C-5_Amendment_0003.pdf

PDF 1 MB Posted

Attached to
Maintenance Dredging of Tw itch Cove and Big Thorofare at Smith Island
Solicitation number
W912DR-17-B-0002
Issued by

About this file

Amendment 0003 This amendment hereby incorporates the following changes into the solicitation: 1. Provide RFI responses. 2. Provide map of two placement sites. 3. The liquidated damages for the referenced project are $1045.00. 4. Extend the bid opening date to January 24, 2017 to allow for additional time to respond to pending RFI's.

View the file

Other files

File Type Posted
G-24_Bid_Abstract_.xlsx XLSX spreadsheet
C-5_Amendment_0005.pdf PDF
C-5_Amendment_0004.pdf PDF
Amd_0004_Plans.pdf PDF
C-5_Amendment_0002.pdf PDF
C-5_Amendment_0001.pdf PDF
C-5_Updated_Drawings_20160630.pdf PDF
C-5_Attachment_D_-_SF_LLL.pdf PDF
C-5_Attachment_B_-_S-1_02.pdf PDF
C-5_Attachment_E_-_Specifications.pdf PDF
C-5_Attachment_F_-_Drawings.pdf PDF
C-5_Attachment_C_-_EFT_Form.pdf PDF
C-5_Solicitation_w-Corrections.pdf PDF
C-5_Attachment_A_-_Wage_Determination_MD160012.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment hereby incorporates the follow ing changes into the solicitation:

1. Provide RFI responses.

2. Provide map of tw o placement sites.

3. The liquidated damages for the referenced project are $1045.00.

4. Extend the bid opening date to January 24, 2017 to allow for additional time to respond to pending RFI's.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Dec-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR-17-B-0002

X 9B. DATED (SEE ITEM 11)

09-Nov-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Dec-2016

CODE

U.S. ARMY CORPS OF ENGINEERS, BALTIMORE

10 S. HOWARD STREET

ROOM 7000

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR-17-B-0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

SUMMARY OF CHANGES

Requests for Information

Question 001: Reference Sec. 01 45 10 / Pg. 5 / 3.4.3 / ……Submittals clerk…….be physically present at the construction site during work…Our “Submittal Clerk” is stationed here at our home office. Can you please remove this spec stating that the submittal clerk needs to be physically present at the site?

Response: Yes, that setup is acceptable.

Question 002: Reference Sec. 35 20 23 / Pg. 38 / 2.11.4 / ……The target elevation for material placed in Area 3 is… I believe this should read “……The target elevation for material placed in Area 4 is …….”

Response: Yes, this will be corrected. This should read the target elevation placed in Area 4 is +2.5 to 3 ft

MLLW.

Question 003: Reference Plan drawing V-105 / Cell 6 There appears to be a good deal of vegetation in Cell 6.

Please confirm that the contractor is not required to do any vegetation clearing for this project.

Response: Yes, the contractor is not required to remove any vegetation. Placement of dredged material will be done around existing vegetation.

Question 004: Reference Sec. 35 20 23 / Pg. 1 / 1.2 / Due to environmental concerns, dredging is permitted between October 16 and April 14. // Sec. 35 20 23 / Pg. 2 / 1.2 / Between February 15 and August 15 very limited construction activities will be permitted within the rookery zone shown on the contract drawings. Evaluation - In regards to the environmental windows shown above, and the fact that this current project is being bid on Dec. 13th, keeping in mind that a typical award comes 45 days after the bid date which would then push this project to begin around February 1st of 2017. This would put the contractor about 15 days before the Swan Island environmental windows close and 2.5 months from the close of the dredging window. Due to this time frame the contractor wouldn’t be able to begin this project until August 16th of 2017 in which the contractor can then begin work at the disposal area.

In reference to my evaluation statement, why is this project being bid 8 months before any construction activities can begin?

Response: Your evaluation is accurate. We assume work will begin in late summer or fall of 2017. This project is being advertised now so that we can get the contract awarded and minimize the risk of losing the funding.

Question 005: Reference Plan drawings / Sheet V-111 / Note 1 / It is highly recommended that the Contractor contact a manufacturer of the concrete armor units… Can you please send out some suppliers that would manufacture these concrete armor units?

Response: The concrete armor units shall be A-Jacks or approved equivalent. A-Jacks are manufactured by Contech Engineered Solutions. Other suppliers may also be able to manufacture these units, but we do not have any available information on this.

W912DR-17-B-0002

Question 006: Reference Plan drawing V-112 Can you please overlay this drawing on Google Earth showing the placement areas? The drawing that is provided is extremely difficult to gage where these placement areas are in relation to the real world.

Response: See Attached Map

Question 007: The liquidated damages in the specs is saying $1,500,000.00 per day. Is this amount correct?

Response: No, The liquidated damages for the referenced project are $1045.00 in accordance with:

Liquidated Damages for FY 16-17 Maintenance Dredging – Various Projects, Chesapeake Bay, Maryland, dated 13 October 2015.

Attachments:

Attachment A - NewTwitchMap1ForPN-May2016

Attachment B -NewTwitchMap2ForPN-May2016

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 20-Dec-2016 10:00 AM to 24-Jan-2017 10:00 AM.

(End of Summary of Changes)