIPTION
Measure the perimeters of the play event use zone in accordance with the requirements of Section 11 68 13 PLAYGROUND EQUIPMENT.
1.3.1 Child Safety
Meet or exceed the impact attenuating performance requirements of synthetic surfacing systems, installed in the use zones, as follows. The surfacing critical height value shall yield up to both a maximum 200 G's peak deceleration, and a maximum 1,000 Head Injury Criteria (HIC) value for a head-first fall from the play event in accordance with CPSC Pub No 325 and ASTM F1292. The protective surfacing should have a minimum critical height value equal to the height of the highest designated play surface.
Measuring fall heights for play events is defined in paragraph FALL HEIGHT.
1.3.2 Child Accessibility
The accessibility requirement in accordance with ASTM F1487 includes the following: When the play event use zone consists of a protective surfacing rated as inaccessible, at least one accessible route shall be provided from the use zone perimeter to the play event. When there is more than one of the same play activity provided, only one shall meet accessibility requirements (i.e.: one swing seat or one spring rocking play event).
When the access and egress points are not the same for a play event, an accessible route shall be provided to both. The accessible route shall access all accessible play events and elements. The protective surfacing materials that meet accessibility are synthetic surfacing and engineered
SECTION 32 18 16.13 Page 4 wood fiber in accordance with ASTM F1951. When the accessible surface is within the use zone, it shall meet the requirements of paragraph CHILD
SAFETY
1.3.3 Play Areas at CDC
The technical representative for outdoor play areas at CDC shall be the installation Child Development Services (CDS) Coordinator. The design of the CDC outdoor play area shall be based on the developmental play program for the age groups accommodated at the CDC. The play area is designed to support the CDC program and to provide a stage set for creative play.
Developmental activities are selected which promote the intellectual, social, emotional and physical growth of the children. The developmental play program is developed by the MACOM CDS Director, installation CDS Coordinator and CDC Director. They are responsible for the developmental play program, child safety and accessibility to meet that program.
1.3.4 Sites Other than CDC
The technical representative for outdoor play areas on sites other than CDCs shall be the Director of Public Works or designated representative.
The design of these outdoor play areas shall be based on the play program and the age groups to be accommodated as determined by the play area committee.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Shop Drawings.
Finished Grade and Underground Utilities
SD-03 Product Data
Synthetic Surfacing; G Geotextile Fabric; G Manufacturer's Qualification; G Wood; G Site Preparation; G Temperature Limitation; G Wood Treatment; G Adhesive; G Color; G
SD-04 Samples
Synthetic Surfacing
SD-06 Test Reports
Percolation Test Recycled Plastic
SECTION 32 18 16.13 Page 5
Synthetic Surfacing
SD-07 Certificates
Materials Manufacturer's Qualification Manufacturer's Representative Installer's Qualification Substitution Protective Surfacing Acceptance
SD-10 Operation and Maintenance Data
Maintenance Instructions; G
1.5 QUALITY ASSURANCE
1.5.1 Manufacturer's Qualification
Submit name of the owner or user; service or preventive maintenance provider; date of the installation; point of contact and telephone number;
and address for 10 sites. Protective surfacing should have been installed in a minimum 10 sites and been in successful service for a minimum 5 year calendar period. The manufacturer shall provide a Certificate of Insurance AA rated for a minimum one million dollars covering both product and general liability.
1.5.2 Manufacturer's Representative
Submit the individual's name, company name and address, and playground safety training certificate. The manufacturer's certified playground safety inspector or the manufacturer's designated certified playground safety representative shall supervise the installation and adjustment of the protective surfacing to verify the installation meets the requirements of the manufacturer, this specification, and paragraphs CHILD SAFETY and
CHILD ACCESSIBILITY.
1.5.3 Installer's Qualification
Submit the installer's company name and address, training and experience certification. The installer shall be certified by the manufacturer for training and experience installing the protective surfacing.
1.5.4 Shop Drawings
When the use zone perimeter and play event configuration conflict with the requirements and paragraphs CHILD SAFETY and CHILD ACCESSIBILITY, submit scale drawings defining corrective measures to include the following:
Adjustment to the play event with the use zone perimeter; use zone perimeter overlaps; fall height and critical height value.
1.6 DELIVERY, STORAGE, AND HANDLING
Provide a delivery schedule at least 10 calendar days prior to the first day of delivery. Deliver, handle, and store protective surfacing material in accordance with the manufacturer's recommendations. The storage area shall be as designated. Store the materials in a dry, covered area until installed. Inspect protective surfacing material, upon arrival at the job site, for meeting specified quality. Unacceptable materials shall be
SECTION 32 18 16.13 Page 6 removed from the job site.
1.7 WARRANTY
Furnish protective surfacing with a minimum 1 year calendar period warranty.
1.8 MAINTENANCE INSTRUCTIONS
Submit 2 bound copies of the manufacturer's operation and maintenance manual describing the recommended preventive maintenance, inspection frequency and techniques, periodic adjustments, lubricants, and cleaning requirements. Furnish protective surfacing spare parts provided by the manufacturer.
PART 2 PRODUCTS
2.1 MATERIALS
Prior to the delivery of materials, submit certificates of compliance attesting that materials meet the specified requirements. Certified copies of the material certificates shall include composition and tests to which the material has been subjected. Submit manufacturer's descriptive data;
catalogue cuts; and the latest edition of ASTM F1487 and CPSC Pub No 325.
Provide materials which are the standard products of a manufacturer regularly engaged in the manufacture of protective surfacing and that are similar to surfacing in satisfactory use a minimum 5 year calendar period.
Protective surfacing consists of synthetic surfacing.
Ensure products comply with Federal procurement preference under section 9002 of the Farm Security and Rural Investment Act of 2002 and as specified in Section 01 33 29 SUSTAINABILITY REPORTING.
2.2 SYNTHETIC SURFACING
Submit a minimum 2 by 2 inch sample. Submit impact attenuation and critical height performance for each thickness of synthetic surfacing and provided. Submit delivery schedule and manufacturer's name for synthetic surfacing plus delivery, storage and handling information. Furnish a list to include part numbers of furnished protective surfacing materials and components for synthetic surfacing and manufacturer's specifications, handling and storage requirements, installation procedures, and safety data sheets to include warnings and critical height performance standards for synthetic surfacing. Synthetic surfacing includes the following:
poured-in-place system; tile system; and combination system. The synthetic surfacing consists of either impact attenuating substrate covered by a wear surface bonded to produce a unified system; a shredded rubber or aggregate substrate covered by a polyethylene plastic woven sheet wear surface; or a uniform material manufactured in such a way that the top portion meets the requirements specified for wear surface. Submit chemical composition, color granule percentage, and test results to which material has been subjected, identifying each material and component containing recycled materials and showing the estimated percentage of recovered material content. Furnish freezing temperature life-cycle durability.
2.2.1 Subbase
The subbase for synthetic surfacing may be either concrete, aggregate, or bituminous material.
SECTION 32 18 16.13 Page 7
2.2.1.1 Aggregate Subbase
Provide aggregate material conforming to Section 32 11 23 AGGREGATE AND/OR
GRADED-CRUSHED AGGREGATE BASE COURSE.
2.2.2 Impact Attenuating Substrate
Provide a substrate compatible with the wear surface, and consisting of modular units; poured-in-place; or loose fill. Recycled materials must conform to EPA requirements in accordance with Section 01 33 29
SUSTAINABILITY REPORTING.
2.2.2.1 Poured-In-Place Substrate
Poured-in-place substrate shall consist of a 100 percent recycled, shredded, styrene butadiene rubber (SBR) adhered with a 100 percent solid polyurethane binder to form a resilient, porous material or shredded rubber. Strands of SBR may vary from a minimum 1/50 inch to a maximum 2/25 inch thickness; by a minimum 1/8 inch to a maximum 4/5 inch length. Binder shall be between a minimum 12 percent and a maximum 16 percent of the total weight of the mixture of rubber and urethane; and shall provide 100 percent coating of the particles. Foam rubber will not be accepted in the substrate.
2.2.3 Wear Surface
Wear surfaces consist of the following: a poured-in-place durable, weather-resistant, ultraviolet stable, water permeable material top-coat;
an integral component of a tile system; synthetic turf wear surface; rubber sheet wear surface; or a polyethylene woven plastic sheet wear surface.
The wear surface shall meet requirements of ASTM D2047 for a minimum 0.8 coefficient of friction.
2.2.3.1 Poured-in-Place Wear Surface
Poured-in-place wear surface consists of ethylene propylene diene monomer (EPDM) particles adhered with a polyurethane binder formulated to produce an even, uniform surface. Particles of EPDM shall meet ASTM D412 for tensile strength and elongation, and contain a minimum 25 percent of rubber hydrocarbons. Particles of EPDM shall be peroxide or sulfur cured in accordance with the manufacturer. Size of rubber particles shall be between a minimum 1/32 inch, and a maximum 1/8 inch diameter. Binder shall be between a minimum 16 percent and a maximum 21 percent total weight of rubber used in the wear surface, and shall provide 100 percent coating of the particles. Wear surface shall be a minimum 3/8 inch thick. The wear surface shall be porous.
2.2.4 Synthetic Tile
Synthetic tile shall be sized as indicated. Synthetic tile shall be a factory-molded unit consisting of the following: combining impact attenuating substrate and wear surface meeting requirements specified for substrate and wear surface; or a dual-density, uniform material, the top portion of which shall conform to wear surface requirements specified.
2.2.5 Color
Submit 2 color charts displaying surfacing colors, color granule percentages and finishes. The color shall be as approved by the
SECTION 32 18 16.13 Page 8
Erin.Burdick Highlight
Erin.Burdick Highlight
Contracting Officer. An EPDM wear surface is preferred for color retention. Black or the following dark colored SBR wear surfaces retain heat and are not acceptable: color combinations containing more than 10 percent black; or color combinations averaging more than 10 percent dark colors.
2.2.6 Sealant
Sealant for tile or combined protective surface systems shall be compatible with the protective surfacing, and shall match the color of the wear surface.
2.2.7 Hardware
Hardware, anchors or fasteners shall be corrosion resistant stainless steel or galvanized steel to anchor the surfacing system securely, in accordance with manufacturer's instructions. Hardware shall provide or be recessed to provide a flat surface and shall be covered by the required depth of protective surfacing.
2.2.8 Binder
Binder for synthetic surfacing shall be nontoxic, weather-resistant, ultraviolet stable, non-hardening, and retaining impact-attenuating performance. It shall be 100 percent solids containing polyurethane, methylene diphenel isocyanate (MDI), or as recommended by the manufacturer. A maximum 2 percent of toluene diphenel isocyanate (TDI) shall be used. Weight of polyurethane shall be between a minimum 8.5 lbs/gal and a maximum 9.5 lbs/gal. Coloring pigments shall be inorganic oxides.
2.2.9 Adhesive
Adhesive shall be a two component polyurethane providing extremely high impact resistant bond and shall be installed as recommended by the manufacturer. The adhesive shall be non-toxic, resistant to ultraviolet light, and safe for children. Adhesive shall conform to EPA registered uses, toxicity levels, and application hazards.
2.2.10 Containment Curbs
Containment curbs include the following: treated wood, concrete, recycled plastic, or recycled plastic molded as lumber. Containment curbs shall provide a smooth and hazard-free transition from the protective surfacing to the adjacent surface. Curbs shall be free of sharp vertical edges, protruding elements and trip hazards. Curbs shall be as recommended by the manufacturer. All edges should be provided with a minimum 1/2 inch radius.
2.2.11 Transition Edge
The transition edge shall be designed to maintain the protective surfacing performance, support the surfacing between changes of material, and shall be concrete in accordance with paragraph CONCRETE CURB. The face of the edge to the subgrade shall be covered with the impact attenuating surface and meet the requirements of paragraph CHILD SAFETY.
2.2.12 Combination System
Combination systems shall consist of combined protective surfacing
SECTION 32 18 16.13 Page 9 materials specified. Each component is a part of a manufactured surfacing system. Wear surface shall be of the materials specified.
2.3 GEOTEXTILE FABRIC
Geotextile fabric consists of the following: nonwoven polypropylene sheet;
nonwoven 100 percent polyester sheet; or nonwoven needle punched polyester sheet composed of recycled polyester resins.
2.4 RECYCLED PLASTIC
Provide the estimated percentage of recovered material content in the material and components; and life-cycle durability. Submit individual component and assembled unit structural integrity test; creep tolerance;
deflection tolerance; and vertical load test results. The estimated percentage of recovered material content in the material and components.
Life-cycle durability. Recycled plastic must contain a minimum 85 percent of recycled post-consumer product and conform to EPA requirements in accordance with Section 01 33 29 SUSTAINABILITY REPORTING.
2.4.1 High Density Polyethylene
The material shall be molded of ultraviolet (UV) and color stabilized polyethylene; and consist of a minimum 75 percent plastic profile of high-density polyethylene, low-density polyethylene, and polypropylene raw material. The material shall be non-toxic and have no discernible contaminates such as paper, foil, or wood. The material shall contain a maximum 3 percent air voids. The material shall be free of splinters, chips, peels, buckling, and cracks. Material shall be resistant to deformation from solar heat gain. Material shall have factory-drilled holes. Components with extra holes not filled by hardware or covered by other components shall be rejected. The material shall not be painted.
2.4.2 Structural Component
Recycled plastic materials will not be used as load bearing structural members.
2.4.3 Recycled Plastic Molded As Lumber
The component shall deflect a maximum 1/360 of the span of the frame when exposed to a uniform live load of 40 lbs/ft, ASTM D648. The product shall meet the structural integrity test requirements set forth in ASTM F1487 and
ASTM D6112.
2.5 CURBS
2.5.1 Concrete Curb
Concrete curbs shall conform to Section 32 16 13 CONCRETE SIDEWALKS AND
CURBS AND GUTTERS
2.5.2 Wood
2.5.2.1 Wood Components
Wood components shall be from managed forests.exterior premium grade and free of knots. Identify wood components obtained from managed forests.
Wood components shall have factory-drilled holes. Components with extra
SECTION 32 18 16.13 Page 10 holes not filled by hardware or covered by other components shall be rejected.
2.5.2.2 Wood Treatment
Wood components that are not naturally rot and insect resistant shall be treated to resist rot and insect attack by using standard treatment procedures. Provide wood treatment chemical content, toxicity level, and life-cycle durability. Any wood placed up to a maximum 6 inches above, or any portion below the top elevation of the protective surfacing, shall be treated after fabrication. Creosote, pentachlorophenol, and tributyl tin oxide are prohibited according to ASTM F1487.
PART 3 EXECUTION
3.1 SITE PREPARATION
Prior to installing the protective surfacing, verify the playground equipment and site furnishings are installed in accordance with Section
12 93 00 SITE FURNISHINGS.
3.1.1 Finished Grade and Underground Utilities
Submit finished grade, underground utilities, storm-drainage system and irrigation system status; and location of underground utilities and facilities. Verify that finished grades are as indicated; the smooth grading has been completed in accordance with Section 31 23 00.00 20 EXCAVATION AND FILL; installation of the underground utilities through the area has been completed in accordance with Section 31 23 00.00 20 EXCAVATION AND FILL; installation of the storm-drainage system through the area has been completed in accordance with Section 33 40 00 STORM DRAINAGE.
The location of underground utilities and facilities in the area of the operation shall be verified. Damage to underground utilities and facilities shall be repaired at the Contractor's expense.
3.1.2 Layout
The layout of the entire use zone perimeter shall be staked before excavation begins. The location of all elements shall be staked to include the following: All play event configuration access and egress points; and use zone perimeters. The use zone is defined as the area beneath and immediately adjacent to a play structure or equipment that is designated for unrestricted circulation around equipment; and on whose surface it is predicted that a user would land when falling from or exiting the equipment. Also, the use zone is associated with the following terms;
"Clear Area," and "Fall Zone". The use zone shall be free of hard surfaces, objects or obstacles that a child could run into or fall on top of and be injured. Use zone perimeters shall not overlap hard surfaces.
The use zone perimeter shall meet or exceed the requirements of paragraphs CHILD SAFETY and CHILD ACCESSIBILITY. Use zone perimeters shall not overlap except for certain play events as defined in ASTM F1487.
3.1.3 Obstructions Below Ground
When obstructions below ground affect the work, shop drawings showing proposed adjustments shall be provided.
SECTION 32 18 16.13 Page 11
3.1.4 Percolation Test
Submit a certified report of inspection, test method used and compliance with recognized test standard shall be described. A test for percolation shall be done to determine positive drainage, to include the lowest elevation of the subgrade in the areas containing synthetic surfacing installed over a pervious base. A positive percolation shall consist of a minimum 1 inch per 3 hour period. When a negative percolation test occurs, a shop drawing shall be provided to indicate the corrective measures.
3.1.5 Substitution
Under no circumstances are substitutions to be allowed or protective surfacing to be selected without written approval from the technical representative. Evaluate manufacturer substitutions for the critical height value with meeting the site conditions and paragraph FALL HEIGHT.
3.1.6 Subgrade
Correct subgrade irregularities to ensure the required depth of protective surfacing is provided. The subgrade elevation shall be as required by the manufacturer.
3.1.7 Subsurface
Install the subsurface in a true, even plane, and sloped to provide positive drainage as indicated.
3.1.8 Subbase
Tolerance of the concrete or bituminous subbase shall be within a maximum 1/4 inch in 10 feet. Tolerance of aggregate subbase shall be within a maximum similar to 1/4 inch in 10 feet. Compact aggregate subbase to a maximum 95 percent, ASTM D1557. The compaction shall be completed in accordance with Section 31 23 00.00 20 EXCAVATION AND FILL.
3.1.9 Concrete or Bituminous Curing
Bituminous or concrete subbase shall be cured in accordance with the manufacturer's requirements. Curing compounds and other deleterious substances that adversely affect adhesion shall be removed. Surface shall be clean and dry.
3.1.10 Fall Height
3.1.10.1 General Requirements
The fall height is defined as the vertical distance between the finished elevation of the designated play surface and the finished elevation of the protective surfacing beneath it. For some play events the fall height and platform height are the same, while for other play events the fall height and maximum equipment height are the same, Section 11 68 13 PLAYGROUND EQUIPMENT. When the furnished play event fall height varies from the play event shown, shop drawings shall be provided defining the revised depth or type of protective surfacing to meet or exceed the requirements of paragraphs CHILD SAFETY and CHILD ACCESSIBILITY.
SECTION 32 18 16.13 Page 12
3.1.10.2 Measuring Fall Height
EQUIPMENT MEASURING FALL HEIGHT
Composite Equipment Structure For a platform surrounded by protective barriers, measure from the platform finished elevation.
For a platform surrounded by guardrails, measure from the guardrail top elevation.
Infant Crawl Area A maximum 24 inches height, measured from the crawl wall or barrier finished elevation.
Playhouse, Nonclimbable Measure from the designated play surface finished elevation.
Spring Rocking Equipment Measure from the seat top elevation.
Stationary Equipment, Climbable Measure from the maximum equipment height finished elevation.
Stationary Equipment, Nonclimbable
Measure from the designated play surface finished elevation.
Swing Measure from the bottom of the pivot point.
3.2 INSTALLING SYNTHETIC SURFACING SYSTEM
Surfacing edges shall fully adhere to the subsurface. Fully cover the subsurface to ensure no hard surfaces are exposed through displacement of loose fill. Rolled or beveled containment curb or transition edges shall maintain the full thickness required to meet paragraphs CHILD SAFETY and CHILD ACCESSIBILITY. Material shall cover foundation and cutouts around elements penetrating the surface. Seams shall be the minimum necessary and shall be tight.
3.2.1 Temperature Limitation
Provide temperature limitations for applying adhesive.
3.2.2 Poured-in-Place System
Components of the poured-in-place system shall be mixed mechanically on site in accordance with manufacturer's recommendations. Hand-mixing is prohibited. Installation of poured-in-place surfacing shall be seamless and completely bonded to subsurface. Material shall cover foundations and shall be tight around elements penetrating the surface. Add a minimum 1/16 inch depth to the required surfacing depth to ensure the full depth of material is installed to meet paragraph CHILD SAFETY.
3.2.2.1 Geotextile Fabric for Poured-In-Place
Install geotextile fabric over a compacted aggregate base as indicated.
Fabric shall cover the entire area and shall be lapped a minimum 4 inch width at the seams. Seams shall be adhered in accordance with manufacturer's recommendations. The aggregate base shall be free of ruts or protruding objects. The fabric shall be installed smooth; and free of tensile stresses, folds, and wrinkles. The fabric shall be protected from clogging, tears, or other damage. Damaged fabric shall be repaired or
SECTION 32 18 16.13 Page 13 replaced as directed.
3.2.2.2 Poured-in-Place Substrate
The substrate layer of the poured-in-place system shall be installed in one continuous pour on the same day. When a second pour is required, the edge of the previous work shall be fully coated with polyurethane binder to ensure 100 percent bond with new work. Adhesive shall be applied in small quantities so that new substrate can be placed before the adhesive dries.
3.2.2.3 Poured-in-Place Wear Surface
Wear surface shall be bonded to substrate. Adhesive shall be applied to substrate in small quantities so that wear surface can be applied before adhesive dries. Surface shall be hand troweled to a smooth, even finish.
When wear surface is composed of different color patterns, pour shall be continuous and seamless. When seams are required due to color change or field conditions, the adjacent wear surface shall be placed as soon as possible, before initial pour has cured. The edge of initial pour shall be coated with adhesive and wear surface mixture shall be immediately applied.
3.2.3 Tile System
Tile shall be laid out to ensure that end cuts are equal. Tile shall be installed in accordance with manufacturer's instructions. Hardware shall be as recommended by the manufacturer. Tile shall be bonded to the subsurface with an adhesive approved by the manufacturer. Cutouts shall be filled with sealant according to manufacturer's instructions to eliminate voids at equipment. Sealant shall be the minimum amount necessary, shall not exceed a maximum 3/8 inch width. Where excessive voids occur at cutouts, tile shall be removed and refitted. The tile system shall be installed throughout the play equipment use zone with the proper thickness.
3.2.4 Combination System
The combination system shall consist of modular impact attenuating substrate units, adhered to form a unified system, . The substrate shall be covered with a wear surface as specified. Cutouts around equipment shall be properly filled and sealed according to manufacturer's instructions to eliminate voids. Sealant shall be the minimum amount necessary, shall not exceed a maximum 3/8 inch width. Where excessive voids occur at cutouts, the modular substrate shall be removed and refitted. Construction methods shall be employed to ensure full depth installation of specified surfacing material and the finished wear surface.
3.2.4.1 Geotextile Fabric
Geotextile fabric shall be installed where a modular or shredded rubber substrate is installed over an aggregate base. It should be installed with poured-in-place wear surface or polyethylene plastic woven sheet wear surface installed over substrate. Fabric shall cover the entire area to receive the tile system and shall be lapped a minimum 4 inch width at the seams. Seams shall be adhered in accordance with manufacturer's recommendations.
3.2.4.2 Modular Substrate
Modular substrate shall be laid out to minimize small end pieces. The substrate shall be installed in accordance with manufacturer's instructions.
SECTION 32 18 16.13 Page 14
3.2.4.3 Poured-in-Place Substrate
Same as paragraph POURED-IN-PLACE SYSTEM.
3.3 RESTORATION AND CLEAN UP
When the operation has been completed, clean up and protect the site.
Existing areas that have been damaged from the operation shall be restored to original condition at the Contractor's expense.
3.3.1 Clean Up
The site and play events shall be cleaned of all materials associated with the operation. Play events and surfaces shall be cleaned of dirt, stains, filings, and other blemishes occurring from shipment and installation.
Cleaning methods and agents shall be as recommended by the manufacturer.
3.3.2 Protection
The area shall be protected as required or directed by providing barricades and signage. Signage shall be in accordance with Section 10 14 01 EXTERIOR
SIGNAGE
3.3.3 Disposal of Materials
Excess and waste material shall be removed and disposed of off Government property.
3.4 PROTECTIVE SURFACING ACCEPTANCE
Submit record of measurements and findings by the certified playground safety inspector. When the protective surfacing is installed, the play events and protective surfacing shall be thoroughly inspected and measured to verify the playground meets manufacturer's recommendations, paragraphs CHILD SAFETY and CHILD ACCESSIBILITY, and paragraph FALL HEIGHT as follows:
1) secure anchoring; 2) all hardware and connectors are tight and below the wear surface; 3) sharp points, edges, and protrusions; 4) entanglement; and
5) pinch, crush, and shear points.
a. Measure use zone distances to determine the area is free of hard surfaces, objects or obstacles. Determine exceptions to use zone overlaps occur in accordance with ASTM F1487. Measure play event fall height and compare to critical height value for the thickness of installed synthetic surfacing. Measure play event fall height and depth of loose fill protective surfacing.
b. Ensure installed chopped tire material is free from steel belts.
Ensure the slide exit region has the required clear zone. Swing seat clearances are measured while occupied by a maximum user for the age group using the equipment.
c. The finished installation shall have the appearance of a single covering. Protective surfacing that does not comply shall be reinstalled. Hardware that does not comply shall be replaced. Ensure positive drainage for the area and the lowest elevation of protective surfacing subgrade has been provided.
d. A written report describing the results of the evaluation shall be
SECTION 32 18 16.13 Page 15
Erin.Burdick Highlight provided.
3.5 RE-INSTALLATION
When re-installation is required, the following shall be accomplished.
Re-install the product as specified. Provide new replacement materials supplied by the manufacturer (material acquisition of replacement parts is the responsibility of the Contractor). Damage caused by the failed installation shall be repaired at the Contractor's expense.
-- End of Section --
SECTION 32 18 16.13 Page 16
File details come from the government source that posted it. Updated .