Industry Day Whiteman AFB B21 Presentation Slides 20250514.pdf
PDF 554 KB Posted
- Attached to
- Whiteman AFB B-21 Industry Event
- Solicitation number
- W912DQ25RA005
About this file
These are the presentation slides for the U.S. Army Corps of Engineers (USACE) Industry Webinar for the B-21 (Raider) Program at Whiteman Air Force Base, scheduled for 14 May 2025. The program involves 22 total projects, including 8 Military Construction (MILCON) and 14 Facility Sustainment, Restoration, and Modernization (FSRM) projects, with an estimated budget of approximately $600 million running through FY32. Two primary projects are highlighted: the Weapons Release System Storage (WRSS) and the Radio Frequency (RF) Hangar, both planned for Design-Bid-Build (DBB) procurement with Firm Fixed Price (FFP) contracts.
The WRSS project involves constructing an addition to building 5208 for a new Armament Storage Facility, with a project magnitude of $10-25 million and a 540-calendar day performance period. The RF Hangar project will construct a 57,532 square foot facility with classified and unclassified spaces, with a project magnitude of $25-100 million and a 900-calendar day performance period. Both projects are scheduled for advertisement in the 1st Quarter of FY26 and award in the 3rd Quarter of FY26. The draft evaluation factors include Performance Confidence, Management Approach, Technical Approach, and Price, with USACE seeking industry feedback on procurement details through David Miller, the Contracting Specialist for the Kansas City District.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Day Whiteman AFB B21 Questions 20250514.pdf | ||
| Industry Day Whiteman AFB B21 Attendees 20250514.pdf | ||
| Special notice.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B-21 (RAIDER) PROGRAM, WHITEMAN AIR FORCE BASE
USACE INDUSTRY WEBINAR
14 MAY 2025
Presented by:
Michael France, Contracting Officer
AGENDA
• Procurement Integrity
• Overview of B-21 Program
• Overview of the Weapons Release System Storage (WRSS)
• Procurement Specific Questions
• Overview of the Radio Frequency (RF) Hangar
• Procurement Specific Questions
• Closing and Questions
PROCUREMENT INTEGRITY
Procurement Integrity is maintained throughout the acquisition, including these early engagements. We protect correspondence and information that you decide to share with USACE.
We anticipate information exchanges to continue throughout the acquisition. Under the Procurement Integrity Act, the exchanges become formal when we move into the solicitation phase.
USACE is in listening mode. We need your help and feedback to develop a good RFP. Our Project Delivery Team will use your shared knowledge and information to help us with acquisition planning.
If you share proprietary or confidential information with us, please identify it so we can take steps to appropriately manage and protect the information.
To help us manage and keep your information confidential, I ask that you only contact the USACE Contract Specialist: David Miller at david.f.miller@usace.army.mil.
Please do not contact Whiteman AFB or USACE PMs for information
B-21 PROGRAM PLANNING AND DESIGN
FOR OFFICIAL USE ONLY
Whiteman Transitions from B-2 to B-21
Program Overview
• 22 Overall Projects
• 8 MILCON Projects
• 14 FSRM Projects
• Whiteman Civil Engineering plans on executing some of the smaller FSRM projects
• USACE will partner to ensure consistent program execution
• Approx $600M and rising
• Program Anticipated to go through FY32
Planning and Design
• Program has an Unrestricted AE MATOC for Planning, Design and Construction Phase
Services awarded in FY21
• Construction
• Mixture of Unrestricted/SB/8a Negotiated Contracts
• Most projects include Secure Areas to be constructed/renovated to ICD 705 standards
• Using lessons learned and consistency throughout B-21 Program across 3 MOBs
B-21 PROGRAM PLANNING AND DESIGN
FOR OFFICIAL USE ONLY
• NWK Current Projects
• FY26 WRSS
• SB
• FY26 RF Hangar
• Unrestricted
• Projects in Design
• FY27 Weapons Load Trainer (WLT)
• FY27 Field Training Detachment (FTD)
• FY27 Communications/Ops Overflow FSRM
WHITEMAN SECURITY
FOR OFFICIAL USE ONLY
Requirements:
• Must be a United States Citizen
• No Criminal Record
• Must have a REAL-ID; or
• Acceptable Alternate Identifications WITH REAL ID Compliance
Extension request Form.
Acceptable Alternate Identifications:
• Birth Certificate WITH Social Security Card
• Transportation Worker ID Card
• Veteran’s Health Card
• U.S or Foreign Passport/Passport Card “Not Expired”
WEAPONS RELEASE SYSTEM STORAGE (WRSS)
FOR OFFICIAL USE ONLY
Construct addition to the north side of building 5208 to accommodate a new Armament Storage Facility. The Addition will require modifications to, or additions to the water, sewer, electrical, natural gas, steam and communications systems.
Design-Bid-Build (DBB) Request for Proposals (RFP) that will result in a Firm Fixed Price (FFP) construction contract.
Magnitude: $10,000,000 to $25,000,000
POP: 540 Calendar Days
Advertise: 1st QTR FY26
Award: 3rd QTR FY26
RADIO FREQUENCY (RF) HANGAR
FOR OFFICIAL USE ONLY
Construct a Radio Frequency/Measurements Hangar Facility with one aircraft position and all associated back shops, material storage, and administrative and facility support spaces. The facility will consist of both unclassified and classified spaces for a total square footage of 5,345 square meter (57,532 square feet).
Magnitude: $25,000,000 to $100,000,000
POP: 900 Calendar Days
Advertise: 1st QTR FY26
Award: 3rd QTR FY26
Design-Bid-Build (DBB) Request for Proposals (RFP) that will result in a Firm Fixed Price (FFP) construction contract.
DRAFT EVALUATION FACTORS
FOR OFFICIAL USE ONLY
Factor 1 – Performance Confidence
• Past Performance (CPARS and / or Past Performance Questionnaires)
• Experience (Minimum of 3 Projects, Maximum of 5 Projects)
Factor 2 – Management Approach
• Management and Staffing
Factor 3 – Technical Approach
• Schedule
• Schedule Narrative
Factor 4 – Small Business Participation (Not required for the WRSS)
Factor 5 - Price
INDUSTRY QUESTIONS AND FEEDBACK LOOP
FOR OFFICIAL USE ONLY
• How much time do you need to submit the initial proposal based on a 100% design included in the solicitation, and why? 45 days?
• Is it realistic to ask for 3 to 5 projects completed as the prime contractor within the past 7-years?
• Are each project’s relevancy examples realistic and helpful? If not, what needs to be improved?
• What are reasonable goals for the small business participation factor (as a percent of subcontracted work)?
• Will the draft submission and evaluation criteria work as discriminators to help us award to a qualified best-value contractor? If not, what needs to be improved and why?
• What is a realistic amount of time to hold the FFP option prices?
• Do you have any concerns participating in these procurements?
• Do you plan on participating in these procurements?
• How can we make this procurement better?
FEEDBACK
FOR OFFICIAL USE ONLY
• INDUSTRY FEEDBACK
USACE will email additional information and questions to today’s participants.
• USACE POC FOR B-21 QUESTIONS/COMMENTS:
David Miller Contracting Specialist Kansas City District phone: 816-389-2258 email: david.f.miller@usace.army.mil mailto:david.f.miller@usace.army.mil
INDUSTRY QUESTIONS AND FEEDBACK
FOR OFFICIAL USE ONLY
CLOSING QUESTIONS
AND
COMMENTS?
| ���B-21 (RAIDER) PROGRAM, WHITEMAN AIR FORCE Base�USACE Industry Webinar ��14 May 2025� |
| Agenda |
| Procurement integrity |
| B-21 PROGRAM PLANNING and design |
| B-21 PROGRAM PLANNING and design |
| Whiteman security |
| Weapons release system storage (WRSS) |
| Radio frequency (RF) hangar |
| DRAFT EVALUATION FACTORS |
| Industry questions and feedback loop |
| feedback |
| Industry questions and feedback |