Text version
W912DS-16-B-0016
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Purpose of this Amendment is to:
a. Answ er bidders questions for information only.
The bid opening due date remains the 22 September at 3PM EST.
NOTE: Bidders must acknow ledge receipt of this amendment by the date specified in the bid (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Sep-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-16-B-0016
X 9B. DATED (SEE ITEM 11)
23-Aug-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Sep-2016
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 73 00 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
AMENDMENT 0008
FY16 Eisenhower Hall Phase III US Military Academy, West Point NY
W921DS-16-B-0016
Amendment 0008
AMENDMENT 0008 to DRAWINGS and SPECIFICATIONS for Eisenhower Hall Phase III, W912DS-16-B-0016.
TO OFFORERS
The following changes shall be made to the drawings and specifications.
DRAWINGS
1. The following DRAWINGS have been REVISED but NOT REISSUED:
- None
2. The following DRAWINGS have been REVISED and REISSUED:
3. The following DRAWINGS have been ADDED:
- None
4. The following DRAWINGS have been DELETED:
SPECIFICATIONS
1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:
- None
2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:
- None
3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:
- None
4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:
BIDDERS RFI’s
(Questions that may be of general interest to all Bidders and/or the Government and that are readily answered by the proceeding changes will appear below. These questions may have been para phased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question (s).
Questions and answers are issued to the Bidders for information only).
1. Questions - Section 08-4229. Confirm that this section is not applicable to this phase.
Answer - The Automatic entrances are not part of phase III work
2. Question - Section 05-5213, para. 2.02: Stainless Steel Railing location mentioned does not belong to Phase III Work. There is no stainless steel railing work at the ticket office storefront vestibule.
However; Section 05-5213 is applicable to all railings indicated in the phase III drawings.
Answer - Railings are called out throughout the set of drawings.
Please see drawings A-402, A-403, A-404, A-405 and A-407 for railings related to exterior terraces.
Section 05-5213 is also applicable to interior rails protecting the wheel chair viewing platforms in the theater. Please see A-304 See also drawings A-601, A-602, A-603, A-604, and A-607 for additional information on railings
3. Question - Please clarify the SOW as it relates to the ceilings / options indicated in various places in the documents as options.
Answer - Reference to drawings A-200 through A-205 Please disregard references to option A and B relative to the interior ceiling work. The interior ceilings work indicated with keynote 1 shall be repaired as base work in accordance with detail 3 / A200.
Work shall be coordinated with the new fire suppression work. The areas of work associated with this clarification are:
1. The Dressing room toilets or shower rooms at level 78 shown on revised drawing A-200
2. The Dressing room toilets or shower rooms at levels 92, 104 and 114 as shown on revised drawing A201
3. The ceiling below the first balcony of the theater at level 104 as shown on revised drawing A202
4. The ceiling below the second balcony of the theater at level 124 as shown on revised drawing A203
5. The ceilings below the roof in stairs 5 and 8 as shown on revised drawing A204
6. The ceilings above the second balcony vomitories at level 149 as shown on revised drawing A204
7. The entire ceiling over the main theater at level 149 as shown on revised drawing A205 including all step downs, fascia and box outs
4. Question - I would like to know if this is a prevailing wage job, or/and if it requires a project labor agreement.
Answer – Yes it is a prevailing wage job and no this project does not require a project labor agreement.
(End of Summary of Changes)