About this file
DRAFT RFP.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912DR-12-R-0012 - Amendment 3.pdf | ||
| W912DR-12-R-0012 - Amendment 2.pdf | ||
| W912DR-12-R-0012 - Amendment 1.pdf | ||
| ICC-B SATOCC Matrix.xlsx | XLSX spreadsheet | |
| W912DR-12-R-0012 SATOCC Div 1 Specs - April 2012.pdf | ||
| Contractor Format for RFIs.xlsx | XLSX spreadsheet | |
| W912DR-12-R-0012 - Solicitation - ICC-B.pdf | ||
| W912DR-12-R-0012 - Attachments in Word.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
This solicitation is for a single aw ard task order construction contract (SATOCC). It w ill be an indefinite delivery indefinite quantity (IDIQ) f irm f ixed priced contract.
This solicitation is subject to the approval of aw ard of a SATOCC greater than $103M. This is an unrestricted acquisition utilizing a tw o-phased best value method.
Phase 1: Qualif ications of Offerors (Bond Surety Letter due w ith Phase 1) Phase 2: Request for Proposal (Bid Bond Due w ith Phase 2)
NAICS: 236220
Size Standard: $33.5M
The period of performance of the contract is f ive years from the date of aw ard.
The maximum capacity for this contract is $499,999,999.99.
The guaranteed minimum is $2,000,000.00
A Top Secret Facility Site Clearance is required for the offeror named in block 14 at the time the offer is due, at the time of aw ard and for the duration of the contract.
Questions regarding this solicitation shall be directed in w riting to Carlen Capenos at carlen.capenos@usace.army.mil.
CARLEN CAPENOS 410-854-0739
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
28-Mar-2012
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________1825 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________8 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________27 Apr 2012 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USACE, BALTIMORE
10 S. HOWARD STREET
BALTIMORE MD 21201
W912DR
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
11:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
410-962-2001FAX:TEL: 410-962-7646 TEL: FAX:
W912DR-12-R-0012 107
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912DR-12-R-0012
Section 00010 - Solicitation Contract Form
DESRIPTION OF PROJECT
The project consists of renovating the existing 39 acre former National Geospatial Agency campus in Bethesda, MD to house the Intelligence Community Campus - Bethesda (ICC-B). The basic scope of the program consists of upgrades to Anti-terrorism / Force Protection (ATFP), “greening” of the campus, renovations of existing buildings, and new construction to tie existing buildings together. The campus consists of six buildings: Abert Hall, Emory Hall, Erskine Hall, Roberdeau Hall, Maury Hall and a Visitor Center. The redevelopment plan has Erskine Hall, Roberdeau Hall, and Maury Hall to remain, and Emory Hall, Abert Hall, and the Visitors Center to be demolished.
A new construction project for a Centrum will connect the remaining buildings. The Centrum will set the architectural theme to the campus. It is desired to design and construct a Central Utility Plant if funds become available. Upon completion of the new construction, the remaining buildings will be renovated and upgraded in later years. The facility will feature several energy and water saving strategies including reducing impervious surfaces, reusing stormwater onsite for gray water and irrigation, and constructing to LEED Silver. Funding will come yearly and individual projects will be issued via task orders. Funding is expected in fiscal years 12 through
16. It is anticipated that task orders will be issued in the $10-80M range and may be one to three a year.
The vision is that this campus would capture the fundamental nature of the Intelligence Community:
• Collaborating within and among the Intelligence Community,
• sustaining military superiority in an era of persistent conflict,
• preventing strategic surprise,
• providing strategic warning,
• operating as one team,
• strengthening core mission capabilities,
• shaping the workforce,
• partnering and innovating to gain advantage
The ICC-B design should support the DNI National Intelligence Strategy, DNI Vision 2015 and the 2012-2017 Defense Intelligence Agency Strategy (links below):
http://www.dni.gov/reports/2009_NIS.pdf http://www.dni.gov/reports/Vision_2015.pdf http://www.dia.mil/about/strategic-plan/2012-2017-DIA-Strategic-Plan.pdf
PRICING REQUIREMENTS
PRICING REQUIREMENTS
No pricing is required in Phase 1. Pricing will be required with the Phase 2 submission. The charts below are for reference for Phase 1 and will need to be filled in in Phase 2.
COEFFICIENT SCHEDULE
Construction Coefficients
Chart A
Pre-Priced Line Items Non-Pre-Priced Line Items
Non-Classified: $0 to $1M
Non-Classified: >$1M
Classified: $0 to $1M
Classified: >$1M
Design Fee Schedule:
Discipline Fully Loaded Hourly Rate ($)
Principal
Senior Project Manager
Project Manager
Sr. Architect
Architect
Sr. Mechanical Engineer
Mechanical Engineer
Sr. Electrical Engineer
Electrical Engineer
Sr. Structural Engineer
Structural Engineer
Sr. Civil Engineer
Civil Engineer
Sr. Sanitary Engineer
Sanitary Engineer
Landscape Architect
Surveyor
2-man Survey Crew
Sr. Environmental Engineer
Environmental Engineer
Certified Industrial Hygienist
Industrial Hygienist
Sr. Fire Protection Engineer
Fire Protection Engineer
Sr. Geotechnical Engineer
Geotechnical Engineer
Sr. Geologist
Geologist
Sr. Scientist
Scientist
Sr. Plumbing Engineer
Plumbing Engineer
Sr. Power Engineer (High Voltage)
Power Engineer (High Voltage)
Sr. Estimator
Estimator
Quality Control Specialist
Sr. HVAC Controls Engineer
HVAC Controls Engineer
Master Planner
Sr. Scheduler
Scheduler
CADD Operator
Sr. Field Engineering Tech (Test)
Field Engineering Tech (Test)
Laboratory Technician
IT Specialist
Telecommunications Specialist
Telecommunications Engineer
Network Engineer (LAN, WAN)
Communications Systems Engineer
Security Engineer
Security Specialist
Safety Engineer
Certified LEED Professional (LEED Coord.)
Interior Designer
Systems Furniture Designer
Specifications Writer
Construction Manager
Construction Inspector
Illustrator/Draftsperson
Computer Scientist/Operator
Technician (General)
Cost Accountant
Budget Analyst
Administrative Assistant
Secretary
Reproduction 30x42
Reproduction 24x36
Reproduction 8.5x11 –B/W
Reproduction 8.5x11 - Color
Reproduction 11x17 – B/W
Reproduction 11x17 - Color
Should a task order be a design-build project, the Construction and Design Fees will be negotiated as separate costs and added together for the final price for each task order. No further profit or overhead is added to either element.
These costs need to be included with the coefficient and within the loaded rates for the design disciplines.
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 499,999,999.99 Dollars, U.S.
ICC-B SATOCC
FFP
Single Award Task Order Construction Contract.
FOB: Destination
MAX
NET AMT
CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE
The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.
CLIN
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
$2,000.00
$499,999,999.99
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 5 yrs. ADC 499,999,999.99 REAL PROPERTY SERVICES FIELD
OFFICE
JOHN N CONNOLLY
300 SENTINEL DRIVE
SUITE 400
ANNAPOLIS JUNCTION MD 20701
410-854-0716 FOB: Destination
Section 00100 - Bidding Schedule/Instructions to Bidders
INSTRUCTIONS TO OFFERORS
SECTION 00100
PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS – PHASE 1
1. OVERVIEW.
1.1 This Request for Proposal (RFP) solicits for a single award task order construction contract (SATOCC) for the upgrade and renovation of the Intelligence Community Campus – Bethesda (ICC-B) located in Bethesda, MD. The resultant contract will be a single Firm-Fixed Priced Indefinite Delivery, Indefinite Quantity contract.
1.2 The purpose of the Source Selection Plan is to establish a uniform evaluation procedure for the proposals by the Source Selection Evaluation Board (SSEB) and the development of the Best Value Decision by the Source Selection Authority (SSA) using the Trade-Off Process (See Federal Acquisition Regulation 15.101-1). In as much as the proposal shall describe the capability of the Offeror to perform the resulting contract, the proposal shall be specific and complete in every detail as well as be prepared simply and economically, providing a straightforward and concise description of capabilities to satisfactorily perform the contract.
1.3 For the purposes of this solicitation, the Government will utilize the Two Phase Design-Build Process. In Phase 1 of the 2 Phase Design-Build selection procedure, interested Offerors submit performance capability proposals for review and consideration by the Government.
1.4 The Government will evaluate the performance capability proposals in accordance with the criteria described herein and will select up to three of the highest rated Offerors to participate in Phase Two.
1.5 In Phase Two of this process, the Government will evaluate technical approach and price factors.
1.6 Only those Offerors who receive a written notification from the Procuring Contracting Officer that their firm has been selected to participate in Phase Two of this solicitation are invited to submit a Phase Two proposal. Those Offerors selected for Phase Two will be provided the technical requirements package for the project.
1.7 Offers that are not selected to participate in Phase 2 will be notified and may request a pre-award debrief.
2. GENERAL INSTRUCTIONS
2.1 Firms formally organized as design-build entities, design firms and construction contractors that have associated specifically for this project, consortia of firms, or any other interested parties may submit proposals. A design firm or construction contractor may offer more than one proposal by entering into more than one association.
Associations may be joint ventures or include key team subcontractors. Any legally organized Offeror may submit a proposal.
2.2 Contractor Team Arrangements. Contractor Team Arrangements are considered an arrangement in which (1) two or more companies form a partnership or joint venture to act as a potential prime contractor; or (2) a potential prime contractor agrees with one or more other companies to have them act as its subcontractors under a specified Government contract or acquisition program. In accordance with FAR Subpart 9.6, the Government will recognize the integrity and validity of contractor team arrangements; provided, the arrangements are identified and company relationships are fully disclosed in the offer. The Offeror shall identify the major or critical aspects of the requirement to be performed by those identified in the Contractor Team Arrangement.
2.3 If applicable, the Offeror shall submit evidence from the Offeror’s SBA Servicing Agency that the Offeror has notified and discussed the proposed joint venture for this project with the appropriate SBA personnel.
2.4 Information submitted about any company other than the Offeror, whether a predecessor company, affiliated company, subsidiary (including wholly owned subsidiaries), subcontractors that will perform major or critical aspects of this requirement, or other associated business, will not be evaluated for any factor unless the proposal contains a detailed narrative explaining why this submitted information is relevant to this acquisition. The Government will consider the adequacy of this explanation in deciding the relevance and weight of the information to this procurement. Information about subcontractors may not be given much weight unless the proposal contains evidence that the subcontractor is committed to perform the work. If information about a subcontractor is properly submitted and given weight during the evaluation, the expectation is that this subcontractor will perform this work.
Before substituting another subcontractor for this work, the Government must consent.
2.5 Offerors shall submit their proposal to the address shown in Block 7 of Standard Form 1442.
2.6 Proposals are due no later than the time and date specified in Block 13 of Standard Form 1442.
3. GENERAL PROPOSAL FORMAT:
3.1 Title Page. Include the title of the solicitation, solicitation number, Offeror name, and date of the submittal.
3.2 Table of Contents. Each binder of the proposal shall contain a detailed table of contents. The complete table of contents shall be included in each binder. Any materials submitted but not required by this solicitation (such as company brochures) shall be relegated to appendices.
3.3 Printed Matter Submissions. Written material shall be on 8 ½ x 11 inch paper printed in no less than a 10 point font. Page limitations, where specified in the RFP, shall be considered a maximum. Pages in excess of any specified limitation shall not be evaluated. A single 8 ½ x 11 inch sheet with written material on one side only shall constitute one page (for organization charts or schedules, a folded 11” x 17” format may be used).
However, if both sides of the sheet bear written material then this single sheet shall be counted as two pages.
3.4 Binders. Proposals shall be submitted in tabbed, three ring binders.
3.5 Number of Copies. Offerors shall submit the following:
Binder 1: an original and one copy Binder 2: an original and two copy Binder 3: an original and eight copies
3.6 Proposals shall be marked:
Date of Closing: _________________
Time of Closing: 11 a.m.
Solicitation RFP: W912DR-12-R-0012
3.7 Phase 1 proposal shall be organized and tabbed as follows:
Binder 1: Solicitation Information
TAB A: Standard Form 1442, completed and signed by authorized individual(s) of the Offeror. Offers submitted in the name of a Joint Venture must be signed in accordance with the terms and conditions specified in the joint venture agreement as evidenced in the proposal.
TAB B: FACTOR 1 Bond Surety Letter
TAB C: Letter providing Cage Code to verify Top Secret Facility Site Clearance or letter showing proof of Top Secret Facility Site Clearance.
TAB D: Certificate of Corporate Principal/Authority.
Sample: CERTIFICATE OF CORPORATE AUTHORITY
(This Certificate shall be submitted as part of the proposal or signed contract if the offeror is a corporation.)
CERTIFICATE
I, _______________________________, certify that I am the ______________________________ of the corporation named as bidder/offeror therein, that _________________________________, who signed this bid/proposal on behalf of the bidder/offeror, was then _______________________ of said corporation; that said bid/proposal was duly signed for and in behalf of said corporation by authority of its governing body, and is within the scope of its corporate powers.
By: ___________________________________(Corporate Seal)
(Signature)
(Typed Name of Corporation)
Binder 2: Small Business Proposal
TAB E: FACTOR 2 Small Business Participation Plan
TAB F: FACTOR 3 Past Performance of the Utilization of Small Business
Binder 3: Technical Proposal
TAB G: Teaming Agreement(s), if applicable. See paragraph 2.2. Note to 8(a)—SBA must approve a joint venture agreement prior to the award of an 8(a) contract on behalf of the joint venture. See paragraph 2.3.
TAB H: FACTOR 4 Past Performance of Task Order Construction Contracts
TAB I: FACTOR 5 Past Performance of Construction Contracts
TAB J: FACTOR 6 Technical Approach
TAB K: FACTOR 7 Team Designers
The total number of pages required is at the discretion of the offeror. It is anticipated that no more than 100 pages should be necessary.
4. EVALUATION RATINGS – PHASE 1
4.1 Proposal Ratings: Factors. Factor 1 will be evaluated as acceptable or unacceptable. Factors 2, 6 and 7 will be adjectivally rated. Factors 3, 4 and 5 will be rated in terms of a performance confidence rating with a separate rating for relevancy. Offerors submitting proposals for this project should limit submissions to data essential for the evaluation of proposals.
FACTOR 1 Bond Surety Letter
FACTOR 2 Small Business Participation Plan
FACTOR 3 Past Performance of the Utilization of Small Business
FACTOR 4 Past Performance of Task Order Construction Contracts
FACTOR 5 Past Performance of Construction Contracts
FACTOR 6 Technical Approach
FACTOR 7 Team Designers
A rating of unacceptable for Factor 1 will render the Phase 1 proposal unacceptable and the offer will not be considered further for Phase 2.
See paragraph 6 below for a discussion of the evaluation criteria applicable to these factors.
4.2 Technical Rating Definitions. The following combined technical/risk rating definitions will be utilized in the evaluation of Factors 2, 6 and 7.
COLOR RATING DESCRIPTION
Blue Outstanding Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses. Risk of unsuccessful performance is very low.
Purple Good Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.
Red Unacceptable Proposal does not meet requirements and contains one or more deficiencies. Proposal is unawardable.
4.3 Performance Risk Rating Definitions. Factors 3, 4 and 5 will be evaluated using the following Performance Confidence Assessments:
RATING DESCRIPTION
Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence No recent/relevant performance record is available or the offeror’s performance (Neutral) record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
Past Performance shall also be rated in accordance with the relevancy of the past performance. The following will be used for Factors 3, 4 and 5:
RATING DESCRIPTION
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Present/past performance effort involved some of the scope and magnitude of effort and relevant complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
5. PHASE 1 SUBMISSION REQUIREMENTS
For purposes of this RFP, an “Offeror” may include a group of two or more entities that have formed a “contractor team arrangement,” as that term is defined in the Federal Acquisition Regulation, Section 9.601. In the case of entities that have formed a contractor team arrangement, the experience and performance history of any member of the team, whether or not gained while working with the other member(s) of the currently-proposed contractor team arrangement, will be considered as a part of the evaluation of the Offeror’s proposal.
In the case of contractor team arrangements involving a prime contractor and subcontractor(s), where the prime contractor submits the proposal in response to this RFP, the prime contractor must have completed at least 50% of the total number of projects submitted for Factors 4 and 5 for consideration in response to the experience and past performance requirements of this RFP.
An Offeror that relies upon the performance history of a member or members of a proposed contractor team arrangement will be expected to maintain that arrangement during performance of any contract awarded to that Offeror under this RFP. As a part of their proposal, the Offeror must provide a contractor team agreement signed by all parties, identifying the legal name(s) of all entities and describing the nature of each entity’s relationship (teaming/partnering, joint venture, mentor/protégé, etc.) and their role on this project. This documentation shall be provided in Binder 3 of the Offeror's proposal.
In Phase 1, Factors 4, 5, 6 and 7 are of equal importance to one another. Factors 2 and 3 are of equal importance to one another. Collectively, Factors 4, 5, 6, and 7 are of greater importance than Factors 2 and 3.
Factor 1 must receive a rating of acceptable to be considered for Phase 2. An unacceptable rating in Factor 1 will render the entire proposal unacceptable and the proposal will be removed from further consideration.
5.1 FACTOR 1: BOND SURETY LETTER: Offeror must provide a letter or other documentation from a surety appearing on the Department of Treasury Circular 570 (list of approved sureties) stating that the offeror is able to provide a bid bond for Phase 2 and obtain performance and payment bonds should they win the contract. The value of those bonds in Phase 2 will be $499M.
5.2 FACTOR 2: SMALL BUSINESS PARTICIPATION PLAN (required for all Offerors): All offerors (both large and small businesses) will be evaluated on the level of proposed participation of small businesses in the performance of acquisition (as small business prime offerors or small business subcontractors) relative to the objectives and goals established herein.
This Participation Plan shall address their corporate approach and methodology for acquiring, soliciting and using small businesses in the performance of this contract. All plans shall address the Offeror's commitment to providing subcontracting opportunities, as well as evidence of planned and /or continued outreach efforts to encourage and use small businesses. This Participation Plan may include all subcontracting tiers.
The government will evaluate:
a. The extent to which such firms, as defined in FAR Part 19, are specifically identified in proposals;
b. The extent of commitment to use such firms (and enforceable commitments will be weighted more heavily than non-enforceable ones);
c. Identification of the complexity and variety of the work small firms are to perform;
d. The extent of participation of small business prime offerors and small business subcontractors in terms of the percentage of the value of the total acquisition; or alternatively may consider the percentage of ‘planned subcontracting’ dollars.
e. The extent to which the offeror meets or exceeds the goals. These goals are a percentage of the total contract value. The goals for this procurement are:
Small Business: 35% Small Disadvantaged Businesses to include 8(a): 12% Woman-Owned Small Business: 14%
Historically Underutilized Business Zone (HUBZone) SB: 5% Veteran Owned Small Business: 10% Service Disabled Veteran Owned Small Business: 7.5%
(Note, a participation plan that reflects a percentage of the contract value for Woman-Owned Small Business would also count towards the overall Small Business Goal; and percentages for Serviced Disabled Veterans also count towards Veteran Owned Small Businesses).
f. Alternate when using planned subcontracted dollars: The extent to which the offeror meets or exceeds the goals: Goals for this procurement are:
Small Business: 50% Small Disadvantaged Businesses to include 8(a): 17% Woman-Owned Small Business: 18%
Historically Underutilized Business Zone (HUBZone) SB: 10% Veteran Owned Small Business: 7.5% Service Disabled Veteran Owned Small Business: 5%
The Participation Plan shall demonstrate commitment to all federally designated categories of small business: Small Businesses (SBs), Veteran-Owned Small Businesses (VOSBs), Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) HUBZone Small Businesses (HUB), Small Disadvantaged Businesses (SDBs), Woman-Owned Small Businesses (WOSBs), and when applicable, Historically Black Colleges/ Universities/Minority Institutions (HBCU/MIs). The plan shall identify all categories for participation as part of the Offeror's team. This shall include a description of the type of work, product or service anticipated to be supplied via a small business concerns. Identification of the names of specific subcontractors is not required for the small business utilization evaluation; however, providing specific subcontractors is desirable and may result in a better evaluation.
This Small Business Participation Plan will be an evaluation factor. A separate Subcontracting Plan meeting the requirements of FAR 19.7 shall be required by the apparently successful Offeror. If the apparently successful Offeror fails to negotiate a subcontracting plan acceptable to the contracting officer within the time limit prescribed by the contracting officer, the Offeror will be ineligible for award.
5.3 FACTOR 3: PAST PERFORMANCE IN THE UTILIZATION OF SMALL BUSINESS
The Offeror shall provide a description of the Offeror’s demonstrated small business achievements in all federally designated small business categories on up to five completed or substantially completed (75% of construction) projects during the past seven years. For each project, Offerors should provide a brief project description, dollar magnitude of the project, location, and the percentage of total work that was subcontracted to small businesses at a first tier and for all tiers, identifying specific SB categories used on each project.
For this submission, large businesses may submit information pertaining to their goals and actual accomplishments under approved Small Business Subcontracting Plans. Submissions of Individual Subcontracting Reports (ISRs) formerly known as SF 294s and Summary Subcontracting Reports (SSRs) are highly encouraged.
5.4 FACTOR 4: PAST PERFORMANCE FOR TASK ORDER CONSTRUCTION CONTRACTS:
Projects submitted must demonstrate past performance of task order based contracts with a period of performance within five years of the original date of issuance of this solicitation. The past performance shall be demonstrated on the overall contract and not the individual task orders. The Offeror shall submit past performance information on a minimum of three, but not more than five, task order construction contracts. At least two of the submitted projects must document the prime contractor’s past performance. If the prime contractor is a Joint Venture then past performance may come from either party of the Joint Venture. The remaining projects may come from other members of the contractor team arrangement, as defined above. All experiences should be submitted from construction contractors and not Architecture-Engineer contracts.
The information regarding the task order construction contracts that is required to be supplied is identified on the form entitled “CONTRACTOR’S TASK ORDER BASE CONTRACTS” (Attachment A) and shall include: the contract number, the contracting agency, contact information for each contract, overall capacity of the contract.
Additionally, for each contract provide a matrix that includes: all task orders issued, the description of all projects, dollar value of the initial task order, dollar value of completed task order, period of performance of each task order (or date) and actual period of performance completion (or date). Offerors may use the form entitled “TASK ORDER MATRIX” (Attachment B) if desired for the task order matrix. These formats are highly encouraged.
The offeror shall describe their past use of and experience with using RS Means (or similar) pricing methods for task orders. The offeror may also describe alternative pricing methods in IDIQ type construction contracts. The purpose of this inclusion is to give the Government information on the offerors' familiarity with Means (or similar) based pricing for assurance that the offeror understands how to properly bid pre-priced and non-pre-priced line items.
Similar contracts may include those that include task orders issued for construction projects in a variety of sizes, a variety of construction disciplines, varying degrees of technical complexity and both design-build type task orders as well as design-bid-build task orders. The Offeror may submit other types of projects, but must explain the relevancy of those projects to the project that is being solicited in this solicitation.
The task order matrix should demonstrate a variety of construction types and methods to assist in evaluating the offeror’s ability and approach to perform work, including demonstrating experience with:
Mix of new construction and renovation projects on same site
Interior Renovations Access Roads Anti Terrorism Force Protection (AT/FP) Systems;
Sensitive Compartmented Information Facilities (SCIF);
Structural Repairs and/or Construction;
Foundation Systems Repair, Construction, and/or Replacement Mechanical, Electrical and Plumbing Systems Repair, Construction and/or Replacement;
Fire Protection and Alarm Systems Repair, Construction and/or Replacement;
Utility Infrastructure and Systems Repair, Construction and/or Replacement;
The offeror shall provide the Offeror’s assigned performance evaluations for projects that demonstrate the offeror’s performance on recent and relative Task Order Construction Contracts.
The offeror shall provide formal performance evaluation. Formal performance evaluations are those that are similar to the Department of Defense Performance Evaluation (Construction) Form DD2626.
In addition to formal evaluations or if a formal evaluation is unavailable, the Offeror shall obtain the information using the Past Performance Questionnaire included. The Past Performance Questionnaire included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 4, Past Performance of Task Order Construction Contracts. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment C), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Carlen Capenos via email at Carlen.capenos@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. This means that offerors may use PPQs filled out previously without having them reaccomplished for this specific solicitation but they must be included in the proposal.
Also include performance recognition documents received within the last seven years such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition.
In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
5.5 FACTOR 5: PAST PERFORMANCE OF CONSTRUCTION CONTRACTS: Projects submitted must demonstrate past performance by the physical and successful completion of similar projects within five years of the original date of issuance of this RFP. For ongoing projects, 100% of the design and at least 75% of the major construction milestones must be completed at the time of proposal submission. The Offeror shall submit past performance information on a minimum of three completed similar projects but not more than five. At least three of the submitted projects must document the prime contractor’s past performance. The remaining projects may come from other members of the contractor team arrangement, as defined above. If the prime contractor is a Joint
Venture then past performance may come from either party of the Joint Venture. The information regarding the projects that is required to be supplied is identified on the form entitled “CONTRACTOR PAST EXPERIENCE” (Attachment C).
Similar projects should demonstrate as many of the following project types (either individually or in combination thereof) as possible:
Design-Build and/or Design-Bid Build Projects in excess of $50M Experience with Campus-like environments that included multiple buildings Experiences with construction phasing with locations that had on-going missions Experience with consolidating utilities and centralizing distribution to promote efficiency Experience with Security Systems;
Experience with Sustainable Buildings Anti Terrorism Force Protection (AT/FP) Systems;
Electro Magnetic Radiation (EMR) shielding;
Sensitive Compartmented Information Facilities (SCIF);
Secure Industrial Programmable Logic Control (PLC) Systems Structural Repairs and/or Construction;
Foundation Systems Repair, Construction, and/or Replacement Mechanical, Electrical and Plumbing Systems Repair, Construction and/or Replacement;
Fire Protection and Alarm Systems Repair, Construction and/or Replacement;
Utility Infrastructure and Systems Repair, Construction and/or Replacement;
The offer shall provide the Offeror’s assigned performance evaluations for the submitted projects that demonstrate the Offeror’s performance on recent and relative Design-Build projects. The Offeror must provide formal performance evaluation. Formal performance evaluations are those that are similar to the Department of Defense Performance Evaluation (Construction) Form DD2626.
In addition to formal evaluations or if a formal evaluation is unavailable, the Offeror shall obtain the information using the Past Performance Questionnaire included. The Past Performance Questionnaire included in the solicitation is provided for the Offeror or its team members to submit to the client for each project the Offeror includes in its proposal for Factor 5, Past Performance of Construction Contract. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ (Attachment C), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Carlen Capenos via email at Carlen.capenos@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. This means that offerors may use PPQs filled out previously without having them reaccomplished for this specific solicitation but they must be included in the proposal.
Also include performance recognition documents received within the last seven such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition.
In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
5.6 FACTOR 6: TECHNICAL APPROACH: To facilitate evaluation , the offeror should organize the submitted material sequentially under tabs. Submit this information in the form of narratives and an organization chart.
5.6.1 Contract Team Organization: Describe in narrative form, how the contract team shall be structured. Describe the principal firms involved and their responsibilities. Identify the team members. All disciplines shall be led by an experienced professional registered in the discipline (if professional registration is available). The Offeror shall submit documentation as to the availability of Key Personnel that indicates each individual’s current assignment and the Offeror’s plan to ensure that the named personnel will be used on this contract; however, if the named person isn’t available upon award, a person with the same or better qualifications may be substituted upon approval by the Government.
The offeror shall discuss their approach to manage multiple projects and subcontractors simultaneously. Identify the construction portion the Offeror intends to self perform and the items to be subcontracted. Similarly, the Offeror shall identify the areas they intend to design through consultants and list those design consultants.
During the life of this contract, the contractor shall maintain a full-time staff on site. This staff, at a minimum, shall include the following: Program Manager, Project Manager, CADD Operator, two Construction Superintendents, Full-time On-Site Quality Control Manager and a Full-time On-Site Safety Manager. Resumes shall be provided for each of these positions.
5.6.2 Design Organization: This contract may involve a wide variety of construction projects, many of which will be executed in a Design-Build method. This section shall discuss how design will be managed and executed throughout the life of this contract. Describe the flow of a typical design package submittal, from design team, through General Contractor to the Government. In addition, describe how the design review process will work and the interaction required for all of the parties involved. Multiple design firms may be necessary for the entire contract as the task orders may vary widely. The qualifications of the design and construction personnel shall be provided. The narrative shall state why your design team(s) is uniquely qualified to undertake this contract, its approach to sustainable design and process of working with the customer(s) during the design phase. The narrative shall include examples of completed design projects that are related to anticipated project types listed in the Project Description and/or Factor 5.
5.6.3 Construction Organization: This contract may involve a wide variety of construction projects. The Offeror shall discuss its construction organizational structure to manage multiple task orders with concurrent periods of performance. This section shall discuss how construction will be executed throughout the life of this contract. The narrative shall state why your team is uniquely qualified to undertake this contract, its approach to construction and working with the customer(s) during construction.
5.6.4 Quality Management Control System: The Offeror shall describe how they intend to manage quality throughout the contract. Discuss quality management methods proposed throughout the design and construction process.
5.6.5 Safety. The Offeror shall discuss how they intend to manage and execute their Safety program for the contract and each task order.
5.6.6 Organization Chart: The proposed organizational chart shall identify the members or entities of the organization and show the lines of authority and communication of all members of the design and construction entities.
5.6.7 Schedules: The offeror must describe how it will manage multiple task orders with concurrent periods of performance.
The offeror must discuss its scheduling capabilities and procedures to be used for this contract, which must include schedule updates, incorporating modifications into the schedule, and other steps to be taken to maintain the individual task order schedules.
The offeror shall describe previous experience with scheduling campus projects or projects with multiple schedules and/or projects located in close if not overlapping proximities.
5.6.8 Top Secret Clearances of Key Personnel: The offeror shall provide the names of the Key Personnel that posses a current Top Secret Clearance. At a minimum, the following positions will be required to possess a Top Secret Clearance throughout the duration of the contract. For construction: Company Principles, Program Manager, Project Manager(s), Construction Superintendents, Quality Control Manager, Safety Manager. For design (for design-build projects): Senior Architect, Senior Civil Engineer, Geotechnical Engineer, Senior Mechanical Engineer, Senior Electrical Engineer, Senior Structural Engineer and Security Engineer. This list shall be validated and provided on an annual basis to the Contracting Officer.
5.7 FACTOR 7: DESIGN TEAM: This SATOCC may issue both design-build task orders as well as pure construction task orders. One design-build project will be the design and construction of a Centrum building that ties together the three major buildings of the campus. The Centrum will set the architectural theme to the campus.
Other design-build task orders may include renovation of interior spaces, upgrades to current infrastructure and ATFP upgrades. It is desired to design and construct a Central Utility Plant if funds become available. In order to assess the team’s ability to handle a variety of design-build task orders, offerors may submit up to three Architect – Engineer (AE) firms as team members and their relative experience with design-build projects. Projects should demonstrate the AE’s Designer of Record (DOR) experience. Firms submitted under this factor shall include firms that the offeror intends to use throughout the life of the contract. The offeror shall submit three projects from each AE firm presented. Projects should demonstrate the AE firm’s experience on design only and/or design-build projects. For ongoing projects, 100% of the design and at least 50% of the major construction milestones must be completed at the time of proposal submission. For design only projects, 100% of design must be complete. All projects must have been completed within seven years prior to the date of this RFP.
Relevant projects include design-build projects with a minimum completion value of $25M or design only projects with a minimum value of $5M. The information regarding the projects that is required to be supplied is identified on the form entitled “CONTRACTOR PROJECTS” (Attachment C)
6. EVALUATION CRITERIA
6.1 FACTOR 1: BOND SURETY LETTER: This factor will be rated as acceptable or unacceptable.
6.2 FACTOR 2: SMALL BUSINESS PARTICIPATION PLAN (required for all offerors): The Government will evaluate the Small Business Participation Plans provided. Those plans containing greater detail and specificity will be given greater credit than general statements and commitments.
6.3 FACTOR 3: PAST PEFORMANCE IN THE UTILIZATION OF SMALL BUSINESS (required only for large businesses): Small Businesses will receive a rating of Neutral. This neither counts for or against the offeror.
Past performance will be rated in terms of how likely there is a performance/confidence risk to the Government; that is, high confidence performance ratings will be taken as indicators of a low risk that the Offeror will successfully perform the work. The more relevant a proposed project is the more weight it will be given. If an Offeror has no record of relevant past performance, or if information on the Offeror’s past performance is not available, the Offeror must state that fact. That Offeror will be rated as neutral.
6.4 FACTOR 4: PAST PERFORMANCE IN TASK ORDER…