Poplar-2019ExpansionStructures-Pre-Bid_Overview.pdf

PDF 3 MB Posted

Attached to
Poplar Island, 2019 Expansion Structures, Talbot County, MD Federal contract opportunity
Solicitation number
W912DR19B0009
Issued by
Department of the Army Corps of Engineers Engineering District Baltimore

About this file

PRE BID OVERVIEW POWERPOINT

View the file

Other files for this federal contract opportunity

Other files attached to Poplar Island, 2019 Expansion Structures, Talbot County, MD, newest first.
File Type Posted
W912DR19B0009_BID_ABSTRACT_072519.pdf PDF
W912DR19B0009_Amendment_0002_071219.pdf PDF
Pre-Bid_SignIn-1July2019.jpg JPG image
W912DR19B0009_AMENDMENT_0001_070119.pdf PDF
W912DR19B0009_POPLAR_ISLAND_2019_EXPANSION_STRUCTURES_SOLICITATION.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

.59

“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

Poplar Island, 2019 Expansion Structures Project Overview for Pre-Bid Site Visit 1 July 2019

PAUL S. SARBANES

ECOSYSTEM RESTORATION

PROJECT AT POPLAR ISLAND

PRESENTATION OBJECTIVES

Poplar Expansion Overview

2019 Expansion Structures Scope

Requests For Information Process

Solicitation Schedule

POPLAR - PLAN FEATURE MAP

PHASE I

(EXISTING)

PHASE II

(EXISTING)

VERTICAL EXPANSION

(CELL 2 RAISING)

LATERAL

EXPANSION

(UNDERWAY)

VERTICAL EXPANSION

(CELL 6 RAISING)

ONGOING EXPANSION PROGRESS

Image taken 26 March 2019

2019 EXPANSION STRUCTURES – SCOPE

SHEET GI002

2019 EXPANSION STRUCTURES – SCOPE

SHEET GI901

72019 EXPANSION STRUCTURES – SCOPE

SHEET C-101

82019 EXPANSION STRUCTURES – SCOPE

SHEET C-501

9BID SCHEDULE

REQUESTS FOR INFORMATION

(RFI) PROCESS

All Questions Must Be Submitted through ProjNet www.projnet.org

Directions in Solicitation, pg 6 RFI Deadline is Friday 5 July @ 1000 http://www.projnet.org/

2019 EXPANSION STRUCTURES SCHEDULE

SCHEDULE*

Solicitation 20 June 2019 Pre-Bid Site Visit 1 July 2019 RFI Deadline 5 July 2019 @ 10am EST Bid Opening 16 July 2019 @ 11am EST *Schedule as of 1 July 2019

300 Day Duration = Fall 2019 to Summer 2020

CONCURRENT POPLAR CONSTRUCTION

Lateral CT 3 through July 2020

Dredged Material Inflow Winter 2019/2020

MES Spillway Operations Ongoing

Rock Reefs Early 2020?

Lateral CT 2 To Be Completed

Summer 2019

THANK YOU FOR ATTENDING

SITE VISIT:

Cell 7 Cell 9 Staging Areas South Bulkhead

Paul S. Sarbanes ecosystem restoration project at poplar island
Slide Number 2
Slide Number 3
ONGOING EXPANSION PROGRESS
2019 Expansion STRUCTURES – SCOPE�SHEET GI002�
2019 Expansion STRUCTURES – SCOPE�SHEET GI901�
2019 Expansion STRUCTURES – SCOPE�SHEET C-101�
Slide Number 8
BID SCHEDULE�
Slide Number 10
2019 Expansion Structures SCHEDULE
CONCURRENT POPLAR CONSTRUCTION
Thank you FOR ATTENDING