AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO.:

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO.

PROJECT NO. (If applicable)

0003 AUG 25, 2015

6. ISSUED BY

USAED-Baltimore District Contracting Division P.O. Box 1715 Baltimore MD 21203-1715

CODE USAED ADMINISTERED BY:

See Item 6

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (x) 9A. AMENDMENT OF SOLICITATION NO.

X

W912DR-15-B-0003

9B. DATED (SEE ITEM 11)

AUG 05, 2015

10A. MODIFICATION OF CONTRACT/

ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers ___ is not x is extended.

DATE OF RECEIPT OF PROPOSALS: SEE TEXT

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE

DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER No. ITEM 10A

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR43.103(b)

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor _ is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

REPLACE COLLAPSED STORM AIRFIELD DRAINAGE SYSTEM

JOINT BASE ANDREWS – NAVAL AIR FACILITY, MARYLAND

SOLICITATION:

1) The bid opening time and date for this project is extended to 1:00 PM, local time, Sep 10, 2015. Change Standard Form 1442, Block 13a, of the Solicitation to reflect this change.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY ________________________________

(signature of person authorized to sign)

BY _________________________________________

(Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

PAGE 2 OF 2 PAGES

AMENDMENT NO. 0003 TO ADVERTISED RFP W912DR-15-B-0003

EFFECTIVE AUG 25, 2015

SPECIFICATIONS:

2) Section 33 05 24, Cured-In Place Pipe Lining (CIPPL), Paragraph 1.2.3 CIPP Wall Thickness: Delete the words “Creep Retention Factor 33%” and substitute the words “Creep Retention Factor 50%.”

3) Section 33 05 25, Centrifugally Cast Mortar Pipe Lining (CCMPL), Paragraph 1.4.1.5 Contractors Experience: Delete this paragraph in its entirety and substitute the following revised paragraph:

“1.4.1.5 Contactor’s Experience

A statement of the Contractors experience. The Contractor shall have a minimum of three (3) years of continuous experience installing CCMPL in pipe of a similar size, length and configuration as contained in this contract. A minimum of 150,000 linear feet of the proposed product is required and minimum of 6 installations are required as applicable to this contract.

The lead personnel including the superintendent, the foreman and the lead crew personnel for the CCTV inspection, the CCMPL installation, liner curing and the robotic service reconnections must have a minimum of three (3) years of total experience with the CCMPL technology proposed for this contract and must have demonstrated competency and experience to perform the scope of work contained in this contract. The name and experience of each lead individual performing work on this contract shall be submitted with the PWS.”

GENERAL:

4) Requests for Information and Government Responses: Requests for information and Government responses, dated August 24, 2015, are attached for information only.

ATTACHMENT: A/S.

REQUESTS FOR INFORMATION AND GOVERNMENT RESPONSES

AUGUST 24, 2015

Reference the price Schedule page 3‐6 of 83 in the documents and Drawing GC003 sheet 25 of 342: Drawing 302 lists five phases of construction. The price schedule lists the work shown in phases 2 and 3 as being the base bid and phase 4 as the optional bid. Where is the pricing for phases 1 and 5 to be submitted? Will phases 1 and 5 of the project also be optional?

Phases 1 and 5 are excluded from this contract per Plan Title Sheet.

Solicitation page 1 of 83 lists a Notice to Bidders stating that funds are not presently available for this effort and that no award will be made under this solicitation until funds are available. What is the anticipated time frame for award of this project?

late September 2015

The documents for the project list two specifications for Pipe Lining – Section 33 05 24: Cured in Place Pipe Lining and Section (CIPPL) and 33 05 25: Centrifugally Cast Mortar Pipe Lining (CCMPL). Which method is to be used for which of the storm sewer pipe lines designated on the plans for relining?

The Contractor may select either method or a combination of both methods provided they meet the requirements of the contract.

What is the geometry (shape) of the pipelines designated for relining? Are all of the pipelines circular in shape?

Pipelines designated for lining are circular.

The storm sewer reconstruction work for 60” to 108” will require on site resin impregnation (over the hole wet out) of the CIPP liners. This work will require around the clock operations. Will this be permissible?

See the Specificaions

Will bypass pumping of the line sections be required during CIPP reconstruction operations and if so, what capacity system will be required for each diameter line section?

Yes, bypass puming will be required and the capacity of the puming is to be determined by the Contractor.

What is the accessibility for water? What types of hose ramps, if necessary, will be required to cross taxiways?

How far away is the water source?

There are fire hydrants as indicated on plans.

Ramps able to sustain aircraft loads might be required or coordination to close taxiways, as needed.

Water lines are indicated on plans.

How is the CIPP cure water to be disposed? Can the water flow downstream to the receiving body?

Cure water must either be captured and disposed of offbase or the Contractor may obtain a NPDES permit. The cure water is considered a non‐permitted discharge per the NPDES "General Permit for Stormwater Associtated with Contruction Activity" that has been obtained for this project.

Provide the design criteria for the CIPP lining: depths of the pipe lines, soil modulus, ovality of pipes, water loadings, live loadings, etc.

See the Plans for locations and depths of pipes and soil boring data. See the two pipe lining Specifiations for structural requirements.

What are the criteria for having cranes on the site to facilitate the installations of the CIPP?

See the Specifications

Describe the accessibility to the work site for the construction crews. How much time should be allowed for the work3ers to access the job site?

See the Specifications

What type of barricades will be required around the construction equipment and construction activities, given the proximity of the pipelines to the airfield?

Varies depending on the location on airfield. See the Plans and Specifications.

What is diameter and construction method for unmarked line section between FS‐20 PH 5 and FS 27 –PH 5?

This is a Phase 5 pipe which is excluded from this contract.

Can access pits be installed to facilitate CIPP lining such as for the large diameter storm sewers? Can pits be installed where the CIPP liner terminates as a tap into another pipeline?

Yes, see Plan Sheet CU001, note 9.

Will after hour delivery of fuel and resin be allowed to the job site?

See the Specifications

Will base security be necessary to access manholes and underground pipelines?

See the Specifications

Will a storage area be provided on base for equipment and materials?

See the Plans

Will mats / access roads be required for truck to access the various manholes / inlets in the grassy infield between the

See the Plans active runways and taxiways?

Are CCTV videos available for review pre bid of the pipe lines designated for relining?

CCTV videos are not available prior to bid.

What procedures / delays / work stoppages are anticipated for weather? Visiting dignitaries? Security?

See Specifications for weather and ramp freeze information.

How much time should be allowed for the construction crews to access the job site at the start of each shift?

See the plans for laydown area and Contractor manned security gate locations.

What the security clearance requirements for the construction workers to be employed on this project?

See Specification 01 14 00 Work Restrictions.

What distance must be maintained between construction work and active runways / taxiways?

See Plan Sheet GC001, Phasing Saftey and Operation Note 9.

What will be the method of continuous on site communications between the construction workers and Joint Base ‐ Andrews’s operations?

See Specification 01 17 00 Contractor Self‐Escort Requirements and Specification 01 14 00, Section 1.42.

In Spec Section 33 40 00, please allow Polypropylene Pipe as an allowable pipe material for storm sewer drainage application. Polypropylene pipe is approved in the current version of UFGS and UFC. As well as approved by FAA ‐ AC No: 150/5370‐10G Item D‐701 Pipe for Storm Drains and Culverts.

Negative

This solicitation appears to allow two options for relining or rehabilitating the existing storm drains. Method 1 is Cured‐ In‐Place‐Pipe (CIPP) and this method is generally recognized as a structural rehabilitation method. Method 2 is a spin cast cement mortar, and it is unknown if this is a structural repair method. How is the Owner or General Contractor to determine the use of either repair method? Is there a diameter restriction for either method? Please clarify?

See Q/A Number 3.

Should design for CIPP and CCMPL be based on fully deteriorated host pipe?

Fully deteriorated.

33 05 24; 1.2.1.1 mentions long term creep retention factor of 50% and 1.2.3 mentions 33%, industry std for most manuf is 50% based on 50yr design life. Please clarify which retention factor is required for this specification.

See this Amendment Number 3.

33 05 25; 1.2.4.2 states that hydraulic capacity be at minimum full flow capacity of the original pipe. For CCMPL lining, the recommended Manning’s coefficient for new mortar lining is .017 and existing Manning coefficient for concrete pipe is generally .015, what Manning value should the designer use to calculate the flow capacity for the pipe on this project?

Industry standard Manning's coefficient is acceptable.

33 05 24; Are existing on‐site hydrants or other water sources available for use on this project for inversion and curing CIPP liners?

See Q/A Number 7.

33 05 24; Will the contractor be able to work 24hours around the clock for several consecutive days in order to cure the CIPP liner?

See Q/A Number 5.

33 05 24; Will the contractor be able to release the curing water from the CIPP liner into the sewer after curing and cool down operations?

See Q/A Number 8.

33 05 25; 1.4.1.5 mentions shop wet out. This appears to be copied from the CIPP specification in error. Please confirm.

See this Amendment Number 3.

33 05 25; 1.4.1.6 mentions using ASCE design for Design of Direct Bury Precast Concrete Pipe. Is this the specification for design of CCMPL also?

Correct.

Can the sewer videos be posted online or CDs sent to the plan holder?

See Q/A Number 19.

The solicitation requirements include the offer due date of September 8, the first day of work following the Labor Day weekend. For this reason, we respectfully request your consideration to change the due date to the following Friday, or grant a full one week extension.

Extend bid opening to 10 September 2015 at 1:00 PM EST

1. The solicitation includes a page about Subcontracting Goals for the project, however, the form on Page 20 of 83, does not include any percentages for the subcontracting goals. We respectfully request that USACE provides the percentages required to be compliant with the client’s SB subcontracting goals.

Replace Subcontracting Goals Informational Text in solicitation with the following: SUBCONTRACTING GOALS

Prior to award, the selected large business bidder shall submit an acceptable subcontracting plan within the time limit prescribed by the Contracting Officer, consistent with Section 806b) of Public Law 100‐180, 95‐507 and PL 99‐661.

The following goals are considered reasonable and achievable during the terms of the contract:

50% as a minimum of the planned subcontracting dollars to be placed with small business concerns. (The following are subsets of the small business goal):

As of that portion placed with small business concerns;

17% shall be placed with small disadvantaged business concerns, to include Historically Black Colleges and Universities and Minority Institutes (HBCU/MI);

18% shall be placed with women owned small businesses;

10% shall be placed with HubZone small businesses;

4% shall be placed with Veteran‐Owned small business;

8.5% shall be placed with Service‐Disabled Veteran‐owned small business.

End of Text

NARRATIVE
REQUESTS FOR INFORMATION & GOVERNMENT RESPONSES