Core #1
Core #2
Core #3
US Army Corps of Engineers Pomme de Terre Lake Project, Hermitage, MO
Material removed from core was 4.5 Inch
Metal Deck below roof material
Core #1 Project Office
Material removed from core was 4.5 Inch
– No photo of core material placed back in hole from drill attachment
Core #2 Project Office
Metal Deck below roof material
Core #3 Project Office
Metal Deck below roof material
Material removed from core was 4.5 Inch – No photo of core material placed back in hole from drill attachment
Control Tower
Material removed from core was 1.5 Inch
– No photo of core material placed back in hole from drill attachment as it fell apart
Control Tower Roof Location
Location