W912DR-17-B-0019-0003.pdf

PDF 869 KB Posted

Attached to
West Filter Building Valve Replacements Federal contract opportunity
Solicitation number
W912DR-17-B-0019
Issued by
Department of the Army Corps of Engineers Engineering District Baltimore

About this file

Amendment 0003

View the file

Other files for this federal contract opportunity

Other files attached to West Filter Building Valve Replacements, newest first.
File Type Posted
W912DR-17-B-0019-0002.pdf PDF
W912DR-17-B-0019-01.pdf PDF
W912DR-17-B-0019.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate the follow ing changes into the solicitation:

1. Provide Updated Price Schedule

2. Issue RFI Responses

3. Extend the Bid Opening time from 10AM to 2PM EST

4. Provide Site Visit Sign-in Sheet

1. CONTRACT ID CODE PAGE OF PAGES

1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Sep-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR17B0019

X 9B. DATED (SEE ITEM 11)

25-Aug-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Sep-2017

CODE

USACE, BALTIMORE DISTRICT

10 S. HOWARD ST

ROOM 7000

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR17B0019

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 25-Sep-2017 10:00 AM to 25-Sep-2017 02:00 PM.

The following have been modified:

PRICE SCHEDULE

UNIT PRICE SCHEDULE –

REVISED: SEP. 14, 2017

Item No. Description Estimated Quantity

Unit Price Amount

0001 West Filter Building Valve Replacement:

All costs in connection with work at the West Filter Building complete, with the exception of work covered under Bid Items 0002 through 0009 below. JOB LS $__________________

0002 Expansion Joint Repair: All costs in connection with Expansion Joint Repair as specified in Section 03 01 32, and defined in contract drawing sheet S-1. 30 LF $__________ $__________________

0003 Pressure Injected Epoxy Resin Repair: All costs in connection with Pressure Injected Epoxy Resin Repair as specified in Section 03 01 32, and defined in contract drawing sheet S-1. 130 LF $__________ $__________________

0004 Pressure Injected Foam Resin Repair: All costs in connection with Pressure Injected Foam Resin Repair as specified in Section 03 01 32, and defined in contract drawing sheet S-1. 20 LF $__________ $__________________

0005 Concrete Spall Repair: All costs in connection with Concrete Spall Repair as specified in Section 03 01 32, and defined in contract drawing sheet S-1. 55 SF $__________ $__________________

TOTAL BASE AMOUNT

Item No. Description Estimated Quantity

Unit Price Amount

OPTION ITEMS

0006 84” West Filter Effluent Butterfly Valve Electro-Hydraulic Actuators: All costs associated with installation of new self-contained electro-hydraulic actuators on existing 84 inch West Filter Effluent Butterfly Valves V-177 and V-178 as specified in Section 33 13 05 and defined on the contract drawings. JOB LS $__________________

0007 84” West Filter Effluent Butterfly Valve Replacement: All costs associated with installation of new 84 inch West Filter Effluent Butterfly Valves V-177 and V- 178 as specified in Section 40 05 13 and defined on the contract drawings. JOB LS $__________________

0008 30” East Filter Backwash Butterfly Valve Hydraulic Actuator: All costs associated with installation of new hydraulic actuator on existing East Filter Backwash Butterfly Valve V-4-189 as specified in Section 40 05 13 and defined on the contract drawings. JOB LS $__________________

0009 30” Emergency Backwash Butterfly Valve Electric Actuator: All costs associated with installation of new electric actuator on Emergency Backwash Butterfly Valve V-4-174 as specified in Section 40 05 13 and defined on the contract drawings. JOB LS $__________________

TOTAL BASE AND OPTION AMOUNT

NOTES TO BIDDERS

Offerors must quote on all items including Option Items. Failure to quote on all items may be cause for rejection of the proposal.

Option Items may be exercised at any time within 90 calendar days after contract award.

The Contracting Officer may exercise the Option Items by written notice to the Contractor, postmarked within the period specified above. The Government is not obligated to exercise the Option Items.

No additional time for contract completion will be allowed when an Option Item is exercised.

EVALUATION OF OPTIONS:

Except when it is determined not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

The following have been added by full text:

RFI RESPONSES

OFFERORS’ REQUESTS FOR INFORMATION (RFI’S) AND GOVERNMENT ANSWERS

For information only Q1) Drawing M-1 does not show a valve with designation V-4-33-6, or a flow meter for filter 33;

however, note 1 on M-2 states that the plan and sections provided on that drawing are typical for all filters 27-36. Please advise if filter 33 has the valve and flow meter.

A1) V-4-33-6 shall be replaced as indicated in the Valve Schedule on Sheet M-4. The associated 18" filter effluent flowmeter shall also be replaced as indicated in Notes 9 and 12 of Sheet M-2.

These items are not shown on the Filter Pipe Gallery Plan on Sheet M-1 because they are underneath the existing stair landing.

Q2) The valve schedule on drawing M-4 is fuzzy and hard to read. Could a more clear copy be provided?

A2) Valve schedule is legible in the electronic PDF version of the drawings. Drawings should be viewed at full scale.

Q3) Paragraph 1.1 a in 33 01 90 – Internally Bonded CRFP Lining states that there are two sections of 84” pipe to be lined, each 101 feet in length. M-3 shows two sections of pipe approximately 10’-6” in length each. Please confirm the sections of pipe and valve to be lined are as shown on the drawings, or advise where the additional lengths of pipe are located.

A3) The 84-inch piping to be repaired with internally bonded CFRP lining are the two 84" steel filter effluent piping segments on either side of each 84" butterfly valve V-177 and V-178 as shown on contract drawing M-3. Section 33 01 90, paragraph 1.1.a.1 will be corrected by Amendment. Additionally, Note 1 on Drawing M-3 will be corrected to specify that CFRP lining shall not be applied to 84” butterfly valves V-177 and V-178.

Q4) Reference specification 01 11 00 – can the Corps of Engineers provide a list of items to be salvaged on the project?

A4) Refer to Contract Drawing M-1, Note 3.

Q5) Due the complexity of the large valve work on this project, is it possible to extend the bid date to give vendors and contractors more time to accurately price the project? This should create more competitive, lower prices for the owner.

A5) No, the bid date will remain as issued in the solicitation.

Q6) At the site visit, it was noted that lead dust and chips were on the floor. Additionally, there is lead paint flaking off the walls and ceilings. Is the removal of all lead paint from all ceilings, walls and floors part of the work of this contract? If so, is the lead paint abatement required in the entire building or only in the areas we are working?

A6) Lead paint test results are included in Specifcation Section 02 83 13.00 20, "Lead in Construction". No lead based paint has been identified on the walls, floors, or ceilings in the West Filter Gallery. Removal of the existing paint on these surfaces is required as part of the surface cleaningidentified in Note 10 on M-1, which shall include the entire length of the West Filter Gallery. This note will be modified by Amendment to clarify the extent of cleaning..

Q7) Please advise what style of valve is to be provided for the 84” butterfly valves. It appears that FLGxPE valves are currently installed with a sleeve type coupling. Is the new valve and coupler to be the same configuration? A PExFLG of this size may not be available. Would a FLGxFLG valve with a flanged coupling adapter be suitable? If so, please provide a specification for flanged coupling adapters.

A7) Refer to Valve Schedule Note 8 on Contract Drawing M-4 indicating the 84” butterfly valves V-177 and 178 as plain end by flanged. A flanged by flanged valve with coupling would also be acceptable providing the coupling meets the requirements of Specification Section 40 05

13. Contractor is responsible for any piping modifications required for proper installation. This will be clarified by an Amendment to Valve Schedule Note 8 on Drawing M-4.

--END

(End of Summary of Changes)