Stratton VA Amend 0005.pdf
PDF 31 KB Posted
- Solicitation number
- W912DS-11-B-0002
About this file
Amendment 0005 revised specifications
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W16ROE10040438
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Include revisions to the Specifications as hereby attached.
2. Provide Questions and Answ ers for Informational Purposes Only.
The bid opening date of 17 March 2011 at 2:00 EST remains unchanged.
NOTE: Bidders must acknow ledge receipt of this amendment by the date and time specified in the solicitation (or as amended) by one of the follow ing methods: in the space provided on the SF 1442, by separate letter, or by telegram, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE
LATE BID, LATE MODIFICATIONS OF BIDS, OR LATE WITHDRAWAL OF BIDS (FAR 14. 304).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Mar-2011
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-11-B-0002
X 9B. DATED (SEE ITEM 11)
08-Feb-2011
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Mar-2011
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS-11-B-0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0005
Replace 60 psi Steam Line and Plumbing Upgrades Stratton VA Medical Center
Albany, New York
Amendment 0005
AMENDMENT 0005 to DRAWINGS and SPECIFICATIONS for Replacement of 60 psi Steam Line and Plumbing Upgrades, Stratton VA Medical Center, Albany, New York
SPECIFICATIONS
1. The following SPECIFICATIONS have been REVISED but NOT REISSUED:
‐ Section 00 80 00– replace paragraph G Phasing Requirements in its entirety with the following: “The contractor can perform work on multiple chase locations (remove the ceiling, set up the containment barrier, demolish the wall, remediate asbestos...) except the pipe replacement shall be reserved to only one chase at a time to limit the disruption of the system to a minimum. It may be possible for contractor to perform multiple chase pipe replacements only at the direction of the Contracting Officer, these decisions will be made on case by case basis during construction. The work sequence of the utility chases will be determined by the Contracting Officer.”
BIDDER’S QUESTIONS AND GOVERNMENT REPLY
1. Can one individual perform Site Supervision, QA/QC & SSHO activities? Response: No, please follow the requirements as stated in the solicitation.
2. Specification indicates that QA/QC & SSHO activities can be performed by one person. Can a Site Superintendent perform site supervision, QA/QC & SSHO activities? Response: No, please follow the requirements as stated in the solicitation.
3. Is it the government’s intent to allow only one column enclosure from the basement to the roof to be worked on at a single time? If so, in order to complete the base bid scope of work in the allowable 365 days, we would have to complete one entire riser every 5-1/2 days and work 7 days/week in order to complete the 66 different plumbing locations. To expand, this would mean that we would need to remove the ceiling, set up the containment barrier, demolish the wall, remediate asbestos, complete the mechanical work, test, insulate, patch, trim, paint, remove the containment barrier, and replace the ceiling for each of the six floors in 5-1/2 days-this is not feasible. Or, is it the government’s intent that this restriction only apply to the steam risers and associated chases? Response: Please refer to the revised section 00 80 00 paragraph G for phasing requirements. The construction duration will remain as stated paragraph 1 of the same specification section. The phasing requirement applies to the entire contract.
(End of Summary of Changes)