A. Project: Job Order Contract (JOC) for construction and maintenance projects at the Seneca Army Depot Activity, Romulus, NY
B. provide all w ork, materials, supplies, parts (to include system components), transportation, plant, supervision, labor, and equipment, except w hen specif ied as Government-furnished, needed to repair, or construct real property facilities at Seneca Army Depot.
C. The estimated value is capped at $3,000,000 for the base period and $1,000,000 for each option period.
D. Contract Specialist: Matthew Lubiak, 917-790-8089, matthew .lubiak@usace.army.mil
E. This acquisition is a 100% SDVOSB set aside. The NAICS code is 236220.
F. Submit proposals to the Contracting Office NLT October 30, 2012 at 2:00 PM EST:
U.S Army Corps of Engineers Contracting Division 26 Federal Plaza, RM1843 New York, NY 10278
G. Offerors are advised to allow ample time to pass through security checks in order to have their proposals delivered by 2:00 PM.
MATTHEW E LUBIAK 917-790-8089
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
27-Sep-2012
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Each Job Order
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________5 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________30 Oct 2012 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
212 264-3013FAX:TEL: 212 264-0238 TEL: FAX:
W912DS-12-R-0003 98
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912DS-12-R-0003
Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Percent BASE PERIOD - Normal working hours
FFP
Unit work requirements to be performed during normal working hours on Depot as ordered in individual Task Orders against this contract. Base period is 36 months.
Enter Contractor's Coefficient %.
FOB: Destination
NET AMT
0002 Percent BASE PERIOD - Other than normal hours
FFP
Unit work requirements to be performed during other than normal working hours on Depot as ordered in individual Task Orders against this contract. Enter Contractor's Coefficient %.
0003 Percent OPTION OPTION YEAR 1 - Normal hours
FFP
Unit work requirements to be performed during normal working hours on Depot as ordered in individual Task Orders against this contract. Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.
0004 Percent OPTION OPTION YEAR 1 - Other than normal hours
FFP
Unit work requirements to be performed during other than normal working hours on Depot as ordered in individual Task Orders against this contract. Coefficients for the option periods are subject to economice price adjustment from the base year. Do not enter coefficient here.
0005 Percent OPTION OPTION YEAR 2 - Normal hours
FFP
Unit work requirements to be performed during normal working hours on Depot as ordered in individual Task Orders against this contractor. Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.
0006 Percent OPTION OPTION YEAR 2 - Other than normal hours
FFP
Unit work requirements to be performed during other than normal working hours on Depot as ordered in individual Task Orders against this contract. Coefficients for the option periods are subject to economic price adjustment from the base year.
Do not enter coefficient here.
Section 00100 - Bidding Schedule/Instructions to Bidders
INSTRUCTIONS TO OFFERORS
SECTION 00110 – Instructions to Offerors
PROPOSAL SUBMITTAL INSTRUCTIONS
The Government will use a competitive Best Value Tradeoff process for this source selection.
Proposals shall be submitted in two separate volumes as follows:
1. Volume I shall contain the Technical Proposal described below. It should be clearly marked "Technical Proposal RFP No. W912DS-12-R-0003". An original and four copies are required. The Technical Proposal shall be limited to 75 pages, and tabbed with the three parts specified in Evaluation Factors. Past performance (Tab D) information does not count toward the 75 page limit. Proposals containing extraneous and irrelevant material will be viewed as a lack of understanding of the requirements on the part of the offeror.
2. Volume II shall contain the Price Proposal described below. It should be clearly marked "Price Proposal, RFP No. W912DS-12-R-0003. An original and two copies are required.
3. Proposals shall be submitted prior to the closing date to the following address:
U.S. Army Corps of Engineers Attn: CENAN-CT, Room 1843 26 Federal Plaza New York, NY 10276-0090
I. TECHNICAL PROPOSAL
An offeror's Technical Proposal shall address the following areas. The offeror shall prepare the Technical Proposal in a format that follows the outline of evaluation factors specified in Section 00120, Evaluation Factors for Award. Care should be taken to ensure that no pricing information is contained in the Technical Proposal.
VOLUME 1 – PERFORMANCE CAPABILITY
Factor/
Element
Description Relative Importance
FACTOR 1 Management Plan
FACTOR 2 Work Execution
FACTOR 3 Past Experience
FACTOR 4 Past Performance
Factors 1, 2, 3 and 4 are listed in descending order of importance
1. Management Plan (Factor 1). The offeror shall submit a list of proposed management and on-site staff, their backgrounds, and respective positions with regard to this contract. They should address their ability to coordinate multiple subcontractors on single or multiple projects; their response time to Government needs; their purchasing system; a plan to administer payroll and labor relation functions; and provide a Quality Control Plan. Such areas of consideration should be:
a. Explain plan for interaction between the Government and Contractor staff. Provide an organizational chart to clearly delineate the lines of authority and leadership of key personnel and project managers. Outline the proposed corporate and on-site staff, their resumes, responsibilities and authorities with regard to this contract and how they will interface with each other.
b. Outline the minimum and maximum on-site staffing levels and describe how and when staffing levels will be adjusted. Discuss the proximity to the installation and how this may effect response time. Address responsibilities, capabilities, and levels of authority in order to assure project accomplishment in a timely and responsive manner. Explain management controls in this process and discuss staffing levels available to cope and negotiate delivery orders simultaneously and effectively. Discuss how staff will provide sketches, plans, shop drawings and as-built drawings, and a plan for ensuring accuracy of sizing calculations (dimensions, electrical capacity, load limits, HV AC sizing, etc). Outline how staff will control cost and be responsible for requisition, purchase, delivery, and inspection of materials.
c. Develop a proposed Quality Control Plan. Describe what measures and controls will be taken to insure that requirements will be met. Outline the quality control staffing to include experience, training and education requirements and what disciplines of construction are areas of expertise. Outline the quality control staff qualifications, responsibilities and authority, and quality control reporting procedure. Outline what measures will be taken to correct construction deficiencies. Outline a proposed safety plan, explaining how Occupational Safety Health Administration (OSHA) and the requirements ofEM-385-1-1 will be met.
2. Work. Execution. (Factor 2). This section shall address the extent and rationale for in-house and subcontract work distribution and local contractor support.
a. Provide rationale for selection and utilization of subcontractors. Explain the subcontracting support capability; criteria for subcontractor selection; plan for coordinating, scheduling, and ensuring timeliness of work execution; and completion of multiple projects with multiple subcontractors. Discuss how the subcontracted effort will be integrated into the total contract effort. What means of communication will there be between contractor and subcontractor? How will multiple projects affect plans? Delineate controls management will have on timeliness and quality of subcontracted effort. Discuss utilization of local business, in the vicinity of the installation, as either a prime or subcontractor.
b. Vicinity, as used in the Defense Federal Acquisition Regulation Supplement (DFARS), means the county or counties in which the military installation is located and all adjacent counties. In accordance with DFARS 226.7102 policy, businesses located in the vicinity of a military installation that is being closed or realigned under a base closure law, including 10 U.S.C. 2687, and small and small disadvantaged businesses shall be provided maximum practicable opportunity to participate in acquisitions that support the closure or realignment, including acquisitions for environmental restoration and mitigation.
3. Past Experience (Factor 3). Using Form A-2 provided in this solicitation, the Offeror shall demonstrate not less than five (5) examples of projects not less than 75% complete or physically completed within the last five (5) years and shall be similar in scope, magnitude and complexity.
Physical completion is defined as the date the facility was turned over to, or occupied by the owner are required. Projects similar in scope, magnitude and complexity are defined as, but not limited to the following: Scope is defined as maintenance and repair projects on any of the following types: infrastructure projects (i.e., water lines, sanitary lines, storm water systems, fire protection systems, electrical systems and HVAC systems, industrial facilities, administrative facilities, and residential/family housing. Magnitude is defined as the maintenance and repair of projects between $50,000 to $500,000 in a single facility or a multi-building complex. Complexity is defined as the use of a multi disciplined team in construction of the facilities of the type as described under scope. Include actual and scheduled start, completion and duration dates and a list of references. References should include company name, point of contact, and phone number. This should include a list of terminated projects. Be specific regarding experience, especially that relating to facilities maintenance and repair projects and minor new construction. Identify scopes of work in previous projects to include types and levels of skills, trade, and equipment.
4. Past Performance (Factor 4). The Past Performance Questionnaire included in this solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 3. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before the proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (FORM A3), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Matthew Lubiak email at Matthew.Lubiak@usace.army.mil proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
Also include performance recognition documents received within the last five (5) years such as award fee determinations, customer letters of commendation, and any other forms of performance recognition.
In addition to the above the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved though the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
In addition, the Offeror is required to provide information on past projects (within the past five
(5) years) that were terminated (for any reason) or in which they have been issued a CURE NOTICE and provide accompanying information as to the details for such action(s) with an explanation of why they were terminated or issued a cure notice.
Factor 4 submissions shall not count towards the page limit.
II. PRICE PROPOSAL
The offeror shall submit in Section 00100 this solicitation, the offeror's price coefficients to accomplish the tasks described herein. The Contractor shall submit completed Standard Form 1442, with price coefficients completed in Items 0001 and 0002 for the Base Year.
The Price Proposal shall include all the requisite cost elements, which comprise the coefficient and a narrative to support the proposal. A clear audit trail must be evident as to the conversion of costs to the coefficients.
Failure to provide the supporting documentation may render the offeror non-responsive and the offer may be removed from the competitive range.
Prices for Job Orders issued against a contract that results from this solicitation will be determined by applying the proposed coefficients against applicable unit prices listed in the Construction Task Catalog for a particular Job Order.
See the Construction Task Catalog, Specifications Section 01 20 - Unit Prices and Payment Procedures, for complete unit price book.
SECTION 00120 - Proposal Evaluation and Contract Award
EVALUATION FACTORS FQR AWARD
A. BASIS OF AWARD.
GENERAL
(i) Subject to the terms and conditions contained herein, award will be made to a single offeror.
No proposal will be accepted that does not contain clear and concise evidence of the contractor's ability to provide work in accordance with this solicitation.
(ii) The Government will evaluate each proposal strictly in accordance with its content and will not assume that performance will include areas not specified in the offeror's proposal.
(iii) Proposals that are unrealistic in terms of management, technical, quality, or has unrealistic low coefficients will be deemed indicative of failure to comprehend the complexity and risks of the proposed contractual requirements and will receive lower ratings commensurate with such weaknesses and/or deficiencies.
(iv) Award will be made to the offeror whose offer will be most advantageous to the Government considering the evaluation factors stated below.
B. EVALUATION FACTORS
In selecting the offeror most advantageous to the Government, the following factors will be considered.
a. Management Plan - (Factor 1). Subfactors (1), (2), and (3) are listed in descending order of importance.
Subfactor (1). Interaction between government/contractor staff.
Subfactor (2). Staffing levels and response time.
Subfactor (3). Quality Control Plan.
b. Work Execution and Subcontracting Plan - (Factor 2).
Subfactor (1). Selection and utilization of contractors.
Subfactor (2). Use of local business
c. Past Experience - (Factor 3). Ability to manage/construct multiple small to medium scale construction and repair projects.
d. Past Performance -(Factor 4). Client/Agency Surveys and the Past Performance Information Retrieval System (PPIRS). Other sources may include, but are not limited to, past performance information retrieved through Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s) or other personnel with knowledge of performance, Federal Awardee Performance and Integrity Information System (FAPIIS), and Electronic Subcontract Reporting System (eSRS).
C. Price Evaluation
Price will be evaluated, separetely and independtly, using price analysis techniques. In selecting the best overall proposal, the Government will consider the value of each proposal in terms of the quality offered for the price. The importance of price in the selection will increase as the quality differences between proposals decrease. For the purpose of evaluation, the Government will assume that 95% of the work will be done during normal working hours and that 5% will be done in other than normal working hours.
D. Basis of Award
The basis of award for the Job Order Contract, which is a Best Value, Tradeoff process, is based on Factor 1 - Management Plan, Factor 2 - Work Execution and Subcontracting Plan, Factor 3 - Past Experience, Factor 4 - Past Performance, and Price. The Contracting Officer will award a firm fixed-price Indefinite Delivery Indefinite Quantity Job Order Contract to the responsible Offeror whose proposal the Source Selection Authority determines conforms to the solicitation, is fair and reasonable with regard to pricing, and offers the best overall value to the Government, considering the price and non-price factors described herein. All evaluation factors, when combined, are considered significantly more important than the price. After the Government individually evaluates and rates each proposal, Source Selection Authority will compare proposals to determine which proposal represent the best value for award. The Government reserves the right to accept other than the lowest priced offer or to reject all offers.
E. Evaluation Procedures
1. SOURCE SELECTION EVALUATION BOARD (SSEB)
The SSEB will be established to conduct the evaluation of proposals received in response to this solicitation. The evaluation will be based on the content of the proposal, proposal corrections and any information obtained from other sources, e.g. past performance information. The SSEB will not consider any proposal information incorporated by reference, except as expressly allowed by this solicitation.
2. EVALUATION
Each member of the SSEB will independently consider all information provided in the proposal. Once the individual reviews are completed, the SSEB will evaluate the proposals and assign a consensus rating for each evaluation factor. Offerors are cautioned to put forth their best efforts for the proposal submission, and to furnish all required information clearly and completely. Offerors should not assume that they will have an opportunity to clarify or correct anything in their proposal after submitting it.
The Government reserves the right to allow proposal corrections, if deemed necessary. A “Competitive
Range” is a subjective determination of the most highly rated proposals in the event that discussions with
Offerors are required. In such an event, the Contracting Officer will establish a competitive range of all the most highly rated proposals.
If discussions are held, the Government may engage in a broad give and take with each Offeror in the competitive range, in accordance with FAR 15.306 (d). The Government will provide the Offeror an advance agenda for the discussions. During discussions, the Government may ask the Offeror to further explain its proposal and to answer questions about it.
Upon conclusion of discussions, those Offerors still considered the most highly rated, will be afforded an opportunity to submit their proposal revisions for final evaluation and selection.
3. DEFINITIONS
Deficiency is a material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.
Significant Weakness in the proposal is a flaw that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance.
Strength is an aspect of an offeror's proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
Significant Strength. A significant strength appreciably enhances the merit of a proposal or appreciably increase the probability of successful contract performance.
Uncertainty. Any aspect of the proposal for which the intent of the Offeror is unclear because there may be more than one way to interpret the offer or because inconsistencies in the offer indicate that there may be an error, omission, or mistake.
4. TECHNICAL RATING DEFINITIONS:
Combined Technical/Risk Ratings Color Rating Description Blue Outstanding Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses. Risk of unsuccessful performance is very low.
Purple Good Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.
Red Unacceptable Proposal does not meet requirements and contains one or more deficiencies. Proposal is unawardable.
6 PAST PERFORMANCE RISK RATINGS:
Performance Confidence Assessments Rating Description Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral) No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
Past Performance Relevancy Ratings Rating Definition Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
VOLUME 1 - TAB A
PROPOSAL DATA SHEET
SECTION 00 22 11 - ATTACHMENT 1
1. Name of Solicitation:
2. Name of Firm:
Address:
Phone:
Fax:
E-mail:
DUNS # (used for accessing the Construction Contractor Appraisal Support System (CCASS) or A-E
Contractor Administration Support System (ACASS) Database)
Also provide any other assigned number that identifies the member firm(s) in the ACASS or CCASS databases. If a separate DUNS has been created for a joint venture (J-V) it must also be submitted.
Provide a DUNS number for each company identified in any proposed Contractor-subcontractor association of firms. If the firm is a joint venture or contractor-subcontractor association of firms, list the individual firms and briefly describe the nature of the association. Provide DUNS for each. If the Offeror has never done work with the Government, provide the Tax ID number (TIN).
Firm 1:
Firm 2:
Firm 3:
Nature of Association:
3. AUTHORIZED NEGOTIATORS. FAR 52.215-11
The Offeror represents that the following persons are authorized to negotiate on its behalf with the
Government in connection with this Request for Proposals (RFP).
[List names, titles, and telephone number of the authorized negotiator.]
Name of Person Authorized to Negotiate:
Negotiator's Address:
Negotiator's Telephone:
Negotiator’s E-mail:
FORM A2
1. Project name and location (city, province, country)
2a. Name of Firm that performed this work (this should be the offeror or one of the offeror’s subcontractors)
2b. Offeror’s involvement in this project (write in “Prime”, “Subcontractor”, or “Joint-Venture Partner”)
3a. Project Owner’s name (Government Agency, commercial firm or other organization)
3b. Project Owner's complete address
4. Contract number of project
5. Date contract was signed
6. Date work was begun 7. Date work was completed or is scheduled for completion
8. Initial contract price (amount for which the offeror was responsible)
USD $
9. Current Contract amount (or amount offeror has invoiced to date)
USD $
10a. Technical point of contact of the Project Owner (name, title, e-mail address, phone number and fax number)
10b. Contracting point of contact of the Project Owner (name, title, e-mail address, phone and fax numbers)
11. Description of Design and Construction work (describe scope of project and DETAILED nature and scope of work actually performed by the Offeror. Include the % of design performed by the offeror, the type of construction, criteria used, and any other information to demonstrate same/similar to the project). For additional explanation, please attach a continuation sheet.
12. Current status of the project (fill in % complete)
The work is ________ % complete.
(If not 100%, indicate current status, on-schedule, behind, terminated for convenience, etc.)
13. English Speaking point of contact for Past Performance information (if different from Project Owner) (name, title, e-mail address, phone and fax numbers)
14. Explain any Problem(s) Encountered and Solution(s) to Resolve them. If the initial completion date or initial contract amount changed during performance of the work, or there were any safety issues, the offeror must provide an explanation here. If no problems were encountered and the contract was completed within the original schedule and budget, state so here. For additional explanation, please attach a continuation sheet.
FORM A3
NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)
CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information
Firm Name: CAGE Code:
Address: DUNs Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other
(Explain)
Percent of project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information
Contract Number:
Delivery/Task Order Number (if applicable):
Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy):
Explain Differences:
Original Contract Price (Award Amount):
Final Contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine
How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)
5. Client Information
Name:
Title:
Phone Number:
Email Address:
6. Describe the client’s role in the project:
7. Date Questionnaire was completed (mm/dd/yy):
8. Client’s Signature:
NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND
SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED
QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS
QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE
HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR.
HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT
THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO
VERIFY ANY AND ALL INFORMATION ON THIS FORM.
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
RATING DEFINITION NOTE
(E) Exceptional Performance meets contractual requirements and exceeds many to the
Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the
Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an
Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good Performance meets contractual requirements and exceeds some to the
Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner.
There should have been no significant weaknesses identified.
(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the
Government/Owner.
(U)
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not
Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.
TO BE COMPLETED BY CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY:
a) Quality of technical data/report preparation efforts
E VG S M U
N
b) Ability to meet quality standards specified for technical performance
E VG S M U
N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
E VG S M U
N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U
N
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
E VG S M U
N
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract
E VG S M U
N
3. CUSTOMER SATISFACTION:
a) To what extent were the end users satisfied with the project?
E VG S M U
N
b) Contractor was reasonable and cooperative in dealing with your staff
(including the ability to successfully resolve disagreements/disputes;
responsiveness to administrative reports, businesslike and communication)
E VG S M U
N
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
E VG S M U
N
d) Overall customer satisfaction
E VG S M U
N
4. MANAGEMENT/ PERSONNEL/LABOR
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
E VG S M U N
b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N
c) Government Property Control E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N
e) Utilization of Small Business concerns E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines
E VG S M U N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
E VG S M U N
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
E VG S M U N
5. COST/FINANCIAL MANAGEMENT
a) Ability to meet the terms and conditions within the contractually agreed price(s)?
E VG S M U N
b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
E VG S M U N
c) If this is/was a Government cost type contract, please rate the
Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
E VG S M U N
d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.
Yes No
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
Yes No
f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.
Yes No
6. SAFETY/SECURITY
a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
E VG S M U N
b) Contractor complied with all security requirements for the project and personnel security requirements.
E VG S M U N
7. GENERAL
a) Ability to successfully respond to emergency and/or surge situations
(including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
E VG S M U N
b) Compliance with contractual terms/provisions (explain if specific issues)
E VG S M U N
c) Would you hire or work with this firm again? (If no, please explain below) Yes No
d) In summary, provide an overall rating for the work performed by this contractor.
E VG S M U N
Please provide responses to the questions above (if applicable) and/or additional remarks.
Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk
(please attach additional pages if necessary):
FORM A4 - KEY PERSONNEL RESUME
Provide information, listed below, on separate sheets showing qualifications of: prime contractor’s project manager responsible for design and construction, the design manager, the designers of record for architecture, civil, geotechnical, fire protection (if known), electrical, and mechanical, and permit preparers (registered in New York).
For dining facilities, include the food service consultant. For construction, include the on-site manager and general superintendent (in charge of self-performed work). Use a continuation sheet, if needed. NOTE: Match the positions on this page to the list of key personnel in the narrative submission requirements and evaluation criteria.
a. Name and Title_________________________________________________________________
b. Assignment on this Project________________________________________________________
c. Name of Current Employer___________________________________________________________________
d. No. of Years (in the current field of expertise): With this Firm__________ With other Firms____________
e. Education:
Degree(s)/Year/Specialization/Institution_________________________________________________
f. Active Professional Registration, if any: __________________________________________________________
First Year/ Current Year ______/______
g. Describe Your Specific Experience and Qualifications Relevant to this Project (include previous employers, name of position, duration of employment, a brief description of duties, and highlight any potential strengths such as USACE experience):
End of Form A4
CLAUSES INCORPORATED BY REFERENCE
52.204-6 Data Universal Numbering System (DUNS) Number APR 2008 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2004 52.225-10 Notice of Buy American Act Requirement--Construction
Materials
FEB 2009
52.228-1 Bid Guarantee SEP 1996 252.204-7001 Commercial And Government Entity (CAGE) Code
Reporting
AUG 1999
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price Indefinite Delivery Indefinite Quantity Job Order Contract contract resulting from this solicitation.
(End of provision)
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
52.222-5 DAVIS-BACON ACT--SECONDARY SITE OF THE WORK (JUL 2005)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Davis-Bacon Act, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
5.9 % 6.9 %
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Seneca Army Depot Activity, Romulus, Seneca County, NY.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
Chief, Contracting Division U.S. Army Corps of Engineers New York District 26 Federal Plaza, Room 1843 New York, NY 10278
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any FAR (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
Section 00600 - Representations & Certifications
CORPORATE CERTIFICATE
IF THE CONTRACTOR IS A CORPORATION OR PARTNERSHIP, THE APPLICABLE PORTION OF THE
FORM LISTED BELOW MUST BE COMPLETED. IN THE ALTERNATIVE, OTHER EVIDENCE MUST BE
SUBMITTED TO SUBSTANTIATE THE AUTHORITY OF THE PERSON SIGNING THE CONTRACT. IF A
CORPORATION, THE SAME OFFICER SHALL NOT EXECUTE BOTH THE CONTRACT AND THE
CERTIFICATE.
FIRM __________________________
I, ______________________________ certify that I am the Secretary Of the Corporation named as Contractor herein, that _______________________________ who signed this contract on behalf of the Contractor was then
_____________________ of said Corporation, that said that contract was duly signed on behalf of said Corporation of its governing body and is within scope of its corporate powers.
In witness thereof, I have hereunto affixed my hand and seal of said
Corporation this _______________date of ____________ _.
CORPORATE SEAL ____________________
SECRETARY
AUTHORITY TO BIND PARTNERSHIP
This is to certify that the names and signatures of all partners are listed below and that the person signing the contract has authority actually to bind the partnership pursuant to its partnership agreements. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership with the United States of America, except as follows: (state "none" or describe limitations, if any) ____________________________________________
This authority shall remain in full force and effect until such time as the revocation of authority by any cause…
This is the start of the file's text. The full file is on GovTribe.