3. DATE OPENED PAGE

29-Aug-18 1 of 2

4. ISSUING OFFICE Name and title of Certifying Official (Type) I CERTIFY that I have opened, read, and recorded on this abstract all offers Signature Date Signed 29 August 2018 received in response to this solicitation.

USACE, BALTIMORE DISTRICT

2 Hopkins Plaza BALTIMORE, MD 21201 Contracting Officer: Ashley M. Wingfield

5. PROJECT TITLE

8. GOVERNMENT ESTIMATE

(Check A, B or C and complete D, E, and F.)

A. HIRED LABOR

B. REASONABLE CONTRACT B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) Contract Specialist: Patricia Morrow (Without Profit)

X C. REASONABLE CONTRACT C. Amendment Acknowledged: C. Amendment Acknowledged (Including Profit)

7A. 7B. 7C. D. E. F. E. F. E. F.

ITEM DESCRIPTION OF OFFERED ITEM EST. UNIT UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED No. QUANTITY PRICE AMOUNT IGE PRICE AMOUNT PRICE AMOUNT

0001 Reimbursement of Performance and Payment Bonds 1 JOB XXX 610,363.43$ XXX 350,000.00$ XXX 210,694.00$

0002 Mobilization and Demoblization 1 JOB XXX 4,253,825.52$ XXX 6,600,000.00$ XXX 3,859,723.00$

0003 Dike Fill Material 1,362,700 C.Y. 8.92$ 12,155,284.00$ 7.00$ 9,538,900.00$ 8.50$ 11,582,950.00$

0004 STONEWORK

0004AA 350-lb Armor Stone – Quarried, Shipped, and Placed on New Dike

47,700 TON 86.48$ 4,125,096.00$ 85.00$ 4,054,500.00$ 94.00$ 4,483,800.00$

0004AB

650-lb Armor Stone – Quarried, Shipped, and Placed on New Dike 34,400 TON 74.70$ 2,569,680.00$ 85.00$ 2,924,000.00$ 98.00$ 3,371,200.00$

0004AC 250-lb Armor Stone – Excavated from Existing Dike and Stockpiled

3,050 C.Y. 59.51$ 181,505.50$ 19.50$ 59,475.00$ 40.00$ 122,000.00$

0004AD

350-lb Armor Stone – Excavated from Existing Dike and Placed on New Dike

11,200 TON 73.19$ 819,728.00$ 59.00$ 660,800.00$ 55.00$ 616,000.00$

0004AE 3000/4000-lb Armor Stone, Excavated from Existing Dike and Stockpiled

4,150 C.Y. 73.19$ 303,738.50$ 21.00$ 87,150.00$ 35.00$ 145,250.00$

0004AF Quarry Run Stone – Quarried, Shipped, and Placed on New Dike/Reverse Filter

39,900 TON 69.41$ 2,769,459.00$ 78.00$ 3,112,200.00$ 77.00$ 3,072,300.00$

0004AG Minus 12-inch Shot "Rock Fill" – Quarried, Shipped, and Placed on New Dike

19,300 TON 74.81$ 1,443,833.00$ 80.00$ 1,544,000.00$ 79.00$ 1,524,700.00$

0004AH

Bedding Stone – Quarried, Shipped, and Placed on New Dike

20,400 TON 52.44$ 1,069,776.00$ 60.00$ 1,224,000.00$ 65.00$ 1,326,000.00$

0004AJ Bedding Stone – Excavated from Existing Dike and Placed on New Dike

1,300 C.Y. 53.20$ 69,160.00$ 60.00$ 78,000.00$ 72.00$ 93,600.00$

0004AK

#57 Stone - Quarried, Shipped, and Placed on Reverse Filter

7,700 TON 61.15$ 470,855.00$ 70.00$ 539,000.00$ 53.00$ 408,100.00$

0004AL

#7 Stone - Quarried, Shipped, and Placed on Reverse Filter

15,000 TON 66.03$ 990,450.00$ 60.00$ 900,000.00$ 53.50$ 802,500.00$

0005 Geotextile 172,800 S.Y. 11.40$ 1,969,920.00$ 7.00$ 1,209,600.00$ 9.54$ 1,648,512.00$

0006 Crushed Stone Roadway 29,900 S.Y. 37.84$ 1,131,416.00$ 23.00$ 687,700.00$ 20.00$ 598,000.00$

0007 Settlement Monitoring Pads 4 EA 2,023.67$ 8,094.68$ 3,587.00$ 14,348.00$ 2,000.00$ 8,000.00$

0008 Seeding and Erosion Control 58,300 S.Y. 7.88$ 459,404.00$ 3.00$ 174,900.00$ 2.40$ 139,920.00$

Cell 11 Spillway Pipe Placement, Outfall Protection, Sand Cover, and Leveling Pad

1 JOB XXX 275,977.34$ XXX 588,350.00$ XXX 313,500.00$

0010 Cell 1D Spillway Demolition 1 JOB XXX 94,229.28$ XXX 71,750.00$ XXX 50,000.00$

TOTAL BASE BID AMOUNT 35,771,795.25$ 34,418,673.00$ 34,376,749.00$

Option

Cell 11 Spillway Foundation and Structure

1 JOB XXX 993,989.14$ XXX 287,000.00$ XXX 880,000.00$

TOTAL ESTIMATED OPTIONAL AND BASE BID AMOUNT 36,765,784.39$ 34,705,673.00$ 35,256,749.00$

PERCENTAGE ABOVE OR BELOW IGE -5.60% -4.10%

NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. Prescribed by GSA-FAR(48 CER)53.236-1 OPTIONAL FORM 1419 (11-88)

ABSTRACT OF OFFERS - CONSTRUCTION 2. DATE ISSUED1. SOLICITATION NUMBER

6. NUMBER OF AMENDMENTS ISSUED: 2 (two) Yes

Bid Bond 20%

20-Jul-18W912DR18B0011

Poplar Island Lateral Expansion Contract 3 Poplar Island, Talbot County, Maryland

No. 1

9. OFFERS

Bid Bond $3M

Coastal Design & Construction, Inc.

P.O. Box 650

Gloucester, VA 23061

Yes

No. 2

H&L CONTRACTING, LLC.

38 HOMAN AVENUE

BAY SHORE, NY 11706

Ashley M. Wingfield

1. SOLICITATION NUMBER PAGE

ABSTRACT OF OFFERS 2 OF 2

CONSTRUCTION

CONTINUATION SHEET

B. BID SECURITY (Type and Amount B. BID SECURITY (Type and Amount)B. BID SECURITY (Type and Amount B. BID SECURITY (Type and Amount)

3. CONTRACT ITEMS C. AMENDMENT ACKNOWLEDGED C. AMENDMENT ACKNOWLEDGED C. AMENDMENT ACKNOWLEDGED C. AMENDMENT ACKNOWLEDGED 7A. B. C. D.

ITEM DESCRIPTION OF OFFERED ITEMS ESTIMATED UNIT E. UNIT F. ESTIMATED E. UNIT F. ESTIMATED E. UNIT F. ESTIMATED E. UNIT F. ESTIMATED

NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

0001 Reimbursement of Performance and Payment Bonds 1 JOB XXX 170,000.00$

0002 Mobilization and Demoblization 1 JOB XXX 14,200,000.00$

0003 Dike Fill Material 1,362,700 C.Y. 6.00$ 8,176,200.00$

0004 STONEWORK

0004AA 350-lb Armor Stone – Quarried, Shipped, and Placed on New Dike

47,700 TON 57.00$ 2,718,900.00$

0004AB

650-lb Armor Stone – Quarried, Shipped, and Placed on New Dike

34,400 TON 66.00$ 2,270,400.00$

0004AC 250-lb Armor Stone – Excavated from Existing Dike and Stockpiled

3,050 C.Y. 19.00$ 57,950.00$

0004AD 350-lb Armor Stone – Excavated from Existing Dike and Placed on New Dike

11,200 TON 19.00$ 212,800.00$

0004AE 3000/4000-lb Armor Stone, Excavated from Existing Dike and Stockpiled

4,150 C.Y. 20.00$ 83,000.00$

0004AF Quarry Run Stone – Quarried, Shipped, and Placed on New Dike/Reverse Filter

39,900 TON 49.00$ 1,955,100.00$

0004AG Minus 12-inch Shot "Rock Fill" – Quarried, Shipped, and Placed on New Dike

19,300 TON 64.00$ 1,235,200.00$

0004AH Bedding Stone – Quarried, Shipped, and Placed on New Dike

20,400 TON 49.00$ 999,600.00$

0004AJ Bedding Stone – Excavated from Existing Dike and Placed on New Dike

1,300 C.Y. 16.00$ 20,800.00$

0004AK #57 Stone - Quarried, Shipped, and Placed on Reverse Filter

7,700 TON 56.00$ 431,200.00$

0004AL #7 Stone - Quarried, Shipped, and Placed on Reverse Filter

15,000 TON 54.00$ 810,000.00$

0005 Geotextile 172,800 S.Y. 10.00$ 1,728,000.00$

0006 Crushed Stone Roadway 29,900 S.Y. 15.00$ 448,500.00$

0007 Settlement Monitoring Pads 4 EA 4,500.00$ 18,000.00$

0008 Seeding and Erosion Control 58,300 S.Y. 2.10$ 122,430.00$

Cell 11 Spillway Pipe Placement, Outfall Protection, Sand Cover, and Leveling Pad

1 JOB XXX 200,000.00$

0010 Cell 1D Spillway Demolition 1 JOB XXX 100,000.00$

TOTAL BASE BID AMOUNT 35,958,080.00$

Option

Cell 11 Spillway Foundation and Structure

1 JOB XXX 800,000.00$

TOTAL ESTIMATED OPTIONAL AND BASE BID AMOUNT 36,758,080.00$

PERCENTAGE ABOVE OR BELOW IGE -0.02%

NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. Prescribed by GSA-FAR(48 CER)53.2 OPTIONAL FORM 1419 (11-88)

2. PROJECT TITLE

Bid Bond 20%

Yes

OFFERS (Continued)

Poplar Island Lateral Expansion Contract 3 Poplar Island, Talbot County, Maryland

No. 6No. 3 No. 4

The Wesson Group, LLC 55 East Main Street Suite 210

Johnstown, NY 12095

W912DR18B0011

No. 5