Industry Day Webinar Slides 20260908_FINAL.pdf
PDF 1 MB Posted
- Attached to
- WAFB/B-21 Project Update to Industry
- Solicitation number
- W912DQSSWAFB
About this file
This document is a webinar presentation from USACE Kansas City District regarding federal military construction contract opportunities at Whiteman Air Force Base for the B-21 program transition.
USACE is conducting approximately 30 military construction (MILCON) and Facility Sustainment, Restoration and Modernization (FSRM) projects totaling approximately $900 million through fiscal year 2032. All projects exceeding $7.5 million will utilize Other Transaction Authority (OTA) delivery methods, specifically Progressive Design Build (PDB) with OT or Construction Manager at Risk (CMAR) with OT. These non-FAR-based procurements use Qualification Based Selection rather than Trade-Off or Lowest Price Technically Acceptable methods, and set-asides do not apply. The OTA selection process consists of a Request for White Paper (10–12 pages) with approximately three finalists advancing to interactive Pitch Presentations, followed by negotiation of a Phase 1 agreement for design and preconstruction services with an option to execute Phase 2 for construction if pricing is determined fair and reasonable.
Specific active projects include FY26 awards (Challenger Dorm, B-21 Weapons Release System Storage, B-21 Radio Frequency Hangar); FY27 B-21 Weapons Load Trainer ($55–70 million, 900 calendar days, CMAR/OT); FY27–FY28 B-21 Field Training Detachment and Flight Simulator ($130–150 million, CMAR/OT); FY27 FSRM projects including dock repairs ($18–24 million), sewer replacement ($19–22 million), and maintenance facility repair ($8–12 million); FY28–FY30 Environmental Protection Shelters ($75–100 million per project, 660 calendar days, PDB/OT); and FY29 Low Observable Facility ($145–165 million, 1,095 calendar days, CMAR/OT). Most projects require secure areas constructed to ICD 705 standards and coordination within Construction Free Zones. Security requirements include U.S. citizenship, no criminal record, and state-issued REAL-ID. Contracting POCs are Angelique Dilmore and Stephanie Kretzer at USACE Kansas City District.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Whiteman Air Force Base Market Intelligence Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WHITEMAN AIR FORCE BASE USACE INDUSTRY
WEBINAR
08 SEPTEMBER 2026
Presented by:
Michael France, Special Programs/Projects Section Chief, Contracting
AGENDA
• Procurement Integrity
• Other Transaction Authority (OTA)
• Project Overviews:
o FY26 Whiteman Projects o FY27 B-21 Weapons Load Trainer (WLT) o FY27 B-21 Field Training Detachment (FTD) & FY28 B-21 Flight Simulator o FY27 FSRM Projects o FY28 & FY30 B-21 Environmental Protection Shelters (EPS) o FY29 B-21 Low Observable (LO) Facility o Remaining B-21 Program
• Industry Questions and Feedback
• Closing Comments and Questions
PROCUREMENT INTEGRITY
Procurement Integrity is maintained throughout the acquisition, including these early engagements. We protect correspondence and information that you decide to share with USACE.
We anticipate information exchanges to continue throughout the various acquisitions. Under the
Procurement Integrity Act, exchanges become formal when we move into the solicitation phase.
USACE is in listening mode. We need your help and feedback to develop meaningful Requests for
White Papers. Our Project Delivery Team will use your shared knowledge and information to help us with acquisition planning.
If you share proprietary or confidential information with us, please identify it so we can take steps to appropriately manage and protect the information.
To help us manage and keep your information confidential, I ask that you only contact the USACE
POC’s: angelique.m.dilmore @usace.army.mil and stephanie.r.kretzer@usace.army.mil
Please do not contact Whiteman AFB or USACE PMs for information.
OTHER TRANSACTION AUTHORITY (OTA)
10. U.S.C. 2808a has recently been updated to allow its use for military construction.
With this new authority, the Air Force has made a decision that ALL Air Force military construction will use OT delivery methods.
OTA’s are not FAR based and do not follow any of the FAR procedures. OT’s are based on Qualification
Based Selections and not Trade-Off or LPTA. In OT’s, set-asides do not apply.
USACE Kansas City is currently focusing on two OT delivery methods:
Progressive Design Build (PDB) w/ OT – This method seeks a Design-Builder to design and construct a project
Construction Manager at Risk (CMAR) w/ OT – This method seeks a Builder to provide preconstruction services and construct the project. With this method, the Government has a separate contract for a
Designer of Record
Both delivery methods follow the same process:
Step 1 will be a Request for White Paper. This requires Design-Builders or Builders to submit a 10–12-page white paper outlining their capabilities and generally why they are the best fit for this project.
The White Papers are evaluated for the most qualified. Generally, a target of 3 are selected to move onto Step 2.
Step 2 is a Pitch Presentation: This presentation is interactive with the Government and allows the firms to better describe their processes, innovative ideas, and demonstrate their collaborative capabilities.
The Pitch Presentations are evaluated, and a single entity is selected as the Most Highly Qualified for the project and who the Government determines will collaborate the best for that particular project.
After the final selection, the Government will enter into negotiations with the selected firm to establish a
Phase 1 agreement for design and preconstruction services or preconstruction services. During this period, the Government and the selected firm will collaborate and negotiate the pricing for construction through open book estimating.
At the conclusion of the design and preconstructions services, if a fair and reasonable price as agreed to, the agreement will be modified to include Phase 2, Construction.
If a fair and reasonable price cannot be agreed to, an “Off Ramp” of the agreement can be executed and the Government can move out with other options.
WHITEMAN & B-21 PROGRAM
FOR OFFICIAL USE ONLY
Whiteman Transitions from B-2 to B-21
Overview
• ~ 30 Projects o Mixture of MILCON
& FSRM projects
▪ Whiteman Civil Engineering plans on executing some of the smaller FSRM projects
▪ USACE will partner to ensure consistent program execution
• ~ $900M
• Projects anticipated through FY32
Execution Strategy
• All projects over $7.5M will use Other Transaction Authority (OTA) with various delivery methods
• Most projects include Secure Areas to be constructed/renovated to ICD 705 standards
• Using lessons learned and consistency throughout B-21 Program across 3 MOBs
WHITEMAN SECURITY
FOR OFFICIAL USE ONLY
Requirements:
• Must be a United States Citizen
• No Criminal Record
• Must have a state issued REAL-ID card
FY26 WHITEMAN PROJECTS
FOR OFFICIAL USE ONLY
The following projects all have submitted proposals that have been evaluated. Anticipating construction awards in Q4FY26 and Q1FY27.
Challenger Dorm
B-21 Radio Frequency (RF) HangarB-21 Weapons Release System Storage (WRSS)
FY27 B-21 WEAPONS LOAD TRAINER (WLT)
FOR OFFICIAL USE ONLY
Construct a new facility that features a secure area, administrative spaces, and classroom sized for eight people. The load trainer area will require proper air circulation and fume ventilation for the various diesel-powered pieces of equipment used within the facility.
The WLT facility sits inside the entrance of the Construction Free Zone (CFZ) and will require coordination with other contractors to not hinder access to the various project sites.
Will be utilizing CMAR w/ OT delivery method.
Magnitude: $55,000,000 to $70,000,000
PoP: 900 Calendar Days
Qualifications Based Selection: 1st QTR FY27
Award OT Construction Agreement: 4th QTR FY27
11FY27 B-21 FIELD TRAINING DETACHMENT (FTD)
FY28 B-21 FLIGHT SIMULATOR
FOR OFFICIAL USE ONLY
FTD: Construct a new facility that can accommodate 59 full-time personnel with a peak student load of 101. Specialized spaces secured areas for server rooms, cockpit part task trainers, egress trainer, engine part task trainers, landing gear trainers, avionics training, aircraft engine and weapons system training spaces.
SIM: Construct a new facility to house three flight simulators, two cockpit procedure trainers, and other associated training related activities.
Will be utilizing CMAR w/ OT delivery method.
Magnitude: $130,000,000 to $150,000,000
PoP: FTD - 900 Calendar Days / SIM - 730 Calendar Days
Qualifications Based Selection: 1st QTR FY27
Award OT Construction Agreement: 4th QTR FY27
Close proximity site constraint
FY27 WHITEMAN FSRM
FOR OFFICIAL USE ONLY
Repair Critical Building Components
Docks 1-6
Scope: Work encompasses full roof replacement, structural roof repairs, permanent fall protection, and hangar door operator upgrades; a complete
HVAC overhaul and plumbing fixture replacement; and electrical and life-safety modernization including branch distribution, grounding/LPS, interior lighting, and full fire alarm/detection system replacement.
Acquisition Strategy: PDB w/OT
Magnitude: $18,000,000 to $24,000,000
Replace Sewer Mains & Manholes
Scope: Work to include approximately eighteen thousand and eighty-five linear feet (18,805 L.F.) of eight-inch (8”) and ten-inch (10”), vitrified clay pipe (VCP) sewer main, including the replacement of eighty-five (88) brick and mortar manholes. Replacement piping shall be
DR-26 PVC, with the replacement manholes being of pre-cast concrete.
Acquisition Strategy: PDB w/ OT
Magnitude: $19,000,000 to $22,000,000
Repair Integrated Maintenance
Facility, BLDG 4055
Scope: Repair and/or upgrade the
68,941 square foot (SF) Integrated
Maintenance Facility (IMF) for the 509th
Munitions Squadron (MUNS). Work will include comprehensive repair and upgrade of facility systems including civil, building envelope, interior construction, HVAC, plumbing, electrical, and fire protection.
Acquisition Strategy: DBB
Magnitude: $8,000,000 to $12,000,000
13FY28 & FY30 B-21 ENVIRONMENTAL PROTECTION
SHELTERS (EPS)
FOR OFFICIAL USE ONLY
Construct four (4) Environmental Protection Shelters on the main apron at Whiteman AFB. Work will include demolition of existing pavements, routing of new electrical service, and construction of four new shelters and two maintenance kiosks. This scope will be similar for both the FY28 and FY30 projects.
There will be constraints to access the project sites as they are across the airfield, through the
PL2 area. A Construction Free Zone (CFZ) will be established around the project site.
Will be utilizing PDB w/ OT delivery method.
Magnitude: $75,000,000 to $100,000,000
PoP: 660 Calendar Days per project
Qualifications Based Selection: FY27
Award OT Construction Agreement: FY28
FY29 B-21 LOW OBSERVABLE (LO) FACILITY
FOR OFFICIAL USE ONLY
Construct an 8,875 square meter, high bay maintenance hangar with two (2) segregated aircraft bays
& administrative space. Construction includes reinforced concrete foundations, steel frame structure, metal roof, powered hangar doors, temperature & humidity control, filtration & ventilation, back-up power, and aircraft power.
There will be constraints to access the project site as it is on the airfield, inside the PL2 area. A
Construction Free Zone (CFZ) may or may not be established around the project site.
Will be utilizing CMAR w/ OT delivery method.
Magnitude: $145,000,000 to $165,000,000
PoP: 1,095 Calendar Days
Qualifications Based Selection: FY28
OT Construction Agreement: FY29
REMAINING B-21 PROGRAM PROJECTS
FY29 Reno General MX Docks (7 Ea) FSRM
FY29 Base Supply Warehouse (B139 Reno) FSRM
FY29 Composite Tool Kit MILCON
FY29 Comm & Operations Spt (B200) FSRM
FY30 AMU 1&2 (B33 Reno) FSRM
FY30 Phase Dock (2-Bay - Hgr 9 Reno) FSRM
FY31 Wash Rack (Hgr 27 Reno) FSRM
FY31 Fuel Cell Hangar (Hgr 1 Reno) FSRM
FY31 Aircraft Parts Store (B26 Reno) FSRM
INDUSTRY QUESTIONS AND FEEDBACK
FOR OFFICIAL USE ONLY
• How much time do you need between the Request for Qualifications (RFQ) and submission of the White Paper?
• Do you have any major concerns or reservations about participating in an OTA procurement environment versus traditional FAR contracts?
• What are your primary uncertainties regarding how USACE will evaluate an OTA procurement?
• What qualifications do you believe should be most important for USACE to prioritize during down-select?
• What level of project detail would be beneficial to share with contractors for CMAR w/ OT when preparing for the white paper submittal, where there are 35-100% design documents?
o All drawings and specs?
o Select drawings for general understanding (No detail sheets, no enlarged plans)?
o General scope summary?
• Are there any best practices or standard commercial practices to take into consideration in transitioning to OTAs?
FEEDBACK
FOR OFFICIAL USE ONLY
• INDUSTRY FEEDBACK
USACE will post this presentation and a questionnaire to the Webinar announcement following this Webinar.
• USACE POC FOR B-21 QUESTIONS/COMMENTS:
Angelique Dilmore – angelique.m.dilmore@usace.army.mil
Stephanie Kretzer – stephanie.r.kretzer@usace.army.mil
Contracting Special Programs/Projects Section
Kansas City District email: Angelique.M.Dilmore@usace.army.mil mailto:angelique.m.dilmore@usace.army.mil mailto:stephanie.r.kretzer@usace.army.mil mailto:Angelique.M.Dilmore@usace.army.mil
FOR OFFICIAL USE ONLY
CLOSING COMMENTS
AND QUESTIONS?
| Slide 1: WHITEMAN AIR FORCE Base USACE Industry Webinar 08 September 2026 |
| Slide 2: Agenda |
| Slide 3: Procurement integrity |
| Slide 4: OTHER TRANSACTION AUTHORITY (ota) |
| Slide 5: OTHER TRANSACTION AUTHORITY (ota) |
| Slide 6: OTHER TRANSACTION AUTHORITY (ota) |
| Slide 7: Whiteman & B-21 PROGRAM |
| Slide 8: Whiteman security |
| Slide 9: FY26 Whiteman Projects |
| Slide 10: FY27 B-21 Weapons Load Trainer (WLT) |
| Slide 11: FY27 B-21 Field training detachment (FTD) Fy28 B-21 Flight Simulator |
| Slide 12: FY27 Whiteman FSRM |
| Slide 13: FY28 & FY30 B-21 Environmental protection shelters (EPS) |
| Slide 14: FY29 B-21 LOW OBSERVABLE (lo) FACILITY |
| Slide 15: remaining B-21 program projects |
| Slide 16: Industry questions and feedback |
| Slide 17: feedback |