Text version
W16ROE11827733
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to revise and reissue the Price Schedule.
The due date of 13 September 2011 no later than 2:00 p.m. EST for submission of proposals is not extended.
NOTE: Offerors must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, by telegram, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR PROPOSAL IN ACCORDANCE WITH THE LATE PROPOSAL, LATE MODIFICATION OF PROPOSAL, OR LATE WITHDRAWAL OF PROPOSAL (FAR 15.208).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Sep-2011
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-11-R-0019
X 9B. DATED (SEE ITEM 11)
09-Aug-2011
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Sep-2011
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS-11-R-0019
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The offeror acceptance period has increased by 60 from 120 to 180.
SECTION 00700 - CONTRACT CLAUSES
The following have been added by full text:
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(End of provision)
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
AMENDMENT 0005
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lump Sum
STATION #4
FFP
All work Associated with Station #4 FOB: Destination
MILSTRIP: W16ROE11827733
PURCHASE REQUEST NUMBER: W16ROE11827733
NET AMT
0002 1 Lump Sum All work Associated with Spur Road
FFP
connecting Camp Shea Road to Stations #4 and #5 Access Road FOB: Destination
0003 1 Lump Sum All work Associated with the access road
FFP
from Stations #4 and #5 to the main road
0004 1 Lump Sum All work associated with Site work
FFP
around Station #4 and Station #5 including storm water detention basin #2
0005 1 Lump Sum
OPTION 1 POWER TELECOM
FFP
All work associated with the power telecom transmission lines
0006 1 Lump Sum OPTION 2 All work Associated with Station #1
FFP
0007 1 Lump Sum OPTION 3 All work Associated with Station #2
0008 1 Lump Sum OPTION 4 All work Associated with Station #3
0009 1 Lump Sum OPTION 5 All work Associated with Station #5
FFP
Breakdown pad
0010 1 Lump Sum
OPTION 6 OPS/STORAGE BUILDING
FFP
All work Associated with the Ops/Storage Building
0011 1 Lump Sum
OPTION 7 AMMO BREAKDOWN PAD
FFP
All work Associated with the Ammo Breakdown pad
0012 1 Lump Sum
OPTION 8 WAYENTS POND ROAD
FFP
All site work associated with the Ops/Storage, Ammo Breakdown pad, and Stations #1 and #2 including the access road to Wayents Pond Road and Storm water detention basin #4
0013 1 Lump Sum OPTION 9 All work Associated with the Access Road
FFP
Connecting Stations #1 and #2 and the Ops/Storage Building to Station #3 (from station 00 to 1060), including depressions associated with culverts C5 and C6
0014 1 Lump Sum OPTION 10 All work Associated with the main road
FFP
Connecting the access road to Stations #4 and #5 to Station #3 (from station 1060 to 2166), including depressions associated with culverts C3 and C4
TOTAL BASE
(CLINs 0001 to 0004) $____________________________
TOTAL OPTIONS
(CLINs 0005 to 0014) $____________________________
TOTAL OFFER
(CLINs 0001 to 0014) $____________________________
NOTES FOR PRICE SCHEDULE:
1. Offerors are required to submit a price for both the Base Items and the Optional Items on the Price Schedule or their offer will be rejected.
2. The low Offerors for the purpose of award will be the conforming technically acceptable offering with the lowest amount for the Total Base & Optional Items. The Government is under no obligation to award any Optional Item.
3. Any price which is materially unbalanced as to the price for the Base Items and Optional Items may be rejected. An unbalanced price is one, which is based on price significantly less than the cost for some work and prices are significantly overstated for other work.
4. Offerors are reminded that they must offer on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the Offerors thereto may render the price non-responsive and be cause for its rejection.
5. The proposal shall be good for 180 days after submission.
6. The Government has 180 days after receipt of notice to proceed to exercise any optional bid items.
7. The duration for work under any exercised option will be 365 days from the date of the option award.
If options are awarded separately from each other, each option will have a performance period of 365 days to be concurrent with the other optional performance periods and the performance period for the base bid.
(End of Summary of Changes)