This amendment modifies a solicitation for construction services to repair damages to the Union Township Levee in Missouri sustained during the 2019 flood events. The U.S. Army Corps of Engineers, Kansas City District is seeking a contractor to perform earthwork, filling, borrow activities, clearing, erosion and rutting repairs, levee surfacing, stone placement, drainage structure installation and rehabilitation, and turf establishment. Seeded areas will include wetland bottom, side slope, and other wetland mixtures. The amendment updates seeding specifications and provides additional details on repair locations and borrow sources. Offerors must acknowledge receipt of the amendment in their response.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
J
PAGE OF PAGES
1 4
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
4-Jun-2020
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY CODE W912DQ 7. ADMINISTERED BY (If other than item 6) CODE
USACE, KANSAS CITY +
FEDERAL BLDG, CT-C
601 E 12TH ST RM 647
KANSAS CITY MO 64106-2896
See Item 6
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X
9A. AMENDMENT OF SOLICITATION NO.
W912DQ20B1053
X 9B. DATED (SEE ITEM 11)
12-May-2020
10A. MOD. OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one ofthe following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegramor letter, provided each telegramor letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT S/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to update the seeding specifications. Deleted text is shown with strikethrough. Added text is shown with underline.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
TEL: EMAIL:
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
29-May-2020
EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
30-105-04 STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
W912DQ20B1053
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added:
SPECIFICATIONS
Counties:
NOTE: Deleted text is shown with strikethrough. Added text is shown with underline.
1. SPECIFICATIONS:
a. Section 32 92 19 Paragraph No 2.1.4 Seed Mixture by Weight
Planting Season Variety Percent (by Weight)
All Permanent Season K-31 Fescue
Domestic Rye Grass
Smooth Brome
Temporary Seeding Sterile Wheat or Oats 100
b. Section 32 92 19 Paragraph No 2.1.5 Wetland Seed Mixture by Pounds per Acre
Planting Season Variety Pounds/Acre
Wetland Bottoms Big Bluestem
Virginia Wildrye
Switchgrass
Prairie Cordgrass
Fox Sedge
Bur Reed or Sweet Flag or
Common Arrowhead
Water Plantain
0.5
0.01
1.5
Wetland Side Slopes Rice Cutgrass
Prairie Cordgrass
Fowl Manna Grass
Fox Sedge
Joe Pye Weed
Swamp Milkweed
Common Rush
Green Bullrush
Common Oats
0.1
0.2
0.25
0.01
0.01
Other Wetland (Haul routes, berms, etc)
Swamp Milkweed
Sweet Coneflower
Great Blue Lobelia
New England Aster
Little Bluestem
Kanlow Switchgrass
Rice Cutgrass
Common Oats
0.25
0.05
0.3
1.5
1.75
a. Section 32 92 19 Paragraph No 3.2.2.1 Broadcast and Drop Seeding
Permanent seed Seed must be uniformly broadcast at the rate of 90 pounds pure live seed per acre. Wetland Bottoms seed must be uniformly broadcast at the rate of 8.01 pounds pure live seed per acre, Wetland Side Slopes seed must be uniformly broadcast at the rate of 34.57 pounds pure live seed per acre, and Other Wetland (Haul routes, berms, etc) see must be uniformly broadcast at the rate of 49.85 pounds pure live seed per acre. Use broadcast or drop seeders. Sow one-half the seed in one direction, and sow remainder at right angles to the first sowing. Cover seed uniformly to a maximum depth of
1/4 inch in clay soils and 1/2 inch in sandy soils by means of spike-tooth harrow, cultipacker, raking or other approved devices.
b. Section 32 92 19 Paragraph No 3.2.2.1 Drill Seeding
Permanent seed Seed must be drilled at the rate of 90 pounds pure live seed per acre. Use grass seed drills. Drill seed uniformly to average depth of 1/2 inch.
c. Section 35 41 00 Paragraph No 3.11.3 Intermittent Crown & Embankment Erosion Station 33+50 to 58+80 and Breach &
Landside Scour Fill Station 58+80 to 60+60
At station 33+50 to 58+80 the contractor shall repair/restore the levee embankment to same cross section as undamaged sections within repair reach per COR direction (approx. 10' crown with 1' vertical on 3' horizontal slopes). (300 CY Fill &
2.6 AC Seeding/Mulching)
At station 58+80 to 60+60 the contractor shall repair/restore the levee embankment within breach repair reach to same cross section as undamaged end sections per COR direction (approx. 10' crown with 1' vertical on 3' horizontal slopes). In addition, the contractor shall fill all associated landside scour at breach area to the surrounding natural ground contours. The height of levee embankment within the breach repair shall be increased by 5% tapering to no increase in height at the toe of the embankment. The 5% height requirement cannot be exceeded by greater than two tenths of a foot (0.20'). The contractor will be required to degrade embankment height should this limitation be exceeded, at no cost to the government. (1,900 CY
Fill & 0.2 AC Seeding/Mulching levee embankment only)
Borrow for repairs is cross-hatched area generally positioned and is as shown on Site Map B-2. Some minor clearing/grubbing of timber less-than-3-inches at diameter breast height (DBH), and removal of heavy herbaceous vegetation within borrow area is to be expected. Standing timber larger than 3" DBH is to be avoided. Borrow area perimeter side slopes should not be steeper than 1' vertical on 10' horizontal and should have variability with areas of lower slope. Borrow surface to be left in a rough finish grade, with depth variations, with a maximum depth of 2-feet. At conclusion of borrowing activities, if locations within borrow area contain an exposed sand layer which would prevent hydrology retention for wetland establishment, the area(s) shall be lined using suitable clay material. No borrow shall be obtained within 250-feet of the landside levee toe line of the existing levee, or within 100-feet of COE mitigation land boundary line. Contractor to utilize borrow route as shown on Site Map B-2, or other haul route as approved by COR. Upon completion of borrow activity the contractor shall seed and mulch all disturbed areas within borrow area limits with wetland seed mixture. The bottom flats of borrow areas shall be seeded with Wetland Bottom seed mixture. All side slopes of borrow area shall be seeded with Wetland Side Slopes seed mixture. All other disturbed areas of borrow area shall be seeded with Other Wetland seed mixture.
a. Section 35 41 00 Paragraph No 3.11.4 Intermittent Crown & Embankment Erosion Station 69+20 to 101+95
The contractor shall repair/restore the levee embankment to same cross section as undamaged sections within repair reach per COR direction (approx. 10' crown with 1' vertical on 3' horizontal slopes). (400 CY Fill & 4.1 AC Seeding/Mulching)
Borrow for repairs shall be obtained from borrow area 1 and is cross-hatched area generally positioned as shown on Site
Map B-3. Some minor clearing/grubbing of timber less-than-3-inches at diameter breast height (DBH), and removal of heavy herbaceous vegetation within borrow area is to be expected. Standing timber larger than 3" DBH is to be avoided.
Borrow area perimeter side slopes should not be steeper than 1' vertical on 10' horizontal and should have variability with areas of lower slope. Borrow surface to be left in a rough finish grade, with depth variations, with a maximum depth of 1-foot. At conclusion of borrowing activities, if locations within borrow area contain an exposed sand layer which would prevent hydrology retention for wetland establishment, the area(s) shall be lined using suitable clay material. No borrow shall be obtained within 250-feet of the landside levee toe line of the existing levee or within100-feet of COE mitigation land boundary line. Upon completion of borrow activity the contractor shall seed and mulch all disturbed areas within borrow area limits with wetland seed mixture.
The bottom flats of borrow areas shall be seeded with Wetland Bottom seed mixture. All side slopes of borrow area shall be seeded with Wetland Side Slopes seed mixture. All other disturbed areas of borrow area shall be seeded with Other
Wetland seed mixture.
b. Section 35 41 00 Paragraph No 3.11.5 Breach & Landside Scour Fill Station 101+95 to 103+80
The contractor shall repair/restore the levee embankment within breach repair reach to same cross section as undamaged end sections per COR direction (approx. 10' crown with 1' vertical on 3' horizontal slopes). In addition, the contractor shall fill all associated landside scour at breach area to the surrounding natural ground contours. See Drawing C-1. The height of levee embankment within the breach repair shall be increased by 5% tapering to no increase in height at the toe of the embankment. The 5% height requirement cannot be exceeded by greater than two tenths of a foot (0.20'). The contractor will be required to degrade embankment height should this limitation be exceeded, at no cost to the government. (9,700 CY
Fill & 0.3 AC Seeding/Mulching levee embankment only)
Random borrow for breach/landside scour fill repair shall be obtained from borrow area 3 and is cross-hatched area generally positioned as shown on Site Map B-3, COR to identify/flag limits. Borrow consists of sand deposition materials
(6" to 30" in depth), and shall not be removed below the surrounding agricultural lands found at perimeter limits of designated borrow area and removed so as to not retain/pond water. See Drawing C-1 for levee random fill zone.
Impervious borrow for repairs shall be obtained from borrow area 2 and is cross-hatched area generally positioned as shown on Site Map B-3. Some minor clearing/grubbing of timber less-than-3-inches at diameter breast height (DBH), and removal of heavy herbaceous vegetation within borrow area is to be expected. Standing timber larger than 3" DBH is to be avoided.
Borrow area perimeter side slopes should not be steeper than 1' vertical on 10' horizontal and should have variability with areas of lower slope. Borrow surface to be left in a rough finish grade, with depth variations, with a maximum depth of 3-feet. At conclusion of borrowing activities, if locations within borrow area contain an exposed sand layer which would prevent hydrology retention for wetland establishment, the area(s) shall be lined using suitable clay material. No borrow shall be obtained within 250-feet of the landside levee toe line of the existing levee. Upon completion of borrow activity the contractor shall seed all disturbed areas within borrow area limits with wetland seed mixture. The bottom flats of borrow areas shall be seeded with Wetland Bottom seed mixture. All side slopes of borrow area shall be seeded with
Wetland Side Slopes seed mixture. All other disturbed areas of borrow area shall be seeded with Other Wetland seed mixture.
2. DRAWINGS: No change.
3. Offerors are required to acknowledge receipt of this amendment on the Bidding Form in the space provided. Failure to acknowledge all amendments may cause rejection of the proposal.
4. All other terms and conditions remain unchanged and in full force.
(End of Summary of Changes)