AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate the follow ing changes into the solicitation:

1. Provide Site Visit Sign In Sheet

2. Revise Specifications

3. Provide MDE Water Quality Certification

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR18B0011

X 9B. DATED (SEE ITEM 11)

20-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Aug-2018

CODE

USACE, BALTIMORE DISTRICT

2 HOPKINS PLAZA

ROOM 03-G-01

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR18B0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMMENDMENT 0001

The following changes have been made to the specifications:

SPECIFICATIONS:

1. TABLE OF CONTENTS, page 3: After DIVISION 35, Section 35 41 00 DIKE CONSTRUCTION, Please Insert Appendix A – MDE Water Quality Certification

2. SECTION 35 41 00, immediately after the end of this section please insert APPENDIX A – MDE Water Quality Certification, as provided per this Amendment.

GENERAL:

3. Pre-Site Visit: Attached are the sign in sheets for the pre-site visit held on 8-1-2018.

ATTACHMENTS:

MDE Water Quality Certification Sign in Pre-site Visit

(End of Summary of Changes)

APPENDIX A

.59

“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

Lateral Expansion Contract 3 Project Overview for Pre-Bid Site Visit 1 August 2018

PAUL S. SARBANES

ECOSYSTEM RESTORATION

PROJECT AT POPLAR ISLAND

PRESENTATION OBJECTIVES

Poplar Expansion Overview

Lateral Contract 3 Scope

Requests For Information Process

Lateral Contract 3 Schedule

POPLAR - PLAN FEATURE MAP

PHASE I

(EXISTING)

PHASE II

(EXISTING)

VERTICAL EXPANSION

(CELL 2 RAISING)

LATERAL

EXPANSION

VERTICAL EXPANSION

(CELL 6 RAISING)

Presenter Presentation Notes Phase 1 - 1998-2000, $54.8M, 640ac Phase 2 - 2000-2002, $41.4M, 500ac

LATERAL EXPANSION CONTRACT 3 - SCOPE

Base Contract:

1) Cell 11 Dike Construction

2) Removing & Stockpiling Existing Stone

3) Cell 11 Spillway Base & Pipes

4) Cell 1D Spillway Demo Options:

5) Cell 11 Spillway Pad & Structure

SAND STOCKPILE LOCATIONS – GI002

STONE STOCKPILE LOCATIONS – GI002

7CONTRUCTION SEQUENCE

GI006 & C-103 NOTES

REQUESTS FOR INFORMATION

(RFI) PROCESS

All Questions Must Be Submitted through ProjNet www.projnet.org

Directions in Solicitation, pg 8-9 RFI Deadline is 10 August @ 1000 http://www.projnet.org/

CONTRACT 3 SCHEDULE

SCHEDULE*

Solicitation 20 July 2018 Pre-Bid Site Visit 1 August 2018 RFI Deadline 10 August 2018 @ 10am EST Bid Opening 29 August 2018 @ 11am EST *Schedule as of 1 August 2018

600 Day Duration = Fall 2018 to Mid 2020

CONCURRENT POPLAR CONSTRUCTION

Sand Stockpile through Feb 2019

Lateral CT 2 through June 2019

Dredged Material Inflow Winter 2018/2019

Spillway/Inlet Structures Summer/Fall 2019

MES Spillway Operations Ongoing

THANK YOU

8-1-18 Poplar Island -Lateral 3-Pre-Bid Project Overview.pdf
Paul S. Sarbanes ecosystem restoration project at poplar island
Slide Number 2
Slide Number 3
Lateral Expansion Contract 3 - SCOPE�
SAND STOCKPILE LOCATIONS – GI002
STONE STOCKPILE LOCATIONS – GI002
CONTRUCTION SEQUENCE �GI006 & C-103 Notes
Slide Number 8
Contract 3 SCHEDULE
CONCURRENT POPLAR CONSTRUCTION
Thank you