ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED DATE OPENEDPAGE OF 04-Aug-15 10-Sep-15 1 OF 1
4. ISSUING OFFICE Name and title of Certifying Official (Type) Department of the Army I CERTIFY that I have opened, read, and Baltimore District, Corps of Engineers recorded on this abstract all offers Signature Date Signed 10 S. Howard Street, Rm 8141 received in response to this solicitation.
Baltimore, Maryland 21203-1715 Contracting Officer: Gary Faykes
5. PROJECT TITLE 9. OFFERS
REPLACE COLLAPSED STORM AIRFIELD DRAINAGE SYSTEM 8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and
A. HIRED LABOR
B. REASONABLE CONTRACT B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) (Without Profit)
6. NUMBER OF AMENDMENTS ISSUED 3 C. REASONABLE CONTRACT C. Amendment Acknowledged C. Amendment Acknowledged (Including Profit)
7A. 7B. 7C. D. E. F. E. F. E. F.
ITEM DESCRIPTION OF OFFERED ITEM EST. UNIT UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED No. QUANTITY PRICE AMOUNT IGE PRICE AMOUNT (1) PRICE AMOUNT (2)
0001 All costs in connection with construction of Phase 2 of the AJXF 11- 1518A Replace Storm Drains on Airfield project, complete as shown on drawings and specified but exclusive of Bid Items 0002 – 0004 below.
--- JOB 19,396,605.77 $19,712,925.00 $10,735,004.00
0002 All costs in connection with Phase 2 removal of unsatisfactory material and replacement with select granular fill complete as shown on drawing and specified.
30 CY 364.32 10,929.60 $200.00 $6,000.00 $130.00 $3,900.00
0003 All costs in connection with Phase 2 area grading complete as shown on drawings and specified. 1200 SY $100.74 120,888.00 $25.00 $30,000.00 $2.50 $3,000.00
0004 All costs in connection with Phase 2 removal, transportation and disposal of ACM Conduit complete as shown on drawings and specified. 100 LF $55.90 5,590.00 $115.00 $11,500.00 $55.00 $5,500.00
0005 All costs in connection with construction of Phase 3 of the AJXF 11- 1518A Replace Storm Drains on Airfield project, complete as shown on drawings and specified but exclusive of Bid Items 0006 – 0010 below.
--- JOB 7,622,995.75 $5,100,000.00 $9,973,651.00
0006 All costs in connection with Phase 3 removal of unsatisfactory material and replacement with select granular fill complete as shown on drawing and specified.
600 CY $142.63 85,578.00 $140.00 $84,000.00 $130.00 $78,000.00
0007 All costs in connection with Phase 3 area grading complete as shown on drawings and specified. 2400 SY $448.76 1,077,024.00 $25.00 $60,000.00 $2.50 $6,000.00
0008 All costs in connection with Phase 3 removal of TCE contaminated soil and replace with select granular fill complete as shown on drawings and specified.
600 CY $191.12 114,672.00 $570.00 $342,000.00 $350.00 $210,000.00
0009 All costs in connection with Phase 3 removal of fuel contaminated soil and replace with select granular fill complete as shown on drawings and specified.
25 CY $304.66 7,616.50 $300.00 $7,500.00 $350.00 $8,750.00
0010 All costs in connection with Phase 3 removal, transportation and disposal of ACM Conduit complete as shown on drawings and specified. 100 LF $55.90 5,590.00 $115.00 $11,500.00 $55.00 $5,500.00
TOTAL BASE BID AMOUNT 28,447,489.62 $25,365,425.00 $21,029,305.00
OPTION BID ITEMS
All costs in connection with construction of Phase 4 of the AJXF 1115- 18A Replace Storm Drains on Airfield project, complete as shown on drawings and specified but exclusive of Bid Items 0012 – 0015 below. --- JOB 13,505,575.63 $8,500,000.00 $15,445,070.00
All costs in connection with providing geotextile fabric for Phase 4 complete as shown on drawings and specified. 425 SY $2.44 1,037.00 $15.00 $6,375.00 $5.00 $2,125.00
All costs in connection with Phase 4 removal of unsatisfactory material and replacement with select granular fill complete as shown on drawing and specified.
3600 CY $167.88 604,368.00 $105.00 $378,000.00 $130.00 $468,000.00
All costs in connection with Phase 4 area grading complete as shown on drawings and specified. 2400 SY $208.45 500,280.00 $20.00 $48,000.00 $2.50 $6,000.00
All costs in connection with Phase 4 removal, transportation and disposal of ACM Conduit complete as shown on drawings and specified. 900 LF $56.12 50,508.00 $88.00 $79,200.00 $55.00 $49,500.00
TOTAL OPTION BID AMOUNT 14,661,768.63 $9,011,575.00 $15,970,695.00
TOTAL BID AMOUNT 43,109,258.25 $34,377,000.00 $37,000,000.00
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 14 Prescribed by GSA-FAR(48 CER)53OPTIONAL FORM 1419 (11-88)
JOINT BASE ANDREWS, MD
1 2 W.M. Schlosser Co, Inc
2400 51st Place Hyattsville, MD 20781
W912DR-13-B-0003
Yes
20% bid bond 20% bid bond
Granite Construction Company 585 West Beach Street Watsonville, CA 95076
Yes