| 1. | Will the COE be providing the AB-3 for the Access Roads? No, The construction contractor is responsible for the material, means and methods. |
| 2. | Will the COE be providing the AB-3 for the 100’ x 100’ Pads? No, The construction contractor is responsible for the material, means and methods. |
| 3. | Please clarify that 2 Access Roads will be required for the Big Tarkio Location? The construction contractor is responsible for determining his/her means and methods to place the material at it final destination. |
| 4. | Please clarify that 2 100’ x 100’ Pads will be required for the Big Tarkio Location? The Construction contractor is responsible for determining his/her means and methods to place the material at it final destination. |
| 5. | Will the 100’ x 100’ Pads be located adjacent to the Scour Locations? The construction contractor is responsible for determining his/her means and methods to place the material at it final destination including but not limited to the location of the work pads and access roads |
| 6. | If Access Road Maintenance and/or 100’ x 100’ Pads require Additional AB-3 will the COE be providing that material? Maintenance of access roads and work pads are the responsibility of the construction contractor. |
| 7. | Will the Contractor be paid for Placing any Additional AB-3 on the Access Roads and/or 100’ x 100’ Pads? Choice of access road material is the construction contractor's responsibility based on his/her means and methods. The work pads must accommodate highway truck deliveries of rock. |
| 8. | What is the planned delivery rate for the Aggregate? Tons/Hour and Tons/Day? The planned delivery rate for the aggregate is 7,500 tons a day per site, 22,500 a day total |
| 9. | Is the solicitation restricted to the 6 small businesses listed in the J&A document? No, any responsible small business that meets the Local Area set aside requirements may submit a Bid |